Meeting Watch Section

Late-Night Bitter Politics Set Stage for May 6

The Ann Arbor city council meeting that started on Monday evening, April 15, 2013 did not end until after 3 a.m. the following day. This was due in part to a stream of about 100 citizens who took the podium for general public commentary and two significant public hearings. The three-minute allocation of time per speaker translated into about five hours of public speaking time.

Mayor John Hieftje

Mayor John Hieftje at the April 15 Ann Arbor city council meeting. (Photos by the writer.)

Conversation amongst audience members at the meeting – as well as subsequently in the community – described the effort as a “citizens filibuster.” The result of all the commentary: Two significant items on the agenda were postponed until the council’s May 6 meeting.

One of those items was the site plan approval for 413 E. Huron. Postponement of a decision on that project was lumped in with the general motion to postpone all remaining action items on the agenda until May 6. It was not necessarily expected that the council would postpone the 413 E. Huron site plan that evening, even if it was hoped by opponents that councilmembers would put off the decision – for a third time.

But there was a reasonable expectation that another significant item would be postponed – the council’s final action on a proposed revision to the city ordinance governing the Ann Arbor Downtown Development Authority. It was during the often acrimonious debate on that decision that the council ultimately opted to postpone all of its remaining action items until May 6.

The acrimony stemmed in part from the fact that the stated intention of Stephen Kunselman (Ward 3) at the start of the meeting was to postpone a final decision – and that was the expected outcome. The fact that this expected outcome was called into question heightened the tension in an already emotional debate. The tension was heightened by the fact that deviation from the anticipated postponement was made possible mainly by the absence of two councilmembers – Marcia Higgins (Ward 4) and Sumi Kailasapathy (Ward 1).

By the time the council reached the DDA ordinance on its agenda, the hour was approaching 2 a.m. And by then Higgins and Kailasapathy had needed to leave the council meeting. Both of them had supported the ordinance changes in the 7-3 vote taken at the council’s April 1, 2013 meeting. But for the final reading on April 15, neither of them were at the table when the debate on the DDA ordinance began.

Kailasapathy described herself to The Chronicle as on the verge of physical exhaustion when she left – having had little sleep over the several days leading up to the meeting. She earns her livelihood as a certified public accountant, and tax season is a time of peak workload.

So apparently recognizing that the absence of Kailasapathy and Higgins would mean defeat for the ordinance change – if it were voted up or down, instead of being postponed – mayor John Hieftje led an effort to force an up-or-down vote on the issue. And councilmembers who were willing to put off the issue were not unified in their view about the parliamentary procedure to use to achieve that delay. So the council voted on two different options – postponing until a date certain (June 17) or tabling the issue. Sabra Briere (Ward 1) provided a crucial vote against postponement, but voted in favor of tabling.

Kunselman argued for the postponement by pointing out that because the sequence of the roll-call vote that evening allowed him to vote last, he could simply assess how the tally stood, and vote accordingly with the prevailing side. That would give him the right to bring back the vote for reconsideration at the council’s subsequent meeting. But Kunselman’s argument was not persuasive to a six-vote majority.

Without a six-vote majority in favor of either tabling or postponing, the council was left to deliberate on the actual ordinance amendments. As some attempted amendments failed – clearly due to the dynamic that had resulted from the absence of two councilmembers – Chuck Warpehoski (Ward 5) eventually proposed adjourning the meeting until the following Monday, when the meeting could continue. However, after a brief recess it was decided that the council would simply postpone all remaining voting items until its May 6 meeting, and put an end to the April 15 meeting.

After approving the motion to postpone the action items, councilmembers ticked through the remaining “housekeeping” items on the agenda, which largely included various reports and communications. Of those, one highlight worth noting was the nomination by Hieftje of Eric Mahler to replace David Nacht on the board of the Ann Arbor Transportation Authority.

The public commentary at the April 15 meeting exceeds The Chronicle’s capacity to report in its customary way. Still, some accounting of the meeting is important for the archives.

This report provides: (1) a summary of votes taken; and (2) a summary of actions that will now appear on the May 6 agenda as a result of the April 15 postponement. In addition, this report begins with details of the deliberations on the proposed DDA ordinance revisions. [Full Story]

AAPS Begins Superintendent Search

Ann Arbor Public Schools board of education study session (April 17, 2013) Editor’s note: Since this study session, the board has held an additional study session and a regular meeting, both on April 24. The Chronicle anticipates offering coverage of those meetings as well.

Ann Arbor Public School superintendent Patricia Green

Ann Arbor Public School superintendent Patricia Green

The board is now in the first stages of it has determined to be a “fast track” superintendent search. That’s because Ann Arbor Public Schools superintendent Patricia Green has turned in her resignation, after a little less than two years on the job. Her resignation takes effect in mid-July. In a brief letter to AAPS staff and families in the school system, Green said she intends to retire after 43 years in the profession. [.pdf of Green's letter]

The bulk of the board’s April 17 study session was spent discussing the first steps of a superintendent search. Led by board president Deb Mexicotte, the trustees discussed topics ranging from retaining a search firm, determining the superintendent profile, creating the search timeline, gathering community input, and naming an interim superintendent.

Also at the study session, Mexicotte also put out another call for trustees to indicate their interests for standing committee membership, as well as interest in chairing a committee. Appointments were to be made by the next regular meeting, which took place on April 24.

The dates and locations of the AAPS community budget forums were also announced. At the forums, the administration will review the budget for the 2013-14 school year.

The board also heard public commentary regarding potential budget cuts and the superintendent search. [Full Story]

Property Values Up, Budget Decisions Loom

Washtenaw County board of commissioners meeting (April 17, 2013): Major budget issues were the focus of the April 17 county board meeting, including news that tax revenues in 2013 will be higher than anticipated.

Raman Patel, Leila Bauer, Washtenaw County board of commissioners, The Ann Arbor Chronicle

From left: Raman Patel, Washtenaw County’s equalization director, greets Leila Bauer, chief deputy treasurer who is retiring after 41 years with the county. (Photos by the writer.)

After several years of reporting declining tax revenues, Raman Patel – the county’s equalization director – gave commissioners a report showing stronger signs of economic recovery, reflected in a 1.68% increase in taxable value. That translates into an estimated $2.327 million more in property tax revenues for county government than had been budgeted for 2013. [.pdf of Patel's presentation]

Also related to the budget, commissioners gave initial approval to a four-year budget planning cycle, a change from the current two-year cycle that’s been in place since 1994. Voting against the item was Ronnie Peterson (D-District 6). He and other commissioners expressed a range of concerns, including the fact that commissioners are elected every two years and therefore might not be able to contribute adequately to setting budget priorities. Although Peterson remained unconvinced, several commissioners observed that the annual budget affirmation process acted as a fail-safe, allowing the board to make adjustments based on changing priorities.

Another item that could have a dramatic impact on the county’s budget was only briefly mentioned: A proposal to issue up to $350 million in bonds to fully fund the county’s pension and retiree healthcare plans. It would be by far the largest bond issuance in the county’s history. County administrator Verna McDaniel plans to make a formal presentation about the proposal at the board’s May 2 working session. She distributed materials on April 17 to help commissioners prep for that meeting. [.pdf of bond proposal handout]

Commissioners also took a final vote officially to dissolve a countywide public transit authority known as the Washtenaw Ride. There was no discussion, but Conan Smith (D-District 9) – a vocal advocate for public transit – cast the sole vote against the resolution.

Other action handled by the board included a federal weatherization grant, a public hearing for the Urban County strategic plan, and resolutions honoring county employees and residents. Among them was Leila Bauer, the county’s chief deputy treasurer who is retiring after 41 years with the county. She received a standing ovation from the board. [Full Story]

Public Art Commission Seeks Student Input

Ann Arbor public art commission meeting (March 27, 2013): Public art commissioners hope to involve more students in their work – but no formal mechanism is yet in place to make that happen.

Connie Brown, John Kotarski, Ann Arbor public art commission, The Ann Arbor Chronicle

Ann Arbor public art commissioners Connie Brown and John Kotarski at AAPAC’s March 27, 2013 meeting. (Photos by the writer.)

At AAPAC’s most recent meeting, John Kotarski proposed adding three students to the nine-member commission as voting members. He suggested that the student commissioners be selected by: (1) the Ann Arbor Public Schools board of education; (2) the dean of the University of Michigan School of Art & Design; and (3) the Arts at Michigan program. Deb Mexicotte, president of the AAPS board, is also program coordinator for Arts at Michigan.

Ultimately, commissioners passed a resolution on a 5-1 vote asking that the city council consider adding students to the commission. Marsha Chamberlin dissented, saying she supported the concept of student involvement but didn’t like this approach. She’d rather handle it informally, perhaps by including students in the task forces that are set up for each project.

Chamberlin also noted that any change in AAPAC’s composition would require a revision to the city’s public art ordinance.

The city council committee that’s currently undertaking dramatic revisions to the public art ordinance has nearly completed its work, with plans to present recommendations to the full council on May 6. The recommendations include eliminating the Percent for Art funding mechanism and the concept of “pooled” funds from capital projects. Instead, the city council will designate specific capital projects to be “enhanced” with extra funding allocated for public art or architectural features, based on recommendations by AAPAC. [.pdf of draft ordinance revisions] [.pdf of most recent memo to city council regarding draft recommendations]

This Chronicle report includes a summary of the council committee’s April 18 meeting, which is probably the last one prior to presenting the recommendations – likely on May 6. The committee is suggesting that the council take a final vote on June 3, after soliciting public input through A2 Open City Hall.

In other action during the March 27 meeting, AAPAC approved its annual art plan. This year, because of uncertainty regarding the program’s future and a current moratorium on spending, the plan sets general goals rather than proposing new projects. Those goals are: (1) the creation of public art in more areas of the city and a commitment to balance the number of artworks throughout the city and its neighborhoods; (2) a focus on high use and visibility as locations for public art; and (3) an emphasis on putting public art in underserved neighborhoods.

