Stories indexed with the term ‘Ann Arbor Park Advisory Commission’

Ault to Replace Nystuen on Park Advisory Group

At its May 7, 2012 meeting, the Ann Arbor city council confirmed the nomination of Ingrid Ault to the city’s park advisory commission. Ault – executive director of the nonprofit Think Local First – replaces Gwen Nystuen, who served two three-year terms on the commission starting in 2006. Service on the commission is limited to six continuous years at a time – but an additional appointment can be made after a three-year pause.

This brief was filed from the city council’s chambers on the second floor of city hall located at 301 E. Huron. A more detailed report will follow: [link]

Park Commission Supports FY 2013 Budget

At its April 17, 2012 meeting, the Ann Arbor park advisory commission unanimously approved two resolutions related to the city’s fiscal year 2013 budget, the year beginning July 1, 2012 through June 30, 2013. It’s the second year of a two-year budget planning cycle. PAC had previously recommended approval of budgets for both years at its April 2011 meeting. The parks budget is part of the city’s overall budget, which city administrator Steve Powers presented at the April 16 meeting of the Ann Arbor city council.

The portion of the city budget relating to parks can be separated into two parts: (1) park operations; and (2) parks and recreation.

On Tuesday, PAC recommended approval of the FY 2013 parks operations … [Full Story]

Park Commission Briefed on Millage Renewal

Ann Arbor park advisory commission meeting (March 20, 2012): At their monthly meeting, park advisory commissioners were briefed on two millages that help fund Ann Arbor’s park system, including one that will likely be on the November ballot for renewal.

Ducks in West Park

Creatures in West Park will not be able to participate in the November millage vote, even though they apparently can get their ducks in a row. A parks millage that's up for renewal helped pay for some of the recent renovations to the park, including the boardwalk, bandshell plaza and entry stairs. (Photos by the writer.)

The park maintenance and capital improvements millage, a six-year tax, brings in about $5 million annually and accounts for about 45% of the parks budget – including the entire funding for the natural areas preservation (NAP) program. Voters will likely be asked to renew it at 1.1 mills from 2013-2018, assuming the city council votes to put the millage on the Nov. 6 ballot at that rate. PAC chair Julie Grand – who has served on a working group to strategize about the renewal – said concerns about the economic climate are a major reason why an increase isn’t being recommended.

During the millage discussion, city councilmember Mike Anglin said he supports the millage but has concerns about Fuller Park, noting that talks regarding Fuller Road Station aren’t over. Parks manager Colin Smith pointed out that no millage funds have been or would be spent on Fuller Road Station. Grand cautioned against connecting the millage renewal to Fuller Road Station, saying it’s important to inform the public clearly about what the renewal means.

To provide that information, the city plans to hold four public forums in April, and a public hearing on the millage will be scheduled for PAC’s April 17 meeting. The city also plans to launch a website in early April with more information about the millage.

Also at the March 20 meeting, commissioners got a mid-year update about the open space and parkland preservation millage, which funds the greenbelt program and park acquisitions. Fuller Road Station was a backdrop to this discussion too, when commissioner Gwen Nystuen asked about protections that are afforded land acquired through this millage.

Land acquisition also came up in two other contexts during the meeting. The future of property owned by MichCon – located north of Broadway Street, between the Huron River and the railroad tracks – was part of the discussion during an update on environmental cleanup at the site. A DTE Energy representative indicated that senior management sees the potential for redevelopment there, but no plans are finalized. It’s expected that DTE Energy, which owns the property through its MichCon subsidiary, will eventually sell the site.

And speaking during public commentary, Ann Arbor resident Larry Baird advocated for the city to acquire land to fill gaps in the Border-to-Border Trail, which roughly follows the Huron River. Specifically, he characterized a connection between Bandemer Park and Barton Nature Area as the top priority, and urged the city to focus more on this project than on high-speed rail.

In the agenda’s one action item, commissioners recommended awarding a $79,980 contract to Michigan Recreational Construction Inc. to handle renovations at Placid Way Park. The resolution also recommends an additional 10% contingency of $7,998 for a total project cost of $87,978. The 1.32-acre neighborhood park is located on the city’s north side near the larger Dhu Varren Woods Nature Area and Foxfire South Park. The project would be funded from the park maintenance and capital improvements millage. [Full Story]

PAC Supports Placid Way Park Renovations

At its March 20, 2012 meeting, the Ann Arbor park advisory commission recommended awarding a $79,980 contract to Michigan Recreational Construction Inc. to handle renovations at Placid Way Park. The resolution passed unanimously by PAC also recommends an additional 10% contingency of $7,998 for a total project cost of $87,978. The recommendation will be forwarded to the city council for approval.

The 1.32-acre neighborhood park is located on the city’s north side near the larger Dhu Varren Woods Nature Area and Foxfire South Park. An entrance to the park with a small parking lot is located off of Placid Way, across from Tuebingen Parkway. [.pdf map of Placid Way Park.]

According to a staff memo, Michigan Recreational Construction, a Howell-based company, submitted … [Full Story]

Ann Arbor Park Improvements In the Works

Ann Arbor park advisory commission meeting (Feb. 28, 2012): Commissioners took action on several parks projects at their most recent meeting, and were briefed on others already in the works.

Colin Smith

Colin Smith, Ann Arbor's parks and recreation manager, signs sheets from more than a dozen local high school students attesting that they had attended the Feb. 28, 2012 meeting of the city's park advisory commission, as part of a class assignment. (Photos by the writer.)

The largest of the action items was a $865,190 contract for road, parking, pathway and other exterior renovations at Buhr Park and Cobblestone Farm. The work will include resurfacing the entry road off of Packard, and improving the path system to allow better access within the park area, as well as a connection from Essex Street into the park. The city council later approved the project at its March 5 meeting.

