415 W. Washington Land Sale Item: Withdrawn

By the time of the Ann Arbor city council’s July 21, 2014 meeting, Chuck Warpehoski (Ward 5) had withdrawn a resolution he’d sponsored on the agenda – which would have listed the city-owned 415 W. Washington property for sale and allocated $250,000 toward developing a master plan for the Allen Creek Greenway.

Warpehoski had sponsored the item along with mayor John Hieftje, with the title “Resolution to List for Sale 415 W. Washington and Appropriate Funds for Allen Creek Greenway Master Plan.”

As of mid-day Friday, July 18, no text or memo was included in the resolution. Warpehoski responded to an emailed query from The Chronicle by saying that the resolution might be pulled, depending on the outcome of a meeting of … [Full Story]

FEMA Grant to Fund 721 N. Main Demolition

Two buildings on the city-owned 721 N. Main property near downtown Ann Arbor will now be demolished, using $87,704 in funds granted by the Federal Emergency Management Agency (FEMA).

721 N. Main site showing the two buildings to be demolished, which are located in the floodway.

721 N. Main site showing the two buildings to be demolished, which are located in the floodway.

The unanimous vote to accept the funds came at the council’s March 4, 2013 meeting. The 721 N. Main site is a former city maintenance yard, and is part of a … [Full Story]

First & Liberty

Street markings of where the Allen Creek drain runs under West Liberty, possibly related to the construction of Village Green’s “Ann Arbor City Apartments” at First & Washington. [photo]

City Council Parcels Out Tasks: Open Space

Ann Arbor city council meeting (May 7, 2012) Part 1: In Part 1 of this council meeting report, The Chronicle has collected those agenda items and discussion that relate to land use and open space, which was one of two dominant themes of the meeting. The other major theme was public art, which will be included in Part 2 of the report – along with other items not related to land use.

Three Parcels

Three parcels received discussion at the council's May 7 meeting, from south to north: 415 W. Washington, 721 N. Main, the MichCon property. (Image links to higher resolution file)

In connection with different agenda items, the council discussed the future of three major parcels within the city, two of which are city-owned: 415 W. Washington and 721 N. Main, and the MichCon site near Broadway bridges.

First the council heard an update on the possible future of the city-owned 415 W. Washington property, located across from the Ann Arbor YMCA, which opened in 2005. The Y replaced the old Ann Arbor Technology Center, which had been the home of the 555 Nonprofit Gallery and Studios, along with independent artists and musicians, who rented space at the center. It burned in the course of a 2003 demolition.

The 555 Nonprofit Gallery and Studios went on to re-locate in Detroit. The group has some experience re-purposing buildings as space for artists, recently hosting a fundraiser for an additional property it has acquired – the 3rd Police Precinct in southwest Detroit. Artists can rent literal jail cells there as work space.

On Feb. 1, 2010, the Ann Arbor city council had established a task force – consisting of greenway advocates and members of the arts community – to explore the future use of the 415 W. Washington property. The Ann Arbor Arts Alliance was the group identified to represent the arts community interests.

Now, the 555 group appears ready to take responsibility for the arts portion of planning for the site. That’s the portion that entails re-using the existing building on the site, which is located in the Old West Side historic district. Carl Goines, a representative of 555, addressed the council on Monday night. Goines had co-founded the group 10 years ago in the tech center.

Goines described how an investment of around $45,000 is needed for surveying and environmental analysis of the 415 W. Washington site. That investment would be required whether the building is preserved or demolished, he said. Mayor John Hieftje indicated in his comments at the meeting that he’d be willing to give the group perhaps a year to establish a viable way to re-purpose the building, but also indicated an eagerness eventually to apply to the Michigan Natural Resources Trust Fund for a grant to develop the entire parcel as a park. If the 555 group could not find a way to rehabilitate the structure within a reasonable time, Hieftje indicated a willingness to pursue the option of asking the city’s historic district commission for permission to demolish the structure.