AAPAC also selected Josh Wiener, an artist from Denver, to work with landscapers and incorporate public art into a new rain garden at the corner of Kingsley and First. The $27,000 project was one of several for which funding had already been approved, prior to the council’s decision to temporarily halt spending on public art.

Commissioners discussed a range of other ongoing projects, including public art at the East Stadium bridge, Argo Cascades and the Justice Center lobby. A project that doesn’t include city funding is the Detroit Institute of Arts’ Inside|Out program. Installation of that artwork in Ann Arbor took place two days after AAPAC’s March 27 meeting. Framed replicas of paintings from the DIA collection were mounted at several locations in the downtown area, and free docent walking tours will be offered on Saturdays and Sundays, starting on April 27. The tours will leave from the Ann Arbor Hands-On Museum every half-hour between noon and 3 p.m.

Looking ahead, Chamberlin reminded commissioners that it’s time to solicit nominations for the annual Golden Paintbrush awards, which recognize local contributions to public art. The award winners are selected by AAPAC, with a presentation at an Ann Arbor city council meeting in June.

March 27 was the first meeting for AAPAC’s two new commissioners, Ashlee Arder and Nick Zagar. Arder, who works for ArtServe Michigan, took action during the meeting to set up a Twitter account for the commission: @AAPublicArt. [Full Story]

AirRide Talks OK’d, Ypsilanti to Join AATA?

Ann Arbor Transportation Authority board meeting (April 18, 2013): Board member David Nacht’s final regular meeting after 10 years of service included action on a significant project he’d worked on during that time: bus service between downtown Ann Arbor and Detroit Metropolitan Airport.

AATA board member David Nacht

AATA board member David Nacht. (Photos by the writer.)

To provide the AirRide service, which was launched a year ago, the AATA is currently in negotiations with Michigan Flyer to revise terms of the second year of the contract. While the first year called for the AATA to pay Michigan Flyer an amount not to exceed $700,000 for the hourly service, the ridership – given the structure of the revenue-sharing deal – has resulted in a far lower cost.

So the board passed a resolution at its April 18 meeting reflecting the current status of negotiations, which are pointing toward a not-to-exceed amount of $300,000 for the contract’s second year. The board’s action rescinded a resolution it had passed at the previous month’s meeting, in favor of one that reflected the current status of negotiations between AATA and Michigan Flyer.

Besides the resolution on AirRide, the only other item requiring a vote was one honoring David Nacht’s decade of service on the board – which covered two full five-year terms. During his brief remarks, Nacht thanked the riders of the AATA’s service, the bus drivers and the mechanics. He also thanked his family – his two sons attended the meeting. In addition, Nacht thanked the Ann Arbor mayor and city council, which make the appointments to the AATA board. At the council’s April 15 meeting, mayor John Hieftje had announced the nomination of Eric Mahler, currently a city planning commissioner, to replace Nacht.

Discussion on non-voting items included the future of public transportation in the broader region – in two significant ways.

First, board members lamented the fact that no U.S. company, and more specifically no Michigan company, had bid on the AATA’s request for proposals to replace battery kits for its hybrid electric buses. But board sentiment was that a larger purchasing consortium for such kits might eventually be achieved through the newly-created southeast Michigan regional transit authority (RTA) – which includes the transit agencies in Washtenaw, Wayne, Macomb and Oakland Counties. And that larger consortium might make it worth the while of a Michigan company that’s a part of the state’s nascent battery industry to invest in the capability to produce bus battery kits.

Second, the board was paid a visit by Ypsilanti city councilmember Pete Murdock, who alerted the board to the likelihood that the city of Ypsilanti would make a formal request to join the AATA. The request would need approval from the AATA board and almost certainly the Ann Arbor city council, and could have implications for board membership. The goal of such a move would be to provide a more stable financial foundation for Ypsilanti bus service.

The city of Ypsilanti itself already levies its constitutional cap of 20 mills of property tax. If the AATA were to ask voters of member jurisdictions to approve a millage – an authority the AATA does not currently exercise – that additional amount would not count against Ypsilanti’s constitutional cap. [Full Story]

Smaller Deficit to Inform AAPS Budget Talks

Ann Arbor Public Schools board of education regular meeting  (April 10, 2013): Editor’s note: Since this board meeting took place, the board of trustees has held a study session – on April 17. And several community meetings on the budget have taken place. The Chronicle anticipates being able to provide coverage of those events as well.

 Wines Elementary 5th grade chorus

Wines Elementary 5th grade chorus performed during the board’s April 10, 2013 meeting. (Photos by the writer.)

At the meeting, the board of trustees was presented with a revenue projection report that now forecasts just a $8.67 million deficit for the 2013-14 school year, compared to the previously-projected $17-20 million shortfall.

The trustees were pleased that the numbers were “less bad” than was initially projected, but they acknowledged that the remaining $8.67 million was still a daunting amount to cut. Concessions totaling $3.4 million have already been made by the Ann Arbor Education Association (AAEA).

The board heard extensive public commentary on several possible budget cuts.

The board also finalized policy changes that had been brought forward by president Deb Mexicotte. The policy changes include placing time limits on board meetings, imposing time limits for item discussions, and changing the board’s committee structure.

After some discussion, the trustees settled on their previous standing committee structure of a planning committee and a performance committee. They also voted to add a governance and an executive committee.

Additionally, the trustees approved a purchase request for software licenses in the amount of $232,486. They also heard a first briefing of the spring grant awards. [Full Story]

AADL Weighs Small Tax Hike in FY 2014

Ann Arbor District Library board meeting (April 15, 2013): Two main topics were discussed at the April AADL board meeting: The draft budget for fiscal 2013-14, and a proposal for an ice-skating rink on the city-owned Library Lane parking lot, adjacent to the downtown library on South Fifth Avenue.

Margaret Leary, Ed Surovell, Ann Arbor District Library, The Ann Arbor Chronicle

From left: Ann Arbor District Library trustees Margaret Leary and Ed Surovell. (Photos by the writer.)

The $12.475 million proposed budget calls for levying the AADL’s tax at a rate of 1.575-mill – a small increase from the current 1.55-mill rate, but still below the amount that AADL is authorized to levy. [.pdf of draft 2013-14 budget]

Ken Nieman – AADL’s associate director of finance, HR and operations – told the board that the budget includes a 3% increase in the merit raise pool for full-time employees and an increase in hourly base rates for part-time workers. The administration wanted to make sure that the library’s lower-paying jobs start at more than $9 per hour. “It will help us attract people and hopefully also keep people as we compete against other businesses out there,” he said.

The board is expected to vote on the budget and set the millage rate on May 6, but several trustees made comments about the draft budget during the April 15 meeting. Ed Surovell argued strongly against even a small tax increase, and said he wouldn’t be voting for a budget that includes any increase to the millage. It’s estimated that the additional 0.025 mills would increase the amount of the library tax for homeowners by $2.50 per year, for a home that has a taxable value of $100,000. The increase is estimated to result in an additional $185,000 in tax revenues, compared to a 1.55-mill rate.

The April 15 meeting also included a presentation by Stewart Gordon and Alan Haber, who are advocating to put a temporary, artificial ice-skating rink at the northwest corner of the Library Lane parking lot. They asked the board to designate a liaison from the library, to facilitate communications as the project unfolds – they hope to construct and open it by Oct. 15. Several commissioners board members expressed skepticism about the proposal, stressing concerns over financing and security issues.

The board also heard from five people during public commentary. Topics included concerns over the hiring of Allerton-Hill Consulting, and thanks for support the library’s support of the ArborWiki and Old News projects. [Full Story]

County Preps to Buy More Natural Areas

Washtenaw County parks and recreation commission meeting (April 9, 2013): The April meeting, which director Bob Tetens forecast would be “the long-promised very short meeting between our busy seasons,” saw WCPARC take the first step to acquire more properties in two locations for the county’s natural areas preservation program (NAPP). The group also heard a report from the Legacy Land Conservancy about a second round of farmland preservation through a NAPP program that the conservancy helps administer.

Fox Science Preserve, Washtenaw County parks and recreation commission, natural areas preservation program, The Ann Arbor Chronicle

The entrance to Fox Science Preserve in Scio Township. An additional four acres might be added to the county preserve, which is frequently used for environmental education and field study. (Photos by the writer.)

The first proposed acquisition for NAPP was the four-acre Jarskey property in Scio Township, which would become part of the Fox Science Preserve. That preserve lies east of Peters Road and north of Miller. Tom Freeman, retired deputy director of WCPARC and consultant on NAPP matters, briefed commissioners on the proposal. He highlighted two ponds on the property, and the popularity of the former gravel pit for educational purposes. Commissioners ultimately authorized preparation of a purchase offer at $14,285 an acre – or a total of $57,140.

The other NAPP proposal was for four wooded parcels totaling about 18 acres in Pittsfield Township, on the north side of Michigan Avenue roughly across from the Pittsfield Township offices. The value of this property, according to Freeman, is in the quality of the woods and the adjacency to the 535-acre Pittsfield Preserve. Commissioners authorized preparation of purchase offers of $390,000 for two of the properties, and $150,000 for the two other parcels – a total of $540,000.

Also at the April 9 meeting, Robin Burke – land protection coordinator for the Legacy Land Conservancy – briefed commissioners on the process used by the agricultural lands preservation advisory committee (ALPAC) to prioritize possible farmland preservation through the purchase of development rights. There were 72 applications for consideration, totaling 6,500 acres. This is the second round of potential deals that the county is weighing. The initial round was closed in March of 2013, protecting a total of 206 areas of farmland in the Bailo Family Partnership and Trust.

The commission also received reports on its finances, use of its facilities, and ongoing maintenance and improvement of WCPARC buildings and land. [Full Story]

Deliberations on DDA Pave Way for Final Vote

Ann Arbor city council meeting (April 1, 2013): The council’s first meeting in April featured some progress on items that have appeared repeatedly on its agenda in the last several weeks.

From left: Jane Lumm (Ward 2), assistant city attorney Mary Fales and Stephen Kunselman (Ward 3).