Commissioners also recommended approval of a 15-foot landscaping buffer in Riverside Park, next to a proposed new DTE Energy substation that abuts the park. DTE is seeking a variance from the city code, which requires a land use buffer for any commercial site that’s adjacent to a park – without the variance, that buffer would need to be located on DTE property. The new substation, to be located in the utility company’s Ann Arbor service center at 984 Broadway, will provide more electrical power to the downtown area due to increased demand.

Also recommended for approval was a $35,200 contract for restroom renovations at the Ann Arbor Senior Center. The facility will be closed in May while the project is completed, and activities will be scheduled at other locations. When PAC chair Julie Grand said she was impressed to see that so many companies had bid on the project, parks manager Colin Smith noted that it might reflect changes related to CUB agreements.

To comply with new state legislation, last summer the city council rescinded a resolution that had previously required contractors for city projects to execute Construction Unity Board (CUB) agreements. The agreements are negotiated between local trade unions and contractors, and require that contractors abide by terms of collective bargaining agreements for the duration of the construction project.

At their Feb. 28 meeting, park commissioners were also updated on a project to make exterior improvements – primarily related to pedestrian pathways – at the Leslie Science & Nature Center. The center, located at 1831 Traver Road, was previously part of the city’s parks system but since 2007 has operated as an independent nonprofit. However, the city still owns and maintains the buildings and property. The first stage of the project will focus on making pathways to the center’s popular raptor enclosures more accessible.

Commissioners also learned that during the week of March 12, the city will begin to install a new pedestrian bridge at the end of the Argo Dam bypass. Because of the construction, the recently renovated bypass will be temporarily closed. A stoplog will be put in to stop the flow of water into the bypass – the project will likely take a couple of weeks. The path along the bypass is expected to be paved later in April, with the end in sight for the entire project by May.

Smith reported that Argo Cascades will be the new name for the bypass – a series of drop pools that eliminates the need to portage along that stretch.

During an update on the parks and recreation budget, Smith reported that due to extra funds available from the park operations budget, plans are in the works to: (1) restore mowing to a 14-day cycle – the cycle has in recent seasons been every 19 days; (2) increase seasonal staffing between April 15 and Oct. 15; and (3) hire three park rangers from May through September, to deal better with maintenance and enforcement issues in the parks.

Several items were also raised during the time set aside for communications. Smith noted that the six-year, 1.1 mill parks maintenance and capital improvements millage will be coming up for renewal this fall. Staff has already started working on the renewal process, gathering materials in preparation for a March 12 city council working session. The millage was last approved in 2006.

It was also noted that two key staff members are leaving their jobs soon. Molly Notarianni, the city’s market manager, is stepping down at the end of March after about four years on the job. The position has already been posted. And long-time Rec & Ed director Sara Aeschbach will be retiring this summer. Both were praised for their service.

At the end of the meeting, commissioner Gwen Nystuen reminded her PAC colleagues about an upcoming sustainability forum on Thursday, March 8 at 7 p.m. in the downtown Ann Arbor District Library building. It’s the third in a series of four, this one focusing on climate and energy, and is part of a broader sustainability project that began last year and includes developing sustainability goals for the city. [See Chronicle coverage of the first and second forums in the series.] A public forum on the forums is also scheduled for March 29 from 6-8 p.m. at the downtown Ann Arbor District Library building, 343 S. Fifth Ave. [Full Story]

Buhr, Cobblestone Project OK’d

At its Feb. 28, 2012 meeting, the Ann Arbor park advisory commission unanimously recommended approval of a $865,190 contract for road, parking and other exterior renovations at Buhr Park and Cobblestone Farm. The contract, which requires approval by city council, would be awarded to Fonson Inc.

Fonson submitted the second lowest of 10 bids. The contract includes a $786,536 base bid plus a $78,654 (10%) contingency for possible change orders. Funding would come from the park maintenance and capital improvements millage, as well as the park rehabilitation and development millage. According to a staff memo, the lowest bid received was from Pranam Global Tech for $499,000. However, no paving subcontractors were listed and no testing fees were included, which were both requirements of … [Full Story]

Contract for Senior Center Restrooms OK’d

A $35,200 contract for restroom renovations at the Ann Arbor Senior Center was recommended for approval by the Ann Arbor park advisory commission at its Feb. 28, 2012 meeting. If approved by the city council, the contract would be awarded to L.C. Construction, which submitted the lowest of eight acceptable bids. The facility will be closed in May while the project is completed, and activities will be scheduled at other locations.

The $35,200 includes a $32,000 base bid and a $3,200 (10%) contingency fund to cover possible change orders. Funds would come from proceeds of the park maintenance and capital improvements millage.

According to a city staff memo, the restrooms don’t meet the state’s Barrier Free Code. The center’s two existing restrooms – each … [Full Story]

DTE Landscaping Buffer Gets Parks OK

At its Feb. 28, 2012 meeting, the Ann Arbor park advisory commission unanimously recommended approval of a 15-foot landscaping buffer in Riverside Park, next to a proposed new DTE substation that abuts the park. DTE also needs to secure a variance from the city’s zoning board of appeals and planning commission, as well as final approval by the city council.

DTE is seeking a variance of the city’s conflicting land use buffer. The buffer is required for any commercial site that’s adjacent to a park – without the variance, that buffer would be located on DTE property. According to a city staff memo, DTE is building the new Buckler substation in the utility company’s Ann Arbor service center at 984 Broadway, to … [Full Story]

Major Renovation of City Ballfields Planned

Ann Arbor park advisory commission meeting (Jan. 24, 2012): Baseball fields in three city parks will be getting a major overhaul, if the Ann Arbor city council approves a recent recommendation by park commissioners.