The other city-owned parcel discussed by the council was 721 N. Main, former site of a city maintenance yard.  That came in connection with a council resolution to establish a task force to study the North Main corridor, and deliver a report in a year’s time, by July 31, 2013. Earlier than that, by the end of 2012, the task force is supposed to provide a recommendation on the use of 721 N. Main.

The city has an already-approved grant from the Federal Emergency Management Agency (FEMA) to pay for demolition of two buildings on the site – but not the main building. The 721 N. Main parcel will also likely be part of a Natural Resources Trust Fund grant application by the city in the spring of 2013.

The task force is also supposed to provide a recommendation on the future use of the MichCon property, between the Amtrak station and the Huron River. MichCon is currently undertaking an environmental cleanup of the land, and the standard to which MichCon remediates the parcel will depend on its intended future use. Hieftje has been clear about his preference – that the city acquire the land for a park. A possible source of funds the city could use for acquisition of such a park would be money generated by the open space and parkland preservation millage.

By administrative policy, a third of the revenue from that millage is overseen by the land acquisition committee of the city’s park advisory commission. The council confirmed a new appointment to that commission at Monday’s meeting – Ingrid Ault, who replaces the term-limited Gwen Nystuen. The other two-thirds of the millage revenues – for preservation of land outside the city as a greenbelt – is administered by the greenbelt advisory commission. And notice of two upcoming reappointments to that body was also on the agenda – for Catherine Riseng and Peter Allen.

Allen is a real estate developer, who might have alternatives in mind for MichCon’s property that include more than just a park. [Full Story]

Major Renovation of City Ballfields Planned

Ann Arbor park advisory commission meeting (Jan. 24, 2012): Baseball fields in three city parks will be getting a major overhaul, if the Ann Arbor city council approves a recent recommendation by park commissioners.

Baseball field #4 at Veterans Memorial Park

Baseball field #4 at Veterans Memorial Park will be among fields at three parks that will be renovated, if the Ann Arbor city council approves a recommendation of the park advisory commission. (Photos by the writer.)

PAC unanimously recommended awarding a nearly $1 million contract to RMD Holdings of Chesterfield, Michigan, for renovation of ballfields at Veterans Memorial Park, West Park and Southeast Area Park. If approved by the city council, work would begin after the 2012 summer season. Ann Arbor Rec & Ed – a unit of the Ann Arbor Public Schools – plans to cancel its fall season in light of the project. Teams playing in Rec & Ed programs are the primary users of these fields.

Commissioners also got an update on the status of West Park renovations – specifically, how problems with an underground stormwater system are being addressed. City engineer Nick Hutchinson described plans for repairing the system, saying that legal issues are still being worked out, but the project will likely be completed by July of 2012. A public forum will be held on Feb. 13 at Slauson Middle School to update residents. At a similar meeting held in mid-January, residents raised concerns over whether the situation in West Park has caused flooding in nearby basements.

Also at PAC’s Jan. 24 meeting, commissioner Gwen Nystuen urged the group to consider taking action on the Allen Creek greenway, in light of remarks made by mayor John Hieftje at the city council’s Jan. 23 meeting regarding the city-owned 415 W. Washington property. Colin Smith, the city’s manager of parks and recreation, reported that there’s been discussion about possibly applying for a state grant to help fund the greenway, but the timeline for applying this year is tight. He also suggested that an initial step would be to develop a master plan for the greenway, as recommended in the city’s parks, recreation and open space plan.

Near the beginning of the meeting, commissioner Sam Offen introduced the new executive director for the Leslie Science & Nature Center, Susan Westhoff, who spoke briefly to commissioners. Offen is a board member of the center, a nonprofit that’s located on city property. [Full Story]

Council Expresses Support for Greenway

At its Aug. 4, 2011 meeting, the Ann Arbor city council passed a resolution added late to the agenda, on Tuesday, Aug. 2, that expresses general support for the idea of constructing a greenway along the Allen Creek corridor.