From left: Jane Lumm (Ward 2), assistant city attorney Mary Fales and Stephen Kunselman (Ward 3). (Photos by the writer.)

After two postponements, the council gave initial approval to a set of changes to the ordinance that establishes the Ann Arbor Downtown Development Authority (DDA). The changes can be divided into those that affect board composition and those that relate to the computation of the DDA’s tax increment finance (TIF) capture.

The tax calculations have implications of roughly $1 million a year for the DDA and the taxing jurisdictions whose taxes are captured by the DDA. Those taxing jurisdictions include the city of Ann Arbor, Washtenaw County, Washtenaw Community College and the Ann Arbor District Library. The vote was 7-3, as mayor John Hieftje, Margie Teall (Ward 4) and Chuck Warpehoski (Ward 5) voted no. Christopher Taylor (Ward 3) was absent. The final vote will likely come at the council’s April 15 meeting. Councilmembers are not obligated to vote the same way the second time around.

The council also wrapped up an issue that has appeared on its agenda for several meetings. At its March 18 meeting, the council had finally decided not to enact a moratorium on site plan applications in D1 (downtown core) zoning districts. Instead, the council had directed the planning commission to conduct a review of D1 zoning. But councilmembers had left open the question of the exact scope of work and the timeframe for its completion by planning commissioners. At the April 1 meeting, the council allowed the commission six months, until Oct. 1, to review the following: the appropriateness of D1 zoning on the north side of Huron Street between Division and South State and the south side of William Street between South Main and Fourth Avenue; the residential premiums; the zoning for the University of Michigan Credit Union parking lot.

Other business was further delayed by the council. At the developer’s request, the council postponed for a second time the 413 E. Huron project, a proposed 14-story, 216-apartment building at the northeast corner of Huron and Division streets. That project will come back before the council at its April 15 meeting. A new public hearing on the 413 E. Huron site plan application was started on April 1 and will continue on April 15.

The council also postponed a second and final vote on changes to the city’s sign ordinance. The changes would prohibit any new billboards, and allow only a limited range of digital signs. That won’t come back before the council until May 6. Several people addressed the council during the public hearing. All of them worked for Adams Outdoor Advertising, and spoke in opposition to the changes. Because of the postponement, the council extended a moratorium on digital sign applications, which has now been in place for a year.

The council also extended a moratorium on spending of monies that have been set aside under the city’s Percent for Art ordinance. A revision to that ordinance, which would likely eliminate the public art set-aside but still allow for aesthetic elements to be built into a project, is expected to be brought forward in the next few weeks. The public art ordinance revisions are being crafted by a council committee that was tasked with that responsibility in December of 2012.

At its April 1 meeting, the council also approved contracts for renovations at the Gallup Park canoe livery, and the Argo and Geddes dams. In addition, the council approved a lease for additional parking in connection with the Argo Cascades.

Other business at the meeting included council approval of the notice to issue bonds for the city’s drinking water system. The council also authorized contracts in connection with street reconstruction and sidewalk repair work for the 2013 season. [Full Story]

County Board Briefed on Audit, Financials

Washtenaw County board of commissioners meeting (April 3, 2013): With a third of the board absent, commissioners were briefed on the county’s 2012 audit – with a look toward changes that will impact future financial statements. The audit was clean.

Mark Kettner, Carla Sledge, Kelly Belknap, Pete Collinson, Rehmann, Washtenaw County board of commissioners, The Ann Arbor Chronicle

From left: Mark Kettner of the accounting firm Rehmann; Carla Sledge, Wayne County’s chief financial officer; Kelly Belknap, Washtenaw County’s finance director; and Pete Collinson, accounting manager for Washtenaw County. (Photos by the writer.)

The county’s finance staff, along with the auditor, Mark Kettner of Rehmann, highlighted several points, including a relatively dramatic increase in the general fund balance over the last few years – from $9.7 million in 2009 to $16.8 million at the end of 2012. Kettner also explained upcoming accounting changes that will require unfunded liabilities from the county’s pension and retirement healthcare plans – now totaling nearly $250 million – to be recorded in a different way, with more disclosure.

The new accounting changes – required by the Governmental Accounting Standards Board (GASB) – won’t begin until 2015, but commissioner Dan Smith (R-District 2) wondered whether the county could implement the changes sooner. It might be possible, Kettner replied, but “I don’t know why you’d want to do it.” He suggested that the board hold a working session to go over the upcoming changes in more detail.

Kettner also pointed out that the changes will affect government entities in different ways. For example, it’s likely that there will be more impact on the city of Ann Arbor, because of how its many “enterprise” funds might be affected and the implications that would have on outstanding bonds. At minimum, the changes will mean more work for finance staff.

Also at the April 3 meeting, commissioners voted to add 39 new jobs in the community support and treatment service (CSTS) department, which provides mental health and substance abuse services to county residents. The work is primarily funded by the Washtenaw Community Health Organization, a partnership between the county and the University of Michigan Health System. Most of the new jobs are union positions. Dan Smith expressed concern about adding to the county’s payroll, but supported the resolution along with other commissioners in a unanimous vote.

The board also took an initial vote to dissolve The Washtenaw Ride. That Act 196 authority is a remnant of a failed attempt to create a countywide transit system last year. Efforts to expand the current reach of the Ann Arbor Transportation Authority are still underway, but don’t require the structure that was put in place under Act 196.

The topic of public transportation was raised later in the meeting as well, as Ronnie Peterson (D-District 6) asked about the county’s role in the southeast regional transit authority (RTA). The RTA was formed by the state legislature last year to coordinate regional transit in the city of Detroit and counties of Wayne, Macomb, Oakland and Washtenaw. There was not uniform support for Washtenaw County to be part of this effort, and it’s not yet clear what the impact will be on the AATA.

In other discussion, Yousef Rabhi (D-District 8) highlighted a proposal in front of the Ann Arbor city council regarding possible ordinance changes governing the Ann Arbor Downtown Development Authority. Depending on what the council decides, there might be implications for the county, he said, so he wanted to put it on the board’s radar. For background on this issue, see Chronicle coverage: “DDA Tax Capture Change Gets Initial OK” and “DDA Ramps Up PR after First Council Vote.”

Also briefly mentioned was a discussion that occurred at a late March county pension commission meeting, raising questions about the new labor contracts that the board approved on March 20, 2013. At issue is whether the county complied with a state law requiring supplemental actuarial analysis before pension benefit changes are adopted. The county administration subsequently conferred with outside legal counsel, and confirmed their view that no new actuarial analysis was necessary.

And although it wasn’t discussed at the April 3 board meeting, the recent labor contracts resulted in another issue related to compliance with state law: Elimination of the county’s healthcare benefits for domestic partners. [Full Story]

DDA Ramps Up PR After First Council Vote

Ann Arbor Downtown Development Authority board meeting (April 3, 2013): The board had no voting business on its agenda, but still dealt with serious business: the city council’s initial approval of changes to the DDA ordinance. The changes are meant to clarify the authority’s tax increment finance (TIF) capture, as well as place restrictions on board composition. [.pdf of Chapter 7 amendments]

DDA board chair Leah Gunn

DDA board chair Leah Gunn at the April 3, 2013 board meeting. (Photos by the writer.)

The proposed amendments to Chapter 7 of the city code, given initial approval at the council’s April 1, 2013 meeting, would reduce the DDA’s TIF capture by roughly $931,000 for FY 2014 – compared to the amount the DDA would receive based on the DDA’s current interpretation of the ordinance. But in adopting its two-year budget recently, DDA did not factor in recent building projects in the downtown – which add to the increment on which the DDA can capture taxes, starting in FY 2014.

So compared to the amount of TIF revenue in the DDA’s adopted FY 2014 budget, the clarified calculations would result in only about $363,000 less TIF revenue for the DDA. And compared to the DDA’s adopted FY 2015 budget, the clarified calculations would result in about $74,000 less revenue than budgeted. The clarified calculations would result in TIF revenue to the DDA in FY 2014 and FY 2015 of $3.570 and $3.682 million, respectively.

A dispute on the clarity of the existing Chapter 7 language had emerged in May 2011 just as the DDA and the city were poised to sign a newly renegotiated agreement under which the DDA manages the public parking system. At that time, the city’s financial staff reportedly first noticed the implications of an existing Chapter 7 paragraph that appears to place a cap on the DDA’s TIF capture – a cap that’s calibrated to projections in the DDA’s TIF plan. The TIF cap rises each year based on forecast growth in the DDA’s TIF capture district.

Several board members weighed in on the issue during the April 3 meeting. The idea of any kind of cap – let alone one that’s based on estimates contained in the appendix of the DDA’s TIF plan – was sharply criticized by Joan Lowenstein, who characterized the approach as based on “a fallacy.” She also called the idea of a cap poor public policy. However, both the cap and its basis are already in the existing ordinance language that the city council’s ordinance amendment seeks to clarify.

Roger Hewitt took the board’s meeting as an opportunity to question whether the ordinance amendments actually clarify how the calculations are to be done, contending that he’d come up with different results than the city treasurer, starting from the same ordinance language. He cautioned that the DDA’s financial planning and the DDA’s budget would need to be re-evaluated – allowing for no “sacred cows” – if the council gave final approval to the ordinance changes.

Russ Collins contrasted the amount of net revenue received by the city from the geographic area of the DDA district before the DDA was established back in 1982, compared to today. The net proceeds from taxes and the public parking system (which lost about $250,000 a year during that era) came to about $1.25 million 30 years ago, according to Collins. Today, the city receives nearly $8 million annually – around $4 million in taxes, $3 million in parking revenue, and a grant to the city of roughly $0.5 million a year toward debt on the city’s new Justice Center building.

Bob Guenzel focused his remarks less on the financial side and more on the aspects of the ordinance change that would restrict future board membership. He saw no benefit to the proposed DDA term limits, noting that the city council has an opportunity to end a DDA board member’s service by deciding not to re-appoint someone to the board. John Mouat was critical of the proposed ordinance changes that would prevent elected officials of taxing jurisdictions from serving on the board, saying he’d found the participation of politically-connected people to be beneficial to the board.