Baseball field #4 at Veterans Memorial Park

Baseball field #4 at Veterans Memorial Park will be among fields at three parks that will be renovated, if the Ann Arbor city council approves a recommendation of the park advisory commission. (Photos by the writer.)

PAC unanimously recommended awarding a nearly $1 million contract to RMD Holdings of Chesterfield, Michigan, for renovation of ballfields at Veterans Memorial Park, West Park and Southeast Area Park. If approved by the city council, work would begin after the 2012 summer season. Ann Arbor Rec & Ed – a unit of the Ann Arbor Public Schools – plans to cancel its fall season in light of the project. Teams playing in Rec & Ed programs are the primary users of these fields.

Commissioners also got an update on the status of West Park renovations – specifically, how problems with an underground stormwater system are being addressed. City engineer Nick Hutchinson described plans for repairing the system, saying that legal issues are still being worked out, but the project will likely be completed by July of 2012. A public forum will be held on Feb. 13 at Slauson Middle School to update residents. At a similar meeting held in mid-January, residents raised concerns over whether the situation in West Park has caused flooding in nearby basements.

Also at PAC’s Jan. 24 meeting, commissioner Gwen Nystuen urged the group to consider taking action on the Allen Creek greenway, in light of remarks made by mayor John Hieftje at the city council’s Jan. 23 meeting regarding the city-owned 415 W. Washington property. Colin Smith, the city’s manager of parks and recreation, reported that there’s been discussion about possibly applying for a state grant to help fund the greenway, but the timeline for applying this year is tight. He also suggested that an initial step would be to develop a master plan for the greenway, as recommended in the city’s parks, recreation and open space plan.

Near the beginning of the meeting, commissioner Sam Offen introduced the new executive director for the Leslie Science & Nature Center, Susan Westhoff, who spoke briefly to commissioners. Offen is a board member of the center, a nonprofit that’s located on city property. [Full Story]

Park Group Recommends Ballpark Overhaul

At its Jan. 24, 2012 meeting, the Ann Arbor park advisory commission unanimously recommended a nearly $1 million contract to renovate softball and baseball fields at three city parks.

If approved by the city council, the $982,333 contract would be awarded to RMD Holdings of Chesterfield, Michigan. That amount includes a $893,030 base bid plus a 10% contingency of $89,303. It was the lowest of four bids received for the project, which will focus on the fenced ballparks at Veterans Memorial Park, West Park and Southeast Area Park. Originally, the city had intended to include fields at Allmendinger Park as well, but bids came in higher than expected and that work was eliminated from the project.

The renovations have been in the works for … [Full Story]

Creek Project Ramps Up at Leslie Park Golf

Ann Arbor park advisory commission (Dec. 20, 2011): Park commissioners were briefed about a project on the section of Traver Creek running through the city’s Leslie Park golf course, addressing erosion and stormwater issues along the streambank.

Jen Lawson, Doug Kelly

Jen Lawson, the city's water quality manager, talks with Doug Kelly, the city's director of golf, prior to the start of the Dec. 20, 2011 park advisory commission meeting. (Photos by the writer.)

Jen Lawson, the city of Ann Arbor’s water quality manager, said the city hopes to hire a design consultant in January, with preliminary designs for the project ready by April. Final designs and construction plans would be done by July, and construction is projected to start in November of 2012.

The project would be completed by the spring of 2013, Lawson said, although an additional two growing seasons would be needed for plants to take hold. The intent is to minimize the impact on golfers during construction – parks and recreation manager Colin Smith noted that the project team is sensitive to the need for revenues from the course.

During the December meeting, commissioners also got an update on the city’s natural area preservation program, which has increased the number of volunteers who help with tasks like invasive species control and animal/plant monitoring.

Communications from staff included an update on the Argo Dam bypass, where work has stopped for the season. Additional work, including paving of a footpath, will occur in the spring. And in communications from commissioners, Sam Offen reminded his colleagues of the upcoming sustainability forums. The first forum is on Thursday, Jan. 12, focusing on resource management. All forums, held once a month, will be at the downtown Ann Arbor District Library building, 343 S. Fifth Ave. starting at 7 p.m. [Full Story]

More Concerns Aired on Fuller Road Station

Ann Arbor park advisory commission meeting (Nov. 15, 2011): With no action items on the agenda, PAC’s November meeting was filled with updates and honors, farewells and a few pointed comments regarding Fuller Road Station.

Lynn Bowen, Julie Grand, Colin Smith

At left: Lynn Bowen, an administrative assistant with the city who provides staff support for the park advisory commission, is retiring and was honored at PAC's November meeting. She has worked at the city for 26 years, including the last six years with parks and recreation. To the right are PAC chair Julie Grand and Colin Smith, the city's parks and recreation manager. (Photos by the writer.)

Commissioners were briefed by city staff about annual finances related to the land acquisition for parks and greenbelt programs, which are funded by a 30-year millage. They also got an update on the city’s marketing efforts for parks and recreation, and heard a report on the status of a sustainability project – several PAC commissioners had attended a September joint work session to help prioritize city goals related to environmental quality, economic vitality, and social equity.

Updates were also given about a sediment removal project in the Ruthven Nature Area, and about two parking-related projects at Riverside Park and Veterans Memorial Park.

In his manager’s report, Colin Smith noted that he’d taken a canoe run through the under-construction Argo Dam bypass pools – the new channel was a ”bit sportier” than he had expected, and is still being tweaked. He also told commissioners he’d received word that two state grant applications made by the city of Ann Arbor – $300,000 for the proposed Ann Arbor skatepark at Veterans Memorial Park, and $300,000 for improvements at the Gallup Park canoe livery – had ranked in the top 12 out of 100 applications statewide for funding from the Michigan Natural Resources Trust Fund. That bodes well for the possibility that the grants will be awarded – a decision from the state is expected in December.