The single “resolved” clause reads: “That the Ann Arbor City Council is fully supportive of the creation of the Allen Creek Greenway, and hereby directs City staff to continue to work with and to assist the Allen Creek Greenway Conservancy during the Greenway’s development and implementation phases.” [.pdf of Aug. 4 Greenway resolution]

The resolution comes as the possibility is becoming more real to construct the first section of the greenway close to the planned Near North housing project. On May 16, 2011, the city council approved neighborhood stabilization funds for the demolition of three houses as site preparation for the Near North project. Adjacent to the Near North site are additional houses that could be demolished and left as open space, which could become part of a greenway. But based on remarks made at the meeting by greenway advocates, it appears that the first segment to be constructed is most likely to be the portion running through 415 W. Washington.

During public commentary, the council heard that various key property owners like the University of Michigan and the Ann Arbor Railroad are interested in hearing a clear statement from the city expressing its commitment.

The 18 “whereas” clauses recite history dating back to 2005 when the city council appointed a task force to study the possibility of a greenway. The history recited by the resolution includes a measure approved by the council on July 6, 2009, which rezoned the First and William parcel as public land and set forth the council’s intention that the property (currently a parking lot) would eventually become part of a greenway. [Additional Chronicle coverage: "First & William to Become Greenway?"]

As a point of history, the July 6, 2009 meeting was the same meeting when the council authorized the start of a request for proposals (RFP) process for development of the city-owned Library Lot, which was eventually terminated  on April 4, 2011, without selection of a proposal.

Also included in the Aug. 4 resolution’s recitation of history is a Feb. 1, 2010 measure that started a process for re-developing the city-owned parcel at 415 W. Washington. The city had previously initiated an RFP process for 415 W. Washington. An RFP review committee met seven times from May to December 2008 to review and evaluate the three proposals the city had received. The RFP committee offered praise for all three proposals but did not designate any one of the three as preferred.

The committee punted the issue back to the city council, recommending that the council refine the RFP. The council’s Feb. 1, 2010 action did not follow that recommendation, and instead created a working group of city councilmembers, the Greenway Conservancy and the Arts Alliance to explore the re-use of the property.

Like the Aug. 4, 2011 resolution, the Feb. 1, 2010 measure was sponsored by mayor John Hieftje, Carsten Hohnke (Ward 5) and Margie Teall (Ward 4) and was also added late to the council’s agenda. The July 6, 2009 measure was sponsored by Hieftje and Hohnke.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link] [Full Story]

Park, Greenbelt Advisory Groups Share Goals

Joint working session of the Ann Arbor park and greenbelt advisory commissions (June 7, 2011): Even with a fan blowing, the meeting room at Gallup Park was hot and stuffy. But members of the city’s greenbelt and park advisory commissions toughed it out for about 90 minutes to hold their second-ever joint working session earlier this month.

Peter Allen, Julie Grand, Ella and Jennifer Santi Hall, Dan Ezekiel

From left: Peter Allen, Julie Grand, Ella and Jennifer Santi Hall, Dan Ezekiel. Grand is chair of the park advisory commission. Allen, Hall and Ezekiel are greenbelt advisory commissioners. Jennifer Hall has served as GAC chair, but her term is ending on the commission – this was her last meeting. Ella Hall also had attended the first GAC meeting with her mother seven years ago – she was three weeks old at the time. (Photo by the writer.)

They covered many of the same topics that they’d discussed at their first joint meeting in April 2010 – funding issues, land preservation and acquisition strategies, as well as specific projects like the Allen Creek greenway and support for small farms.

Ginny Trocchio of The Conservation Fund, which has a contract to manage the greenbelt and park land acquisition programs, gave commissioners an overview of finances, projects and goals. Both programs are funded by a 30-year, 0.5 mill tax for land acquisition, called the open space and parkland preservation millage, which Ann Arbor voters approved in 2003. Two-thirds of the millage proceeds are used for the greenbelt program, and one-third is allotted to park land acquisition. To get money upfront for land acquisition, the city took out a $20 million bond in fiscal 2006 that’s being paid back with revenue from the millage. Current combined fund balances for the two programs total nearly $9 million.