The extended remarks by board members on the topic came in the context of a 7-3 vote by the city council on April 1, giving initial approval of the ordinance changes. [Christopher Taylor (Ward 3) was absent from the meeting of the 11-member council.] A second vote, expected at the council’s April 15 meeting, would be required to enact the changes. Based on their remarks made at the council table, two of the seven votes in support of the changes – by Marcia Higgins (Ward 4) and Sabra Briere (Ward 1) – were widely read as likely to change at the second vote. Ordinance changes require a six-vote majority.

In addition to discussion of the possible ordinance changes, the DDA heard its usual range of committee reports, including the monthly parking update. Public commentary related to a possible artificial ice-skating rink atop the Library Lane underground parking garage. [Full Story]

Commissioners OK Greenbelt Strategic Plan

Ann Arbor greenbelt advisory commission meeting (April 4, 2013): An updated strategic plan for the city’s greenbelt program received unanimous approval at this month’s GAC meeting. The plan included only minor changes since the draft was reviewed in September of 2012.

Jennifer Fike, Huron River Watershed Council, Ann Arbor greenbelt advisory commission, The Ann Arbor Chronicle

Jennifer Fike, finance director of the Huron River Watershed Council, is interested in joining the greenbelt advisory commission. If nominated and confirmed by the city council, she would replace Laura Rubin, HRWC’s executive director, whose term on the commission ends in June. (Photos by the writer.)

The plan lays out a broad range of goals for the preservation of farmland and open space within the greenbelt boundaries. There are no significant changes from the last version approved in 2009, although the plan does include a new section on education and outreach.

The plan also includes the goal of establishing a greenbelt registry program, to formalize relationships with landowners who aren’t yet part of the greenbelt program, but who are committed to the program’s principles of land preservation. “It’s creating a pipeline of projects for the future,” said Dan Ezekiel, GAC’s chair. Three commissioners – Peter Allen, Shannon Brines and Archer Christian – agreed to work with Ginny Trocchio, who manages the greenbelt program, to develop a proposal for the full commission to consider.

Also at the April 4 meeting, Jennifer Fike – finance director for the Huron River Watershed Council – was introduced as a possible replacement on the commission for Laura Rubin. Rubin, who serves as HRWC’s executive director, fills a position on GAC that’s designated for an environmental organization. Her term ends on June 30. Because she is term-limited, she can’t be re-appointed.

Ezekiel noted that there are other vacancies as well, and that anyone who’s interested in applying should contact their city council representative. [.pdf of application form for city boards and commissions] Meetings for the commission are scheduled monthly, although the April meeting was only GAC’s second one in 2013. Both the January and March meetings were canceled. [Full Story]

AAPS Board OKs Labor Deals, Mulls Policies

Ann Arbor Public Schools (AAPS) board of education regular meeting (March 27, 2013): The main agenda item for trustees was agreements with the Ann Arbor Education Association (AAEA), representing the district’s teachers, paraeducators, and office professionals. The agreements, which were approved unanimously by the board, will save the district approximately $3.4 million in the 2013-14 fiscal year.

Mitchell Elementary students prepare for their musical performance

Mitchell Elementary students prepare for their musical performance. (Photos by the writer.)

Teachers agreed to a 3% pay cut for the 2013-14 year, while paraeducators and office professionals agreed to mandatory furlough days for the 2013-14 and 2014-15 school years. The trustees and district superintendent Patricia Green expressed their appreciation for what they called the “shared sacrifice” of the AAEA members.

The board heard extensive public commentary on several possible budget cuts. The board is facing $17-$20 million of cuts for next year’s budget.

The board also spent a significant time reviewing policy changes, brought forward by president Deb Mexicotte. Some of the policy changes included placing limits on board meeting times, adding items to the agenda, and changing the board’s committee structure. The board is considering a change from its current committee-of-the-whole to its former committee structure of two different standing committees. Previously the board had a committee for planning and one for performance – but it’s not clear if the board will settle on those committees. The board will consider the  raft of policy changes at its next regular meeting, on April 10.

The trustees also adopted an affirmation of boardsmanship, which is a “shared belief of values” that Mexicotte presented. The hope is that such a shared set of values would help guide them in their interactions with each other and the community. The affirmation came about as a result of their August 2012 board retreat, when board members decided that their number one board goal was to work on building trust with each other. [Full Story]

South State Retail Project Moves to Council

Ann Arbor planning commission meeting (April 2, 2013): A new retail project – with plans for a Jimmy John’s restaurant – will now move to the city council for approval, following a recommendation from planning commissioners this week.

Wendy Woods, Ken Clein, Sabra Briere, Ann Arbor planning commission, The Ann Arbor Chronicle

From left: Ann Arbor planning commissioners Wendy Woods, Ken Clein and Sabra Briere, who also represents Ward 1 on the Ann Arbor city council. (Photos by the writer.)

Called the State Street Center, the project will be located on a thin strip of land off of South State, just north of Ellsworth and adjacent to a relatively new Tim Hortons. Commissioners recommended approval of the site plan and for rezoning the parcel to C3 (fringe commercial). The Jimmy John’s will face South State. A separate one-story retail building will be located behind the restaurant.

Some commissioners expressed concern that the businesses in the retail building won’t be very visible from South State. Jim Cernuto, the owner’s project manager, noted that the State and Ellsworth corridor is “coming alive” after the opening of Costco, and that there’s strong interest from potential tenants. The proposed C3 zoning is the most inclusive type of non-residential zoning, allowing for a wide range of businesses, including convenience stores, dry cleaners, wholesalers and warehousing.

Also during the meeting, several commissioners brought up items for future discussion. Bonnie Bona noted that the city’s energy commission plans to develop recommendations for the city council regarding future development of the former YMCA site, on William between Fourth and Fifth avenues. She suggested that planning commissioners should discuss whether they also want to make recommendations, laying out what councilmembers should consider in deciding the site’s future. At its March 4, 2013 meeting, the council voted to direct the city administrator to prepare an RFP (request for proposals) for brokerage services to sell the lot.

Sabra Briere raised the issue of a whether the city should develop a “solar blocking” policy. If someone puts solar panels on the roof of their house, she noted, there is no ordinance to protect the home from other buildings that might be constructed nearby and block the sun – even though the city is encouraging this kind of solar energy use. Although she didn’t explicitly mention it, the issue of shading has been an argument against the proposed development at 413 E. Huron. In that case the issue has concerned the impact of building shade on trees, not solar panels. Briere also serves on the city council representing Ward 1. Councilmembers voted on April 1 to postpone action on that project.

Related to the 413 E. Huron project is a recent council directive to the planning commission to review the city’s downtown core (D1) zoning. Also on April 1, councilmembers provided specific guidance for that review, along with an Oct. 1 deadline for the completion of the work. Briere communicated the council’s direction to commissioners at their April 2 meeting, but there was no further discussion about it.

The commission’s regular meeting on April 2 was relatively brief, lasting about an hour. It was followed by a working session, where commissioners got an update from Nathan Voght, project manager for Reimagine Washtenaw. The effort is aimed at improving the Washtenaw Avenue corridor between Ann Arbor and Ypsilanti. Voght works for Washtenaw County’s office of community & economic development, which is overseeing the project. [Full Story]

Parks Agenda: Downtown, Dogs, Dams, DTE

Ann Arbor park advisory commission meeting (March 19, 2013): A packed agenda for this month’s PAC meeting included several items related to downtown parks and the Huron River.

Amy Kuras, Andrew Walton, Doug Kelly, Stewart Gordon, Ann Arbor park advisory commission, Library Green Conservancy, The Ann Arbor Chronicle

Park planner Amy Kuras, left, talks with Stewart Gordon, an advocate for putting an ice-skating rink atop the Library Lane site. In the background are Andrew Walton, left, and Doug Kelly, the city’s director of golf. Walton supervises the Huron Hills golf course. (Photos by the writer.)

Commissioners discussed a proposal to build an ice-skating rink atop a portion of the city-owned Library Lane underground parking structure. They took no action on the item, but were briefed on the proposal by two advocates of the effort: Alan Haber and Stewart Gordon. The two men also attended a subsequent March 26 meeting of a PAC downtown park subcommittee. This report includes a summary of that session as well.

River-related items on PAC’s March 19 agenda included a resolution to recommend awarding a $295,530 contract to Gerace Construction Co. for repair work and repainting at Argo and Geddes dams, as well as site improvements around Argo Dam. Brian Steglitz, an engineer with the city, told commissioners that the work is being done in response to the most recent inspection by state regulators.

Commissioners also recommended awarding a $512,180 contract for improvements at the Gallup Park canoe livery to Construction Solutions Inc., which will be funded in part by a $300,000 state grant. Cheryl Saam, facility supervisor for the Argo and Gallup canoe liveries, gave commissioners a presentation on those operations, in preparation for budget recommendations that PAC is expected to consider at its April 16 meeting.

As part of her report, Saam noted that the city plans to issue another request for proposals (RFP) to design a whitewater section along the Huron River, downstream from the Argo Dam near the Argo Cascades. Parks and recreation manager Colin Smith reminded commissioners that the first attempt at this project wasn’t successful. The Michigan Dept. of Environmental Quality did not approve the initial design, and would not issue the necessary permit for the project. The staff is working with the state to address MDEQ’s concerns, he said. Smith also reported that DTE Energy still intends to pay for the project, which is located adjacent to property that the utility company is cleaning up.

DTE representatives were on hand at the meeting because of a different project: To request an easement on city-owned land in Riverside Park, where utility poles are located. The easement is needed as part of an $8 million new electrical substation that DTE is building on land adjacent to the park. Commissioners unanimously recommended that the city council approve the easement.

In another presentation to set the stage for next month’s budget discussion, PAC heard from Doug Kelly, the city’s director of golf, and Andrew Walton, recreational facility supervisor at Huron Hills. They reviewed the status of the city’s two golf courses – at Huron Hills and Leslie Park – and noted that both courses have seen significant revenue gains over the past five years.