During the meeting commissioners also honored two volunteers with the city’s natural area preservation program – Sarah Newman and Drew Lathin – and said farewell to Lynn Bowen, the administrative assistant who works with PAC. The meeting was her last before retiring from the city.

An item not on the agenda – the proposed Fuller Road Station – drew focus from public commentary as well as some questions from commissioners later in the meeting.  [Full Story]

Skatepark, Gallup Grants Rank High

Two state grant applications made by the city of Ann Arbor – $300,000 for the proposed Ann Arbor skatepark at Veterans Memorial Park, and $300,000 for improvements at the Gallup Park canoe livery – ranked in the top 12 out of 100 applications statewide for funding from the Michigan Natural Resources Trust Fund. At the Nov. 15 meeting of the Ann Arbor park advisory commission, Colin Smith, the city’s parks and recreation manager, told PAC members that he received the application scores in the mail earlier in the day.

The skatepark application ranked 12th out of the 100 applications, based on a scoring system used to evaluate the grants. The Gallup Park application ranked 2nd. Smith also reported that a … [Full Story]

Ann Arbor Senior Center: Changes Reviewed

Ann Arbor park advisory commission meeting (Oct. 18, 2011): Having skipped a meeting in September, park commissioners faced a full agenda at their October session, highlighted by a consultant’s report on the Ann Arbor senior center.

Christopher Taylor, Sam Offen, Tim Doyle

Ann Arbor city councilmember Christopher Taylor, left, accepts a ballot from Tim Doyle, right, a park advisory commissioner. In the center is Sam Offen, who was re-elected as chair of PAC's budget committee. Taylor is a non-voting ex-officio member of PAC.

The report – including 16 recommendations for changes to improve the Burns Park center and senior services – is the latest in an effort that dates back to 2009, when the city considered closing the center. Suggestions include: (1) expanding programs to other locations, particularly to low-income senior housing; (2) partnering with other programs in the area, such as the popular travel program offered by Pittsfield Township’s senior center; and (3) possibly making the Burns Park facility more of a community center, and renaming it to reflect that broader mission.

Staff will be taking this report and incorporating elements of it into a strategic plan, which will be reviewed by PAC and city council before action is taken.

The meeting also included votes to recommend awarding contracts for renovations at Island Park, and support for a bioremediation pilot project at Southeast Area Park. Matt Naud, the city’s environmental coordinator, told commissioners that the test would determine the effectiveness of an approach to remove an existing vinyl chloride plume. The process would involve giving nutrients to naturally occurring microorganisms that can break down the contaminant. The plume resulted from vinyl chloride being released from the now-closed city landfill into groundwater on the south side of Ellsworth Road.

Margaret Parker, a member of the Ann Arbor public art commission (AAPAC), gave a presentation about two potential public art projects along the Huron River – at the Argo Dam bypass, and the Gallup Park canoe livery. Since the work would likely be on city-owned parkland, members of the parks staff and park advisory commission would be part of a task force for the project. Laura Rubin, executive director of the Huron River Watershed Council, also attended PAC’s meeting. She spoke in support of a more comprehensive vision for art as part of RiverUp!, an effort to improve a 104-mile stretch of the Huron River.

During public commentary, commissioners heard suggestions for several ways to improve non-motorized connections between South State and South Main streets.

The October meeting also included a review of FY 2011 and first-quarter FY 2012 financials for the parks system, and PAC’s annual election of officers. There were no deliberations, and current officers – including PAC chair Julie Grand – were re-elected unanimously. [Full Story]

Park Group Briefed on River Art Walk Proposal

Margaret Parker of the Ann Arbor public art commission (AAPAC) made a presentation on potential art projects along the Huron River during the Oct. 18, 2011 meeting of the city’s park advisory commission (PAC). [.pdf of River Art Walk proposal] The proposal had been discussed in detail at the art commission’s Aug. 24, 2011 meeting.

Parker told PAC members that two locations have been identified for possible public art along the river: (1) at Gallup Park, in conjunction with planned improvements to the canoe livery; (2) at the Argo Dam canoe bypass, which is currently under construction. A broader project for art along a much longer stretch of the river could also be developed in connection with the RiverUp! … [Full Story]

Bioremediation Possible for Southeast Park

Matt Naud, the city’s environmental coordinator, solicited a recommendation from the Ann Arbor park advisory commission at its Oct. 18, 2011 meeting regarding whether to pursue a bioremediation pilot test in a section of Southeast Area Park, a 26.5-acre city park at Ellsworth and Platt roads. The test would determine if technology to remove an existing vinyl chloride plume is effective.

The plume resulted from vinyl chloride being released from the now-closed city landfill into groundwater on the south side of Ellsworth Road. Currently, extraction wells are used to pull the groundwater and contaminants back to the extraction wells where the water is discharged to the sanitary sewer for treatment.

The pilot project would test a different type of remedial process called bioremediation, … [Full Story]

Consultants Deliver Senior Center Report

At its Oct. 18, 2011 meeting, the Ann Arbor park advisory commission (PAC) received a final report from consultants regarding the Ann Arbor senior center. [.pdf of full report] At its June 24, 2011 meeting, PAC had received a staff update on the senior center, which is located at Burns Park.

The report stems from city budget talks in 2009, when city officials were looking to cut costs and said that closing the senior center would save about $150,000 annually from the city’s general fund. In response to protests from local residents, the city formed a task force to develop strategies to keep the center open.