Trocchio also highlighted an upcoming event to celebrate the greenbelt program. On Thursday, June 16, an open house will be hosted at the Braun farm – one of the program’s protected properties in Ann Arbor Township. The event is free and open to the public, and starts at 5:30 p.m. – parking is available at 4175 Whitmore Lake Road.

At the end of the June 7 meeting, commissioners congratulated two GAC members for their service – it was the final meeting for Gil Omenn and Jennifer Santi Hall, who has served as chair. Their terms expire June 30, and it’s not clear when appointments to replace them will be made. [Full Story]

Planning Commission Postpones Parks Plan

Ann Arbor planning commission meeting (Feb. 8, 2011): After 90 minutes that included public commentary from three board members of the Allen Creek Greenway Conservancy, planning commissioners voted to postpone action on the city’s Parks and Recreation Open Space (PROS) plan until their Feb. 15 meeting.

Ray Fullerton

Ray Fullerton, a board member of the Allen Creek Greenway Conservancy, passes out a letter to planning commissioners that makes suggestions for revising the city's Parks and Recreation Open Space (PROS) plan. In the background is planning commissioner Kirk Westphal. (Photos by the writer.)

The postponement coordinated with a similar move made last month by the Ann Arbor park advisory commission, which rescheduled its vote to its Feb. 15 meeting in order to allow for additional public input.

The PROS plan provides an inventory, needs assessment and action plan for the city’s parks system, and is updated every five years. The updated document is required by the state in order for the city to be eligible to apply for certain grants.

A public hearing on the PROS plan drew three board members of the Allen Creek Greenway Conservancy, a nonprofit dedicated to developing a park running through Ann Arbor from Stadium Boulevard to the Huron River, roughly following the course of the original Allen Creek. They advocated for stronger support of the greenway within the PROS plan. [Full Story]

Vote on Ann Arbor Parks Plan Postponed

Ann Arbor park advisory commission meeting (Jan. 18, 2011): Commissioners were set to vote on recommending approval of the updated five-year Parks and Recreation Open Space (PROS) plan, but decided to postpone their vote until the February meeting to allow for possible additional public input.

Sam Offen, Tim Doyle

Park advisory commissioners Sam Offen, left, and Tim Doyle look at a schematic of the proposed Allen Creek Greenway during a presentation at PAC's Jan. 18 meeting. (Photos by the writer.)

A speaker during PAC’s public hearing on the plan had pointed out that the official public commentary period runs through Jan. 24. That prompted discussion among commissioners about whether to hold off until all possible commentary is heard – though some indicated there’d already been ample opportunity for feedback. Another public hearing on the PROS plan will be held at the planning commission’s Feb. 1 meeting, with a vote by that group set for Feb. 15. City council is expected to hold a public hearing and vote on the plan in early March.

Tuesday’s PAC meeting included two presentations. Mike Quinn, a board member of the Allen Creek Greenway Conservancy, described the group’s efforts and asked PAC to convey a sense of urgency about the project to city council. And Scott Rosencrans, a former PAC chair, gave an update on the Ann Arbor skatepark: “The big news is that this is the year we build the skatepark.”

Updates from city parks staff included a quarterly financial report, during which parks manager Colin Smith reported that parks & recreaction is looking at 2.5% cuts during the next budget cycle. Commissioners also got briefed on the outcome of the Miles of Golf proposal to take over operations of the Huron Hills golf course – a proposal rejected by the city late last year – and an update on planned improvements at the Gallup Park canoe livery. Staff will hold a public meeting with concept plans on Tuesday, Jan. 25 at the livery, starting at 7 p.m. If the plan is approved, the city is poised to apply for state grant funding for the project, estimated to cost about $450,000. [Full Story]