The issue that drew the most public commentary during the meeting wasn’t on the March 19 agenda: a possible dog park on a knoll in West Park. Residents in that area aren’t happy about the prospect of barking dogs in their neighborhood. [Full Story]

AADL To Hire Communications Consultant

Ann Arbor District Library board meeting (March 18, 2013): Several items during the AADL board’s most recent meeting related to the issue of communications.

Eli Neiburger, Prue Rosenthal, Ann Arbor District Library, The Ann Arbor Chronicle

Eli Neiburger, AADL’s associate director of IT and production, talks with AADL board president Prue Rosenthal in the small room off of the fourth-floor boardroom. The former closet is used as a studio for podcasting. (Photos by the writer.)

Nancy Kaplan, chair of the board’s new communications committee, announced that AADL will hire Allerton-Hill Consulting to do a communications audit and plan for the library, to be completed this year. The decision was made in consultation with AADL director Josie Parker, Kaplan said. It didn’t require a board vote because the amount of the contract is the maximum for not triggering board approval: $28,000. Contracts for purchases over that amount must be authorized by the board.

Board president Prue Rosental, in supporting the decision, noted that during the campaign to pass a bond for a new downtown library – which voters rejected on Nov. 6, 2012 – library advocates learned that “people in the community didn’t know what we do and how well we do it.”

Some of those “what we do” activities were highlighted during two presentations at the meeting: (1) an overview of AADL podcasts produced by staff and patrons; and (2) a report from Eli Neiburger, AADL’s associate director of IT and production, about his recent trip to Germany as a guest of the U.S. State Department and Zukunftswerkstatt (“Future Workshop”), visiting libraries in several cities. The head of the Zukunftswerkstatt was interested in using AADL’s efforts as a model to get German libraries more involved with younger communities, using gaming and other activities. As a result of the partnership with AADL, a dozen libraries in Germany have started running events through the GT System, which AADL staff developed. A league tournament is being held, and three winners will come to Ann Arbor for the May 19 German-American Gaming League Championships, held at the AADL.

Communications was also a topic during public commentary. Libby Hunter, a member of the Protect Our Libraries political action committee, urged the board to be more open and transparent, asking them to allow the public to attend committee meetings, to videotape their meetings for broadcast on Community Television Network, and to explain their use of closed sessions in relation to the Michigan Open Meetings Act. And Don Salberg asked for more information related to the condition of the downtown library, and for details on the board’s rationale for wanting a larger building on that same site.

Also during public commentary, Stewart Gordon spoke briefly about an effort to put a skating rink on the city-owned Library Lane site, adjacent to the downtown library on South Fifth Avenue. He hoped the topic could be put on the board’s agenda at some point.

The one resolution that was on the board’s agenda was unanimously approved: A one-year contract extension with Pace Mechanical Services for $83,865. The contract, which will run through June 30, 2014, covers HVAC equipment and maintenance.

The board also talked briefly about its budget preparations for fiscal 2013-14, which begins July 1. The budget and finance committee will bring a draft budget to the board’s April 15 meeting, with a vote on the budget scheduled for May 20. For the current fiscal year, the AADL has a budget of about $12 million, with a millage rate set at 1.55 mills. [Full Story]

413 E. Huron, Zoning Review: They’re Back

Ann Arbor city council meeting (March 18, 2013) Part 2: In a session that lasted until nearly 2 a.m., lengthy public commentary and council deliberations focused on two related items at the council’s last regular meeting: (1) a possible moratorium on D1 (downtown core) site plans; and (2) the site plan for 413 E. Huron, located in a D1 district. Both items resulted in some unfinished business that will need to be addressed at the council’s April 1 meeting.

413 E. Huron project. Left is the original rendering considered by the planning commission. Right is an updated version presented to the city council on March 18, 2013

Images for the proposed 413 E. Huron project, at the northeast corner of Huron and Division. On the left is the original rendering considered by the planning commission. On the right is an updated version presented to the city council on March 18, 2013. Even more revisions could be presented at the April 1 council meeting.

The council decided to conduct a review of D1 zoning, without imposing a moratorium. But councilmembers left some work on that issue until April 1, when the review’s clear scope of work and timeline are expected to be set.

The lack of any moratorium cleared the way to consider the 413 E. Huron project. Even though councilmembers deliberated in a fair amount of detail on the project, they still had a number of questions they wanted to pursue with the developer. So the council decided to postpone the item until April 1.

The council’s discussion of the 413 E. Huron project included a fine-grained examination of the project’s compliance with zoning code regarding the disturbance of natural features – trees in particular. It was punctuated by a resident shouting “You lie!” as the developer’s representative – Conor McNally of Atlanta-based Carter – responded to questions from councilmembers.

According to a letter sent by the developer to the council on March 29, councilmembers continued to submit additional questions in writing through March 28. That led to a request from the developer to remove the item from the April 1 agenda in favor of April 15, to allow for time to respond to questions. The developer is also hoping to revise 3D renderings to show changes in the building that have been made since March 18.

The developer’s request to pull the item from the agenda can’t be accommodated – because the council voted to postpone until a date certain, which means the item will need to appear on that April 1 agenda. To remove it would require a decision of the council, and that can’t be done administratively at the direction of the planning staff or on the initiative of the city clerk.

So the item will appear on the agenda, although the council may be inclined to make their deliberations brief, if their intent is to postpone it until April 15 – which would be consistent with the developer’s expressed preference. The public hearing on the site plan appears on the April 1 agenda as well, although it was declared closed by mayor John Hieftje on March 18.

This report includes a summary of public commentary and council deliberations on the moratorium and the 413 E. Huron site plan from March 18. A write-up of other agenda items is included in Part 1 of the March 18, 2013 meeting report. [Full Story]

AAPS Begins Superintendent Evaluation

Ann Arbor Public Schools board of education committee of the whole (March 20, 2013): At its committee meeting the trustees focused on identifying the metrics they will use for the formal evaluation of superintendent Patricia Green.

Ann Arbor Public Schools superintendent Patricia Green

Ann Arbor Public Schools superintendent Patricia Green. (Photos by the writer.)

Green is the one district employee for whom they are directly responsible. Earlier that evening, the trustees met in closed session with Green to go over her interim mid-year evaluation. Because it was an informal evaluation, the board did not release an official statement.

Beginning with the 2013-2014 school year, at least 25% of the superintendent’s annual year-end evaluation must be based on student growth and assessment data, according to a state mandate. In 2014-15, that percentage increases to 40%, and in 2015-16 school year, at least 50% of the evaluation will be based on student growth and assessment data. This mirrors the criteria in place for teacher evaluation. Up to now the superintendent’s evaluation has been largely narrative.

Board vice president Christine Stead noted that the board was implementing the metrics ahead of time, since they were not legally required to be in place until the next school year. [Full Story]

New Labor Contracts Key to County Budget

Washtenaw County board of commissioners meeting (March 20, 2013): In its main action, the county board approved new long-term contracts with 15 of Washtenaw County government’s 17 bargaining units – including annual wage increases, a cap on employee healthcare contributions, and the elimination of “banked leave” days. The precedent-setting move aimed to protect unions before Michigan’s right-to-work law takes effect on March 28, and cut legacy costs for the county.

Conan Smith, Dan Smith, Washtenaw County board of commissioners, The Ann Arbor Chronicle

From left: Conan Smith (D-District 9) and Dan Smith (R-District 2) at the Washtenaw County board of commissioners meeting on March 20. Dan Smith cast the lone vote against new contracts with labor unions representing county employees, citing concerns over the length of the agreements. Most of the contracts run through Dec. 31, 2023. (Photos by the writer.)

About 85% of the nearly 1,300 county workers belong to a union. The board also approved similar wage and benefit changes for the county’s non-union employees.

The right-to-work law will make it illegal to require employees to support unions financially as a condition of their employment, but labor agreements in place prior to March 28 will not be affected until they expire. Most of the previous contracts with the county’s labor unions were set to expire on Dec. 31, 2013. All but one of the new deals will run for more than 10 years – through Dec. 31, 2023.

Dan Smith (R-District 2) cited the length of those contracts as a reason for casting his no vote – he was the only commissioner to vote against the union contracts, though he supported the agreement for non-union employees. The duration eliminates the flexibility to deal with different conditions that might face the county in the future, he said. There is no “re-opener” clause that would allow either side to renegotiate before 2023.

Despite his no vote, Smith praised the most significant changes that will impact employees hired after Jan. 1, 2014. Those employees will participate in a defined contribution retirement plan, instead of the current defined benefit plan – the Washtenaw County Employees’ Retirement System (WCERS). In defined benefit plans, retirees receive a set amount per month during their retirement. In defined contribution plans, employers pay a set amount into the retirement plan while a person is employed. The most common defined contribution plan is the 401(k). Similar changes in retiree healthcare plans will also affect new employees.

The shift in the county’s approach to retirement plans and retiree healthcare was a major concern for several other commissioners. While acknowledging the benefits of eliminating the county’s legacy costs, Conan Smith (D-District 9) cautioned that retirees could be put at risk without the predictable stability of a defined benefit plan. However, he also noted that the board can’t continue to put the institution at risk by “guaranteeing something that we don’t know we’re going to be able to afford in the long run.”

Those legacy costs were a factor alluded to during the March 20 discussion, linking to another major decision that is expected to come before the board: bonding to cover the county’s unfunded liabilities for employee pensions and retiree healthcare. The issue hasn’t been discussed directly at any of the board’s regular meetings, but commissioners have been informed that a proposal likely will be brought forward by administration.

Based on actuarial valuations at the end of 2011, the county had $101.27 million in unfunded liabilities for its defined benefit pension, and $148.46 million in unfunded liabilities for its retiree healthcare. Those amounts will be higher when the 2012 actuarial valuations are completed later this year. The new accounting standards of GASB 68 require that unfunded liabilities must be included in an organization’s financial statements for fiscal years beginning after June 15, 2014.