In November 2010, the city council approved a $34,750 contract for the consulting firm Hooker … [Full Story]

Repairs Recommended for Island Park

At its Oct. 18, 2011 meeting, the Ann Arbor park advisory commission passed two resolutions related to Island Park. PAC recommended approval of a $92,586 contract with Legacy Custom Builders Inc. for repair of the Island Park Greek Revival shelter. The price includes an $84,169 bid and a $8,417 (10%) construction contingency.

According to a staff memo, the shelter was built in 1914 and has been renovated several times, most recently in 1995. Weather, insect and animal damage has caused the structure to deteriorate. Four contractors made bids on the project, and Legacy Custom Builders proposed the lowest bid. The firm is based in Northville, Mich.

In a separate resolution, the commission recommended approval of a $71,500 contract with Saladino Construction Company Inc. … [Full Story]

Action on Argo Headrace, Trails Near Fuller

Ann Arbor park advisory commission meeting (Aug. 16, 2011): During a three-hour meeting on Tuesday, park commissioners walked down several topical trails in what PAC chair Julie Grand aptly described as a “super-packed” agenda.

Argo headrace

The view looking east down the dewatered Argo headrace, with the embankment on the right. The trail along the embankment to Broadway is closed, as the city prepares for major reconstruction of the headrace. (Photos by the writer.)

Commissioners approved a resolution recommending a change to the scope of work at the Argo headrace – a change that will add a new entrance to the soon-to-be-reconstructed waterway from Argo Pond to the Huron River. The modification to the project was linked to an offer from DTE to pay for a whitewater section that’s part of the overall project, which freed up city funds for the new entrance. A state permit needed to start the reconstruction is expected to be received by Aug. 23.

A second resolution introduced at Tuesday’s meeting urged the city council to incorporate design of a trail system – including the county’s Border to Border (B2B) trail – into the Fuller Road area in advance of building the proposed Fuller Road Station. Two members of the Washtenaw Bicycling & Walking Coalition were on hand with suggestions for where trails might be located to bypass the busy intersection of Fuller Road, Maiden Lane and East Medical Center Drive.

The topic of trails also emerged tangentially during a presentation by PAC vice chair John Lawter on dog parks. Some people walk their dogs off leash on park trails and in other park areas, violating Ann Arbor’s ordinance requiring dogs to be leashed. The exception is in the city’s two dog parks, on the north and south edges of town.

Lawter suggested that Ann Arbor might find other ways to let dogs off leash, either by creating another traditional dog park that’s more centrally located, or designating certain hours for dogs to be off leash in specific parks. PAC might form a subcommittee to explore options for a new dog park, and for how to increase enforcement of existing dog-control ordinances. Such an effort might uncover more data points like those Lawter provided in his presentation, which included the pounds of poo collected annually at Swift Run dog park.

Data collection has also been part of developing the city’s first urban forest management plan. Oliver Kiley of JJR, the consultant leading this project, updated the commission on the effort. Possible outcomes include a recommended maintenance plan, protections for mature trees, targets for new tree plantings, and proposals for relevant ordinances and zoning. The discussion among commissioners led to concerns over whether the city is prepared for something similar to the emerald ash borer – which decimated thousands of trees in the city over the past decade and chewed up the city’s forestry budget for several years.

The urban forest management plan will be among the 26 city plans in a sustainability framework being developed, focused on “triple-bottom line” goals of economic vitality, environmental quality and social equity. The commission was briefed on this project in preparation for a Sept. 27 joint meeting of the park, planning, energy and environmental commissions. The goal of that meeting is to start prioritizing goals from these existing city plans. [Full Story]

PAC: Integrate Trails into Fuller Road Station

At its Aug. 16, 2011 meeting, the Ann Arbor park advisory commission unanimously passed a resolution recommending that planning for a trail system – including the county’s Border to Border (B2B) Trail – be incorporated into plans for the proposed Fuller Road Station. The resolution was drafted by commissioners Gwen Nystuen and Tim Berla, and will be forwarded to the city council.

Among other things, the resolution states that detailed plans for the design and funding of the trail system, including the B2B Trail through Fuller Park and the connecting links on all sides, should be approved by PAC and city council prior to action on the Fuller Road Station project. The resolution calls for trail improvements to be completed prior to or … [Full Story]

PAC Recommends Change to Argo Project

At its Aug. 16, 2011 meeting, the Ann Arbor park advisory commission recommended amending the project scope with TSP Environmental for work on the Argo dam headrace.  [.pdf of staff memo and resolution]

The Livonia firm had been hired last year to build a bypass channel in the headrace for $988,170 and to add whitewater features for an additional $180,000. However, DTE is now offering to pay for the whitewater feature of the Argo dam project, if the city agrees to hold off on construction of that piece until after DTE completes remediation on its nearby property, as required by the state.

By having DTE pay for the work, the city is expected to save $163,636. The resolution approved at Tuesday’s PAC … [Full Story]

RiverUp! Focuses on Revitalizing Huron River

Ann Arbor park advisory commission (July 19, 2011): A new project to shore up the ecological health and recreational infrastructure of the Huron River – and to strengthen the economies of river communities like Ann Arbor and Ypsilanti – is getting ready for its public debut in mid-August. Park commissioners were briefed on the RiverUp! effort at their July meeting, and were invited to an Aug. 16 bus tour of sites that will be given initial attention in the Ann Arbor and Ypsilanti area.

Greek Revival shelter at Island Park in Ann Arbor

Greek Revival shelter at Island Park, where an event to launch the RiverUp! project will be held on Aug. 16. (Photos by the writer)

Elizabeth Riggs of the Huron River Watershed Council, which is coordinating the project, told PAC members that RiverUp! is spearheaded by a conservancy group called the Wolfpack. Co-founded by attorney and former Clinton advisor Paul Dimond and retired Ford executive Ray Pittman, Wolfpack members – mostly from the Ann Arbor area – have been previously focused on state issues. Now, Riggs said, they are turning their attention to a 104-mile stretch of the Huron River, starting from the north at Milford through Ann Arbor and Ypsilanti, and downstream to Flat Rock.