Commissioners also got a year-end 2012 financial update during the March 20 meeting – the final 2012 audit will be brought to the board in April. Total revenues exceeded total expenditures by $2.26 million. The county had planned for a surplus of $1.889 million to carry into 2013 – so the year ended with an excess of $327,607 above that targeted amount.

In other action items, the board voted to form a committee that will explore the feasibility of creating a land bank, and appointed three people to the committee: Commissioner Ronnie Peterson (D-District 6), county treasurer Catherine McClary, and Mary Jo Callan, director of the county’s office of community & economic development. The committee is directed to report back to the board by Aug. 7, 2013.

During communications from the board, Conan Smith reported that the southeast Michigan Regional Transit Authority board has now been fully appointed, and will convene on March 28 for an orientation meeting. He suggested that the two Washtenaw County representatives – Richard “Murph” Murphy and Liz Gerber – come talk to commissioners about what the county’s interests and priorities are. “The earlier we weigh in, the more systemic the impact of our comments are going to be,” he said. “If we don’t talk to them until they’ve already made decisions, then it’s going to be too late.” [Full Story]

Planning, DDA: City Council to Set Course?

Ann Arbor city council meeting (March 18, 2013) Part 1: The two main events of the council’s meeting centered around planning in the downtown area: (1) consideration of a possible moratorium on D1 (downtown core) site plans; and (2) consideration of the site plan for 413 E. Huron, located in a D1 district.

The March 18, 2013 city council meeting did not adjourn until nearly 2 a.m. From left: Sabra Briere (Ward 1), Margie Teall (Ward 4) and city administrator Steve Powers.

The March 18, 2013 city council meeting did not adjourn until nearly 2 a.m. From left: Sabra Briere (Ward 1), Margie Teall (Ward 4) and city administrator Steve Powers. (Photos by the writer.)

The council decided to conduct a review of D1 zoning, without imposing a moratorium. That cleared the way to consider the 413 E. Huron project, which the council eventually voted to postpone – at roughly 1:30 a.m. Because of the amount of time spent on just those items, they’ll be included in a separate Chronicle report.

Apart from those two items, the council’s agenda still included a planning and land use focus, as well as a downtown theme. An additional theme was the city council’s relationship to two other public bodies – the city planning commission and the board of the Ann Arbor Downtown Development Authority.

In the case of the planning commission, the council for a second time balked at the commission’s recommendation of R3 (townhouse) zoning for a recently annexed parcel on Ellsworth near Stone School Road – planned as the site of Summit Townhomes, which would be a 24-unit development. The council postponed consideration of the Summit Townhomes site plan and the zoning, having previously postponed the zoning. The council also had previously referred the zoning recommendation back to the planning commission for re-review. The council’s second postponement on March 18 came after the commission’s re-affirmation of its original recommended R3 zoning. The council sent no explicit communication to the planning commission requesting action, beyond the implicit message of postponing the vote.

In the case of the DDA board, the council is weighing changes to the city ordinance governing the composition of that body, but postponed those changes for a second time at its March 18 meeting. The more significant of the ordinance changes involves clarifying how the Ann Arbor DDA’s tax increment finance capture is calculated, which has implications for millions of dollars for the DDA, the city of Ann Arbor, Washtenaw County, Washtenaw Community College and the Ann Arbor District Library.

Also related to the DDA, early in the council’s meeting an oral report was given on a session of the council’s audit committee – held the previous week to review the DDA’s FY 2012 audit. In the middle portion of the council meeting, councilmembers postponed the ordinance changes. And in the early morning hours of March 19, after the voting agenda was concluded, a member of the audit committee – Sally Petersen (Ward 2) – announced her intention to propose a task force on the DDA.

Related to other boards and commissions, the council confirmed the appointment of a chair for the zoning board of appeals (ZBA): Alex Milshteyn. He replaces Carol Kuhnke, who resigned in December 2012 after being elected judge of the 22nd Circuit Court.

In other business, the council gave approval for the zoning and site plan of The Shoppes at 3600, a proposed retail development on Plymouth Road.

The council also voted to object to the renewal of a liquor license for The Arena, a downtown bar located at Division and Washington streets. The basis for the objection – which will be forwarded to the Michigan Liquor Control Commission for final action – was non-payment of taxes.

The council also gave initial approval to a revision to the city’s sign ordinance. It would essentially maintain current conditions, but provide for certain limited digital signs with a restricted range of changeable elements.

Council communications included a briefing on upcoming changes the council will be asked to consider for the city’s public art ordinance. In other communications, the council will be giving a fire station reconfiguration plan some additional explicit discussion at a future working session – although it appears that the idea has insufficient traction to move forward.

Public commentary at the meeting covered a range of topics, including a call for the council to waive privilege on legal advice that councilmembers had received on the D1 moratorium issue – because they’ve now voted not to enact the moratorium. [Full Story]

AAPS Reviews Special Ed, Clemente Center

Ann Arbor Public Schools board of Education (March 13, 2013): The meeting was highlighted by reviews of two district programs: (1) the Student Intervention and Support Services (SISS) program; and (2) the Roberto Clemente Student Development Center.

Performance art by Lawton Elementary teacher Susan Baileys 2nd grade class at the AAPS March 13, 2013 board meeting.

Performance art by Lawton Elementary teacher Susan Bailey’s 2nd grade class at the AAPS March 13, 2013 board meeting. (Photos by the writer.)

The trustees seemed to be unimpressed with the SISS report – because not enough quantifiable data was presented. They asked the SISS team to come back with a more data-rich report at a future meeting.

Alesia Flye, deputy superintendent for instruction, presented the review of Roberto Clemente. The administration’s ultimate recommendation was to relocate the Clemente program to Pioneer High School beginning the fall of 2013 – for an estimated savings between $127,379 and $348,677. This was presented to the board as an information report. No action will be taken until the budget is finalized later on this year.

The board also discussed and unanimously approved a resolution to support three students who are currently facing criminal charges for their alleged roles in the Huron Pioneer football brawl.

Also at the meeting, the trustees also approved 2013-14 School of Choice (SOC) openings, which will be opened up on April 8 until May 8, 2013. Despite recommendations from the administration against it, the trustees approved 25 spots to be opened at Skyline High School for incoming ninth graders.

The board also formally approved a $2.5 million budget adjustment to cover lower-than-projected revenues and greater-than-projected expenses through the first half of the current budget year.

Upcoming budget decisions and anticipated cuts were also a prominent theme of the meeting. The board set a schedule for public forums to take place over the next month. And students who participate in the theater program addressed the board asking trustees not to cut support to that program. [Full Story]

New Residential Project Moves to Council

Ann Arbor planning commission meeting (March 19, 2013): Planning commissioners reviewed two projects at their most recent meeting: a commercial project near South State and Ellsworth; and a residential development off Traver Road near the Leslie Park golf course.

Eleanore Adenekan, Tony Derezinski, Ann Arbor planning commission, The Ann Arbor Chronicle

Ann Arbor planning commissioners Eleanore Adenekan and Tony Derezinski at the commission’s March 19, 2013 meeting. (Photos by the writer.)

The commission discussed, but then postponed action on a proposed site plan for State Street Center, just north of Ellsworth near the new Tim Hortons. The project calls for a drive-thru restaurant and separate retail building, with an entrance off of South State.

The planning staff had recommended postponement after discovering that the city’s official zoning map had been incorrectly labeled. It showed the site as zoned C3 (fringe commercial), and the developer had made plans based on that erroneous labeling. But during background research for this proposal, planning staff discovered that the site actually had been zoned as O (office) in 2003. The postponement is intended to allow the developer to submit a rezoning request.

A project that had previously been postponed by commissioners – called Hideaway Lane – was discussed and ultimately recommended for approval on March 19. The proposal is a residential development of 19 single-family houses on a 4.6-acre site off Traver Road, near the city’s Leslie Park golf course and on the edge of Traver Creek. Much of the discussion focused on issues related to the project’s impact on natural features, and how the developer plans to mitigate that impact.

The commission also authorized the reimbursement of expenses for Kirk Westphal – the commission’s chair – to attend the American Planning Association’s National Planning Conference in Chicago from April 13-17. He’ll appear on a panel with city staff to talk about Ann Arbor’s recently adopted sustainability framework. Westphal, a Democrat, recently announced his intent to run for Ann Arbor city council in Ward 2, for the seat currently held by Jane Lumm. [Full Story]

AATA Receives Audit, Preps for Urban Core

Ann Arbor Transportation Authority board meeting (March 21, 2013): The board’s main business of the evening was a presentation from the audit firm Plante Moran on the result of AATA’s fiscal year 2012 audit.

David Helisek, at the podium, presented highlights of the audit report to the AATA board.

David Helisek, at the podium, presented highlights of the audit report to the AATA board on March 21, 2013. (Photo by the writer.)

About the audit report, Plante Moran’s David Helisek told the board: “Hopefully, you found it somewhat boring.” By that he meant there were no material weaknesses or significant deficiencies to report. And his firm had struggled even to find suggestions for improvement in controls and processes. In the category of a suggestion was a recommendation to formalize a policy on user access to IT systems. And one question was left over from the previous year’s audit – on the legal basis of the AATA’s investment in heating oil futures as a hedge against possible price increases in diesel fuel. The AATA has inquired with the state of Michigan on that issue, but has not received an answer.

At the meeting, the board also rescinded a $119,980 contract it had authorized with PM Environmental – because of a failure on the AATA’s side to go through the standard procedure for bidding out the contract. The contract is for remediation of contaminated soil at the AATA’s headwaters on 2700 S. Industrial Highway. That contract will now be re-bid, and PM Environmental will have an opportunity to participate in that process.

In a final voting item on its agenda, the board authorized a four-month extension to the current pricing agreement the AATA has with Michigan Flyer – to provide AirRide service between downtown Ann Arbor and Detroit Metro airport. The extension will allow negotiations to take place on a new arrangement, which is being considered in the context of at least two factors. Ridership on the service, launched last year in April, has exceeded projections. And Michigan Flyer may be eligible for a federal grant that could increase the number of trips per day. The current service is hourly.

The board also heard a range of updates from its committees and CEO Michael Ford. Among the most significant was about a meeting scheduled for March 28 among representatives of Washtenaw County’s “urban core” communities that have, for the last few months, been engaged in discussions with AATA about expanded transit in a much smaller geographic footprint than the entire county. [Full Story]

County Awards Trail-Building Grants

Washtenaw County parks and recreation commission meeting (March 12, 2013): Several actions at WCPARC’s most recent meeting related to grants and partnerships – including the allocation of $600,000 in Connecting Communities funding.

721 N. Main, Washtenaw County parks & recreation commission, Ann Arbor, The Ann Arbor Chronicle

A view of the 721 N. Main site in Ann Arbor, looking south from Summit Street. The Washtenaw County parks & recreation commission awarded the city a $150,000 grant to develop trails in the property, but only if the city gets matching funds from the state. (Photos by the writer.)

Four communities received grants from WCPARC under that trail-building program: the village of Dexter ($225,000); Ypsilanti Township ($75,000); Pittsfield Township ($150,000); and the city of Ann Arbor ($150,000). Funding for Ann Arbor – only half of the $300,000 that the city had applied for – is to fund a trail at 721 N. Main, a city-owned site that’s being redeveloped. The award is contingent on the city receiving a matching grant from the Michigan Dept. of Natural Resources Trust Fund (MDNRTF).

WCPARC is also applying for an MDNRTF grant, hoping to get $300,000 to help develop a master plan for the Staebler Farm County Park. The 98-acre property, which straddles Plymouth Road in Superior Township, had been a family farm for nearly a century. The commission held a public hearing on this issue, and heard from four nearby property owners who raised concerns about trespassing. The proposal calls for WCPARC to contribute $450,000 in county funds to the project.

Moving forward on another major project, commissioners approved three actions related to the proposed recreation center on Ypsilanti’s Water Street redevelopment site, located along Michigan Avenue. WCPARC agreed to share equally with the Ann Arbor YMCA in a $28,000 market study to help determine whether there’s enough community interest to support the proposed center. Commissioners also authorized staff to move forward with the acquisition, for $31,500, of an easement from the Huron Fischer Honda Leasing Co. for a section of the Border-to-Border (B2B) trail that would connect Riverside Park to the Water Street site. The third action was a resolution acknowledging a partnership between WCPARC and the city of Ypsilanti to design, build and operate the rec center.

And WCPARC also authorized staff to apply for $1.4 million from the federal Transportation Alternative Program (TAP) to extend the B2B River Terrace Trail from Dexter-Huron Metropark east 1.1 miles to Zeeb Road. TAP is administered through SEMCOG (Southeast Michigan Council of Governments). The application would be in partnership with Scio Township and the Washtenaw County Road Commission. [Full Story]

Public Art Projects Move Forward

Ann Arbor public art commission special meeting (March 7, 2013): Because attendance was low at AAPAC’s regular meeting in late February, commissioners held a special meeting the following week to wrap up items that hadn’t been addressed.

Deb Polich, Bob Miller, Ann Arbor public art commission, Arts Alliance, The Ann Arbor Chronicle

Bob Miller, right, is the new chair of the Ann Arbor public art commission. To the left is Deb Polich, executive director of the nonprofit Arts Alliance. They were attending the March 15 meeting of the city council’s public art committee, which is developing revisions to the city’s public art ordinance. (Photos by the writer.)

Commissioners voted to accept a memorial for Coleman Jewett as an official AAPAC project and to approve Sarah Gay as a volunteer project manager. Her duties would be to lead efforts for city council approval, donor relations and fundraising. John Kotarski advocated for less involvement from AAPAC, saying he hoped to streamline the project.

However, other commissioners felt it should be handled like other projects, with oversight by AAPAC. The proposal is for a bronze Adirondack chair at the Ann Arbor farmers market. The city’s market manager, Sarah DeWitt, attended the March 7 meeting and will help coordinate the project.

Commissioners also voted to increase the honorariums for artists who have been selected as finalists for a $400,000 project at the East Stadium bridge. The overall project amount remains unchanged, but honorariums were raised from $2,000 to $3,000 for each of the four finalists: Volkan Alkanoglu, based in Atlanta, Georgia; Sheila Klein of Bow, Washington; Rebar Group of San Francisco; and Catherine Widgery of Cambridge, Mass. They will be in town on April 1 for a site visit and public open house.

Another effort that’s in the early phases got a vote of support from commissioners, but no financial commitment at this point. The project will use old aluminum canoes from the city of Ann Arbor’s Argo canoe livery, which artists and community groups will turn into artwork that will be displayed throughout the downtown in 2014. Partners in the project include the Ann Arbor Area Convention & Visitors Bureau (CVB), the Main Street Area Association (MSAA), the Arts Alliance, and the Huron River Watershed Council. AAPAC is involved only in a supportive role, to help with public engagement.

The role of public engagement was part of a discussion regarding AAPAC’s annual public art plan, which is due to the city council on April 1. Some commissioners expressed frustration at the process, given the uncertainty of the public art program’s future. Ultimately, they gave guidance to Aaron Seagraves, the city’s public art administrator, to draft a plan that includes projects in highly-visible, highly-used locations, currently underserved in terms of public art.

The March 7 meeting also included the election of officers. Bob Miller was elected the new chair, replacing Marsha Chamberlin. Kotarski abstained from voting. He noted that the commission will soon be at only 40% capacity – a reference to the fact that there are three vacancies on the nine-member commission, with an additional resignation expected by Wiltrud Simbuerger in the near future.

Two of those vacancies will likely be filled shortly. Nominations are on the city council’s March 18 agenda for confirmation: Nick Zagar, an artist and commercial real estate agent who serves on the Ann Arbor Art Center board; and Ashlee Arder, programs coordinator at ArtServe Michigan.

All of these actions come in the context of the city council’s ongoing review of the city’s public art program, which began in early December of 2012. This article begins with a report on the most recent meeting of the council’s public art committee on Friday, March 15. An update of their work will be attached to the council’s March 18 agenda as an item of communication. Their next committee meeting is scheduled for March 28. [Full Story]

County Board Priorities Emerge at Retreat

Washtenaw County board of commissioners budget retreat (March 7, 2013): County commissioners continued their work to lay a foundation for the 2014-2015 budget, in a three-hour retreat that covered a wide range of issues – including the possibility of a new millage, bonding or other revenue sources.

Conan Smith, Ronnie Peterson, Washtenaw County board of commissioners, The Ann Arbor Chronicle

From left: Washtenaw County commissioners Conan Smith (D-District 9, Ann Arbor) and Ronnie Peterson (D-District 6, Ypsilanti). (Photos by the writer.)

The retreat comes in the context of a projected $24.64 million general fund deficit over a four-year period from 2014 through 2017. A much smaller general fund deficit of $3.93 million is projected for 2014, but county administrator Verna McDaniel hopes to identify $6.88 million in structural changes for that year – a combination of new revenues and cuts in expenditures. If that happens, the larger projected deficit would be addressed, because those cuts and revenue increases would compound and carry over into future years.

The retreat didn’t aim to identify dollar amounts or even specific programs to be cut or supported. Rather, the conversation – which included small-group work – was designed to elicit broader priorities of the board. Commissioners did not explicitly reference priorities that had been developed for the previous 2012-2013 budget cycle, though some common themes emerged. [.pdf of 2012-2013 budget priorities]

Several commissioners stressed the importance of strategic investment to create an environment that supports the local economy. Transportation, education, and housing – particularly on the county’s east side, in the Ypsilanti area – were all cited as critical to economic development efforts. Funding strategies were floated, including the possibility of a human services millage, road tax, or “social impact” bond. Also discussed was the possibility of absorbing the road commission into county government operations.

The retreat follows a budget briefing that McDaniel and her financial staff had given to commissioners at their Jan. 16, 2013 meeting. The board has also discussed the budget process at two working sessions earlier in the year, and will follow up the retreat with a working session in April. McDaniel is expected to deliver a budget proposal to the board in September. The board must adopt the budget by the end of 2013. [Full Story]

“Connecting William” To Be Resource Plan

Ann Arbor planning commission meeting (March 5, 2013): Despite protests by members of the Library Green Conservancy and hesitation by some commissioners, the city planning commission voted unanimously to add the Connecting William Street plan to its list of resource documents that support the city’s master plan. After the vote, Wendy Woods tried to reopen the item for reconsideration, but she was unsuccessful in garnering support from the majority of commissioners, so the initial decision stands.

Sabra Briere, Jack Eaton, Ann Arbor planning commission, The Ann Arbor Chronicle

Jack Eaton talks with Sabra Briere before the start of the Ann Arbor planning commission’s March 5, 2013 meeting. Briere serves on the commission as the representative from city council. Eaton spoke during a public hearing on the Connecting William Street plan.

The Connecting William Street project was undertaken by the Ann Arbor Downtown Development Authority at the behest of the city council. It focuses on recommendations for coordinated development of five city-own sites in the William Street area, on the south side of downtown. By becoming a resource document, the CWS plan carries less weight than it would if it were part of the city’s master plan.

Amber Miller of the DDA gave a presentation during the March 5 commission meeting, similar to those previously given to the council and the DDA board.

Much of the discussion among commissioners focused on the issue of open space. Miller noted that recommendations on that issue have been deferred to a committee of the city’s park advisory commission. That downtown parks committee is in the early stages of its work – it was scheduled to meet earlier in the day on March 5, but that meeting was canceled.

Commentary during a public hearing on the CWS plan also focused on open space, with several members of the Library Green Conservancy advocating for a centrally located park atop the Library Lane underground parking structure. They criticized the DDA’s process for developing the plan, and felt the planning commission had not adequately publicized the fact that a public hearing on Connecting William Street would be held that evening.

Additional public commentary came after the commission’s vote. Woods said her decision to ask for reconsideration of the item was prompted by concerns raised during this final public commentary. She felt it wouldn’t hurt to wait two weeks until the commission’s next meeting, so that more people could have the chance to weigh in, if they wanted.