Also at their July meeting, commissioners got an update about efforts to build an Ann Arbor skatepark. They also reviewed tentative FY 2011 budget results for the parks system – finals numbers will be presented to the commission in August.

Several other topics were discussed or mentioned during the meeting, in the form of communications from staff or commissioners: (1) an update on work at Argo dam; (2) concerns over the proposed Fuller Road Station and the site design’s consideration of the Border-to-Border Trail; (3) a roughly $100,000 donation from the Henrietta Feldman trust; (4) news of the resignation of Greta Brunschwyler, executive director of the Leslie Science & Nature Center; and (5) a preview of an August agenda item regarding dog parks.

Other news regarding the Argo dam project – a $1.17 million effort to build a bypass channel in the Argo dam headrace, and to add whitewater features – emerged the week after PAC’s July 19 meeting.

A July 25 memo from city staff reports that the city was recently notified by DTE officials of upcoming remediation work that DTE plans to do in 2012 adjacent to DTE’s property on the south side of the Huron River, between Allen Creek Drain and the Broadway Bridge. The remediation is being required by the Michigan Dept. of Environmental Quality.

DTE is offering to pay for the whitewater feature of the Argo dam project, if the city agrees to hold off on construction of that piece until after DTE completes its remediation. Details of the offer haven’t been finalized. [Full Story]

Couple Gives $50,000 for Ann Arbor Park

Ann Arbor park advisory commission meeting (June 21, 2011): Park commissioners heard some unusual and welcome news at their June meeting – two long-time Ann Arbor residents, Leslie and Michael Morris, are donating $50,000 to the city in support of South University Park.

Michael Morris, Leslie Morris, Colin Smith

From left: Michael Morris and Leslie Morris, who are donating $50,000 to rehab South University Park, and Colin Smith, the city's parks and recreation manager.

In brief remarks to commissioners, Leslie Morris – a former Ward 2 city councilmember – explained how she and her husband had played a role decades ago in creating the park, which is located at South University Avenue and Walnut. They hope their donation will help develop the park based on current needs of the neighborhood, she said.

Michael Morris noted that before they became involved in forming that neighborhood park, their civic engagement primarily had been limited to voting. But getting involved in that project ultimately led to much deeper engagement, culminating in the service of Leslie Morris on council. ”It’s been a rewarding time for us,” he said, “and I’m pleased we’re able to do more to continue the life of that park.”

Later in the meeting, commissioners got updates on the Ann Arbor senior center and Mack pool. Both facilities rely on general fund support and had been at risk of closing, when city officials were looking to cut costs in 2009. Residents rallied, and the city formed two task forces to develop strategies – both for raising revenues and cutting expenses – to keep both facilities open.

The reports given at PAC’s June 21 meeting were updates for the first fiscal year that these strategies took effect. Neither facility completely hit its target budget goals, but each took steps toward closing the gap between revenues and expenses.

Commissioners also got a quarterly update on capital improvements in the park system, including plans to renovate the Island Park Greek Revival shelter and the pergola at West Park, and to replace a path at Leslie Science & Nature Center – a project that might use recycled crushed glass as a porous surface. PAC members voted to recommend approval for funding of two specific projects: renovation of locker rooms at Veterans Memorial Park, and of tennis courts at West Park.

At the end of the meeting, Steve Thorp spoke during public commentary, urging the city to give West Park a new name – Central Park West – and to possibly put a dog park there. [Full Story]

Contract for Vets Park Locker Room OK’d

At its June 21, 2011 meeting, the Ann Arbor park advisory commission recommended approval of a $131,670 contract with Construction Solutions Inc. to renovate locker rooms at Veterans Memorial Park Pool and Ice Arena. The contract includes $119,700 for the work, plus a 10% ($11,970) contingency. It was the lowest of four bids submitted for the work.

According to a staff memo, the locker rooms get heavy use and were last renovated 20 years ago. Renovations would include installation of barrier-free shower stalls, benches and toilet partitions, energy efficient light fixtures, new windows and an upgraded ventilation system. The project would be paid for from the approved FY 2011 proceeds of the park maintenance and capital improvements millage. The recommendation will be forwarded to city council … [Full Story]

Park, Greenbelt Advisory Groups Share Goals

Joint working session of the Ann Arbor park and greenbelt advisory commissions (June 7, 2011): Even with a fan blowing, the meeting room at Gallup Park was hot and stuffy. But members of the city’s greenbelt and park advisory commissions toughed it out for about 90 minutes to hold their second-ever joint working session earlier this month.

Peter Allen, Julie Grand, Ella and Jennifer Santi Hall, Dan Ezekiel

From left: Peter Allen, Julie Grand, Ella and Jennifer Santi Hall, Dan Ezekiel. Grand is chair of the park advisory commission. Allen, Hall and Ezekiel are greenbelt advisory commissioners. Jennifer Hall has served as GAC chair, but her term is ending on the commission – this was her last meeting. Ella Hall also had attended the first GAC meeting with her mother seven years ago – she was three weeks old at the time. (Photo by the writer.)

They covered many of the same topics that they’d discussed at their first joint meeting in April 2010 – funding issues, land preservation and acquisition strategies, as well as specific projects like the Allen Creek greenway and support for small farms.

Ginny Trocchio of The Conservation Fund, which has a contract to manage the greenbelt and park land acquisition programs, gave commissioners an overview of finances, projects and goals. Both programs are funded by a 30-year, 0.5 mill tax for land acquisition, called the open space and parkland preservation millage, which Ann Arbor voters approved in 2003. Two-thirds of the millage proceeds are used for the greenbelt program, and one-third is allotted to park land acquisition. To get money upfront for land acquisition, the city took out a $20 million bond in fiscal 2006 that’s being paid back with revenue from the millage. Current combined fund balances for the two programs total nearly $9 million.

Trocchio also highlighted an upcoming event to celebrate the greenbelt program. On Thursday, June 16, an open house will be hosted at the Braun farm – one of the program’s protected properties in Ann Arbor Township. The event is free and open to the public, and starts at 5:30 p.m. – parking is available at 4175 Whitmore Lake Road.

At the end of the June 7 meeting, commissioners congratulated two GAC members for their service – it was the final meeting for Gil Omenn and Jennifer Santi Hall, who has served as chair. Their terms expire June 30, and it’s not clear when appointments to replace them will be made. [Full Story]

PAC Gets Update on Fuller Road Station

Ann Arbor park advisory commission meeting (May 17, 2011): This month’s PAC meeting focused on one topic – an update on the proposed Fuller Road Station, a large parking structure, bus depot and possible train station being planned on city-owned property near the University of Michigan’s medical campus.

Laptop with slide presentation on Fuller Road Station

Laptop with Fuller Road Station presentation, given by Eli Cooper, the city of Ann Arbor's transportation program manager.

Eli Cooper, the city of Ann Arbor’s transportation program manager, reprised a presentation he’s given dozens of times over the last two years to various public bodies and community groups. The newest details relate to recent federal funding earmarked for the project – $2.8 million from the Federal Rail Administration, to pay for environmental assessment and engineering at the site. Cooper admitted he had started to feel a bit like the boy who cried “Wolf!” regarding potential funding, but he noted that the “wolf” has materialized – in the form of the grant award.

The $2.8 million won’t come close to covering the estimated $121 million cost of the full project, including a rail station, which is estimated to cost about $18 million. But more than the funding itself, Cooper said, the award is significant because it indicates the FRA’s willingness to be the lead federal agency for this project.

Cooper also reported that the agreement being crafted by UM and city staff is nearing completion, and will likely be made public within a month. It will govern the construction, operation and maintenance of Fuller Road Station, and will include details about the project’s financing. Cooper told PAC that they would have the chance to review the agreement before it heads to the city council for approval. [Full Story]

Council To Get Reminder of Parks Promise

Ann Arbor park advisory commission meeting (April 26, 2011): The park advisory commission (PAC) meeting on Tuesday lasted around three hours, and concluded with a budget-related resolution that reminds the Ann Arbor city council of an administrative policy on parks budgeting.

Tim Berla, Park Advisory Commission Ann Arbor

Park advisory commissioners Tim Berla (left) and Doug Chapman (right). Berla is talking about differences in funding levels for parks as compared with the rest of the city's general fund.

PAC chair Julie Grand lamented the short notice they had received about the proposed changes to the way parks programs will be supported in the fiscal year 2012 budget – which meant that the public had little opportunity to weigh in with PAC.

On May 2, the city council is holding its public hearing on the FY 2012 budget, which the council needs to approve at its May 16 meeting. The 2012 fiscal year begins July 1, 2011.

The city’s administrative policy on parks support dates back to a measure passed by the city council in October 2006, which reads in relevant part: “If future reductions are necessary in the City’s general fund budget, during any of the six years of this millage, beginning with Fiscal Year 2007-2008, the general fund budget supporting the parks and recreation system for that year will be reduced by a percentage no greater than the average percentage reduction of the total City general fund budget.”

The policy was seen as important to assure voters that once the 2006 millage was passed, millage money would not replace general fund support for parks.

But based on city staff calculations, the portion of the city’s general fund in the proposed FY 2012 budget that supports parks would fall short of the 2006 administrative policy standard by $90,000. And some park commissioners objected to the fact that some of the money previously drawn from the general fund to support parks will now be drawn from the METRO and stormwater funds.

The stormwater fund receives revenues paid through fees based on the amount of impervious surface on a property. The METRO fund receives revenues that the state requires telecommunications companies to pay municipalities for use of the right-of-way. For purposes of the administrative policy, the city is counting the METRO funds that are supporting parks as part of the general fund.

The resolution passed by PAC called on the city council to adhere to the prevailing administrative policy. A different resolution passed by PAC expressed the body’s support for the cost-savings measures in the parks and recreation programs included in the FY 2012 budget. Besides parks and recreation programs, park operations are supported by the general fund – in the public services area of the budget. The administrative policy discrepancy lies in the park operations budget.

In other budget-related business, the commission recommended fee increases and new program fees that had been suggested by city staff. Those increases will need final authorization by the city council.

The commission also received a presentation from the Ann Arbor public art commission on a program to create murals. One of the initial sites selected for mural installation is the restroom building at Allmendinger Park. [Full Story]

Commission Makes Park Budget Recs

At its April 26, 2011 meeting, Ann Arbor’s park advisory commission (PAC) voted to recommend to the city council the staff-proposed parks and recreation budget for fiscal year 2012. The council will authorize the FY 2012 budget at its May 16 meeting. But the commission also passed a resolution asking the council to honor its promise to residents made in 2006, when voters approved a parks maintenance and capital improvements millage.

The proposed part of the budget for parks and recreation services includes savings from items like lower energy usage resulting from infrastructure energy improvements ($65,083) and eliminating underused computer software ($7,000). The parks and recreation part of the city’s roughly $80 million general fund budget is planned to be about $3.6 million.

Also part of PAC’s purview in the city budget is a portion of the field operations budget involving park operations. For park operations that are part of field operations, the city is expecting to achieve savings in the use of temporary labor to staff vacant positions ($158,248).