Sabra Briere, who had expressed strong reservations before casting her original yes vote, said she supported Woods in her effort to reconsider the item, suggesting that postponement would be appropriate. She expressed concern that the commission was deciding to use the CWS plan as a future planning document – which would be referenced when the planning staff and commission make their recommendations to the city council on site plans and other planning and development actions. Given that importance, Briere – who also serves on city council – wanted to be absolutely certain before accepting it.

Other commissioners disagreed. Kirk Westphal, the planning commission’s chair, also served on a DDA leadership outreach committee (LOC) that helped craft the Connecting William Street plan. He said he felt extremely comfortable with the public process that had led to these recommendations. Eric Mahler also argued against reopening the item for another vote, saying the commission needed to bring closure to this long process. He was satisfied that sufficient public notice had been provided.

It’s unclear whether the city council will take any action on the Connecting William Street plan. As to what happens next, Susan Pollay, the DDA’s executive director, told planning commissioners that the DDA will be following the council’s guidance. Councilmembers have already taken a first step related to one of the five parcels – the former YMCA lot. At their meeting on March 4, 2013, councilmembers voted to direct the city administrator to prepare an RFP (request for proposals) for brokerage services to sell the lot. A $3.5 million balloon payment on the property is due at the end of 2013. [Full Story]

Council’s Meeting Dominated by Downtown

Ann Arbor city council meeting (March 4, 2013): The council had five items on its agenda related geographically to downtown Ann Arbor – but delayed voting on two of them.

Architect Brad Moore (left) talks with resident Ray Detter. Moore is architect for two projects that were on the council's March 4 agenda – Blue Heron Pond and 624 Church St. The councils approval of both site plans indicates the council is not contemplating imposing a Moore-atorium on site plans.

Architect Brad Moore (left) talks with resident Ray Detter. Moore is architect for two projects that were on the council’s March 4 agenda – Blue Heron Pond and 624 Church St. The council’s approval of both projects indicates the governing body is not contemplating a Moore-atorium on site plans. (Photos by the writer.)

On one of those items, the council voted to postpone its initial consideration of changes to Chapter 7 of the city code, which governs the way the tax increment finance (TIF) capture is calculated for Ann Arbor’s downtown development authority. The revisions to Chapter 7 would also affect the composition of the DDA board, excluding elected officials from service.

The council also postponed until its next meeting, on March 18, a possible moratorium on site plan review for projects in the downtown. The possible moratorium previously had been postponed from the council’s Feb. 19 meeting. After hearing extensive public commentary on the topic on March 4 – from residents and representatives of the developer of a proposed 14-story residential project at 413 E. Huron – the council went into closed session.

On emerging from the closed session, the council voted, without deliberation, to postpone the item. The wording in the resolution provides an exemption from the moratorium for site plans that already have a recommendation for approval from the city planning commission. If enacted, the moratorium as worded would still apply to the 413 E. Huron project, because the planning commission’s 5-3 vote for approval fell short of the six it needed for a positive recommendation. The 413 E. Huron site plan is now expected to be on the same March 18 meeting agenda when the moratorium will be re-visited.

Eluding the impact of the proposed moratorium’s wording was another downtown project, which appeared on the March 4 meeting agenda. The site plan for a 14-story apartment building at 624 Church St. was approved at the council’s meeting – but that project would not have been impacted by the moratorium as it’s currently proposed. That’s because it had received a recommendation of approval from the city planning commission.

The council also voted to reconstitute a task force to re-evaluate the downtown design guidelines, which supplement the city’s zoning regulations.

In the final downtown-related item, the council voted to direct the city administrator to issue a request for proposals for brokerage services to possibly sell the city-owned parcel at Fifth and William streets – the location of the former Y building. It’s currently used as a surface parking lot in the city’s public parking system.

While the city is contemplating the sale of that site, which it purchased for $3.5 million, the council voted to buy a much less expensive parcel outside the downtown, near the Bluffs Nature Area. The council approved a purchase price of $115,000 for the parcel, which is located off Orkney Street.

The council also approved two other site plans for projects not in the downtown – although the four-unit project at 515 N. Fifth is near the downtown. The council also approved the Blue Heron Pond development, a 64-unit project on the western side of town, located at Liberty and Maple.

In other business, the council approved receipt of a federal grant to demolish two of the buildings on the city-owned property at 721 N. Main. The buildings are in the floodway. A third building, in the flood fringe, is being studied by the city for possible reuse.

The property at 721 N. Main is a former maintenance yard. So none of the 44 vehicles authorized for purchase by the council at the March 4 meeting will be maintained there. Total cost of the vehicles was $928,499.

None of the vehicles authorized for purchase was a plug-in electric vehicle. However, the council passed a resolution in support of preparing city infrastructure for plug-in vehicles. Two-other energy-related agenda items included one supporting the city’s participation in Earth Hour, and another one supporting use of the city’s energy fund for energy improvements in connection with community projects.

An item that drew considerable discussion before approval related to street closings associated with the June 9, 2013 Ann Arbor marathon. [Full Story]

AAPS Weighs Future Cuts, $2.5M Gap Now

Ann Arbor Public Schools board of education regular meeting (Feb. 27, 2013): At a meeting that lasted until 3 a.m., the Ann Arbor Public School (AAPS) school board covered a variety of topics, including: an extensive report on high school issues; budget shortfalls; and budget reductions.

Robert Allen, AAPS deputy superintendent for operations

Robert Allen, AAPS deputy superintendent for operations delivered a second quarter financial report that showed the district is nearly $2.5 million over budget.

A report on high school scheduling got a mixed reaction from the board. While many trustees appreciated the work that went into the report, there was disappointment that no hard recommendations were made by the committee. No decisions were made on the issue of moving high school start times or moving Skyline High School from a trimester to a semester schedule.

And Robert Allen, deputy superintendent of operations, left the board reeling when he reported the district was just under $2.5 million over budget and needed to adjust the 2012-2013 budget. The discrepancy resulted from staffing adjustments and changes in funding from the state of Michigan.

Having been directed by the board at a previous meeting to explain better the implications of each item cut, Allen again reviewed some budget reduction options for the coming year.

The board was also briefed on the condition of physical properties and updated on the capital funding plan. Executive director of physical properties Randy Trent suggested the possibility of placing a combined bond and sinking fund millage on the ballot, instead of asking for a simple renewal of the sinking fund millage, levied currently at 1 mill. The idea would be to ask voters for the same amount – to cover the combined proposal – with the advantage that the bond revenues can be spent more flexibly.

The board was briefed on major purchases for projectors and copiers and voted to approve some purchases on which they’d already been briefed a their previous meeting – for AstroTurf and laptop computers.

The board also voted to place a discussion of a resolution on its agenda for March 13, which would express the board’s support for three district high school students who now face criminal charges as a result of a brawl at the conclusion of a football game last year.  [Full Story]

Ann Arbor DDA: We’ve Been Good Stewards

Ann Arbor Downtown Development Authority board meeting (March 6, 2013): In a main agenda item, the DDA board authorized a $300,000 grant to the Ann Arbor Housing Commission – for renovations to the 64-unit Baker Commons public housing facility. It added to the $280,000 grant made late last year for the replacement of the Baker Commons roof.

DDA board member Keith Orr delivered extended remarks in response to a proposal currently being weighed by the Ann Arbor city council that would make amendments to the city ordinance governing the downtown development authority.

Ann Arbor Downtown Development Authority board member Keith Orr delivered extended remarks in response to a proposal currently being weighed by the Ann Arbor city council that would amend the city’s ordinance governing the DDA. (Photos by the writer.)

The grant award had come at the request of AAHC executive director Jennifer L. Hall, who’s proposing a major change to the way the 360 units of public housing are administered. The approach involves privatization and project-based vouchers.

The DDA’s support for public housing also surfaced at the meeting as a talking point for board members in the context of a proposal being considered by the Ann Arbor city council – which would amend the city ordinance regulating how the DDA’s tax increment finance (TIF) capture works. The amendments would clarify existing language in the city ordinance in a way that would favor the other taxing authorities, whose taxes are captured as a part of the DDA’s TIF. The council postponed action on that proposal at its March 4, 2013 meeting. In that context, at the DDA’s March 6 meeting, board member Sandi Smith raised the specter that the DDA would in the future not be able to support affordable housing in the same way it has done in the past.

In addition to clarifying the question of how TIF is calculated, the amendments would prevent elected officials from serving on the board and would impose term limits for board service. Board members took turns at the start of the meeting arguing that the DDA had been a good steward of public dollars and that the amendments to the ordinance are not warranted. Board members indicated that they didn’t think their service as volunteer members of a board was being afforded adequate respect by the city council.

The board comments followed a turn at public commentary at the start of the meeting from Brendan Cavendar of Colliers International, a commercial real estate services firm. His commentary departed from the typical pattern of someone signing up to address the board for up to four minutes. Instead, Cavendar had been invited to appear, and responded to prompts from board members to deliver a range of positive responses, including: future tenancy of the former Borders location; rising rents in the downtown area; and affirmation of the importance of the downtown public parking system.

The city’s public parking system is managed by the Ann Arbor DDA under a contract with the city of Ann Arbor. The monthly parking usage report is featured at every board meeting. But the March 6 meeting featured the parking system in an additional way. The board decided to award the full $50,000 of a discretionary management incentive to the DDA’s subcontractor – Republic Parking – for operation of the public parking system. It’s an annual decision, but it’s the first time in the last five years that the full amount has been awarded. The decision was based on good performance on metrics tracked by the DDA, according to the board.

In a third voting item, the board authorized $610,662 in support of getDowntown’s go!pass program, which provides a subsidy to cover the cost of rides taken on Ann Arbor Transportation Authority buses by employees of participating downtown businesses. To participate, a business must purchase a go!pass for all employees, at an annual cost of $10 per employee. Roughly 6,500 downtown employees are provided with go!passes through the program. [Full Story]