The promise to which the second PAC resolution refers is a measure passed by the city council in October 2006, setting forth an administrative policy, which reads in relevant part: “If future reductions are necessary in the City’s general fund budget, during any of the six years of this millage, beginning with Fiscal Year 2007-2008, the general fund budget supporting the parks and recreation system for that year will be reduced by a percentage no greater than the average percentage reduction of the total City general fund budget.” The policy was seen as important to assure voters that once the millage was passed, millage money would not replace general fund support for parks.

Based on city staff calculations, the portion of the city’s general fund in the proposed FY 2012 budget that supports parks would fall short of the 2006 administrative policy standard by $90,000. And some park commissioners objected to the fact that some of the money previously drawn from the general fund to support parks will now be drawn from the METRO fund. The METRO fund receives revenues that the state requires telecommunications companies to pay municipalities for use of the right-of-way. For purposes of the administrative policy, the city is counting the METRO funds that are supporting parks as part of the general fund.

So the second resolution passed by PAC called on the city council to adhere to the prevailing administrative policy. Julie Grand, PAC’s chair, was critical of the short notice that PAC had received on the funding change and the lack of opportunity for public comment to PAC on the issue. The city council’s public hearing on the FY 2012 budget is scheduled for May 2, as part of the city council’s meeting, which begins at 7 p.m. at council chambers, 301 E. Huron St.

This brief was filed shortly after the Washtenaw County boardroom at 220 N. Main St. A more detailed report of the meeting will follow: [link] [Full Story]

PAC Supports Grants for Skatepark, Gallup

Ann Arbor park advisory commission meeting (March 15, 2011): A meeting packed with presentations also included a last-minute addition to the agenda: Resolutions recommending support of the city’s application for grants from the Michigan Dept. of Natural Resources Trust Fund. The grants – for $300,000 each – would help fund the Ann Arbor skatepark and upgrades to the Gallup canoe livery and park.

Julie Grand, Sam Offen

Julie Grand, chair of the Ann Arbor park advisory commission, talks with PAC member Sam Offen before the start of Tuesday’s meeting. Offen was the only commissioner to vote against support of a state grant application for the Ann Arbor skatepark. (Photos by the writer.)

The resolution for Gallup passed unanimously, but commissioner Sam Offen – without comment – cast a vote against the resolution for the skatepark grant.

Also at Tuesday’s meeting, commissioner Gwen Nystuen suggested forming a committee to look more closely at the Fuller Road Station project – she felt that as stewards of the city’s parkland, PAC should take a more active role in examining the proposed parking structure, bus depot and possible train station. The project, a joint effort between the city and the University of Michigan, would be located on land that’s previously been designated as parkland, though it’s been leased to the university as a surface parking lot since the early 1990s. Nystuen did not put forward a formal resolution, and commissioners took no action on the idea.

The meeting included five presentations from various groups, including updates on the city’s two golf courses, the new Give 365 volunteer program, and a restoration project for a stretch of Malletts Creek near Huron Parkway. Commissioners also heard a proposal for a new Wednesday night farmers market, and got a mid-year financial report on the open space and parkland preservation millage. [Full Story]

PAC OKs Park Plan, Suggests Golf Fee Bump

Ann Arbor park advisory commission meeting (Feb. 15, 2011): In their main business of the afternoon, park advisory commissioners signed off on the city’s Parks and Recreation Open Space (PROS) plan – an item it had postponed from its January monthly meeting.

John Lawter, Amy Kuras, Gwen Nystuen

Before the meeting, park advisory commissioner John Lawter receives the final draft of the PROS plan from park planner Amy Kuras. Looking on is commissioner Gwen Nystuen. (Photos by the writer.)

Before approving the plan, the commission heard public commentary on the issue, as well as an update from park planner Amy Kuras about how some concerns had been addressed in revisions to earlier drafts. Later in the evening, the city’s planning commission also signed off on the plan. The PROS plan is set to come before the city council on March 7.

Heard during public commentary was criticism of the PROS plan for language it contains describing public-private partnerships for park services. One example of a potential partnership arose later in the meeting, when parks and recreation deputy manager Jeff Straw outlined a request for proposals, currently in draft form, that would explore interest from vendors in providing food concessions at park facilities.

The commission also approved a recommendation to raise fees slightly at the city’s golf courses for some items. Consideration of the fee increase came prior to the year’s regular budget decisions, so that the city council can consider and give final approval to the fee increases before the city’s golf courses open for play in the spring.

Also at the meeting, parks and recreation manager Colin Smith reviewed the parks budget presentation that had been made at a Jan. 31, 2011 city council work session. Smith also gave commissioners an update on two items concerning Argo Dam. He described how intake lines for a well that’s used for measuring water levels in the pond – so that the dam gates can regulate that level – had become clogged, and had ultimately required hiring a diver to unclog one of them.

The second Argo-related item was an update on the planned bypass channel which was recommended by the city’s park advisory commission and approved by the city council last year. Insurance issues are still being worked out with the contractor, Smith said, and construction will not start as early has had been hoped. Construction is not expected to be complete before the end of the construction season – in November.

Commissioners also agreed that before the city council approves the operating agreement between the city and the University of Michigan for the planned Fuller Road Station, they would like an opportunity to review that agreement.

At the meeting, commissioners also heard about a setback in a construction project that’s already nearing completion – renovations to the drainage system in West Park. Eight swirl concentrators were installed as a part of the project – four near the north Seventh Street entrance and four near the south entrance on Seventh. Craig Hupy, head of systems planning for the city, reported that four out of the eight swirl concentrators were in some state of failure, and that one of the four had experienced a catastrophic failure. The other four are also suspected to have problems. [Full Story]