Stories indexed with the term ‘annual public art plan’

Public Art Projects Move Forward

Ann Arbor public art commission meeting (April 23, 2014): A major public art project for East Stadium bridges will be moving to the city council for approval, following a recommendation made at this month’s Ann Arbor public art commission meeting.

Kristin "KT" Tomey, Ann Arbor public art commission, The Ann Arbor Chronicle

KT Tomey is working on a project to develop maps for walking or running tours of public art in Ann Arbor. (Photos by the writer.)

“Arbor Winds” by Massachusetts artist Catherine Widgery features elevated, stand-alone louvered glass columns that are etched with images of trees – three on each end of the bridges, on the north side of Stadium Boulevard. The same type of louvered glass panels will also be used under the bridge along South State, affixed to the wall of the underpass – five sets on each side of South State Street. The overall project has a budget of $400,000 and has been in the works since 2011. If approved by council, it will likely be installed in 2015.

Commissioners also expressed enthusiasm for a new effort proposed by KT Tomey, who hopes to develop a mobile app for walking or running routes that highlight public art in Ann Arbor and on the University of Michigan campus. As a runner herself, she noted that people look for running routes when they visit new towns. So the app could be used to promote public art both to visitors and residents alike. Her first step is putting together .pdf maps that will be downloadable from AAPAC’s website.

Another new proposal prompted concerns about process. On the day of the meeting, John Kotarski – AAPAC’s vice chair – circulated an email to commissioners proposing that the city accept three pieces of donated art from Jim Pallas, an established Michigan artist and friend of Kotarski’s. The pieces are proposed to be located in the lobby of the Justice Center, in the atrium of city hall, and outside of city hall. Although commissioners seemed supportive of the idea, some expressed concern that the proposal wasn’t following AAPAC’s guidelines for accepting gifts of art, which include setting up a review committee.

Kotarski pointed out that Pallas is 75 years old. He noted that if artists donate artwork before they die, they can deduct the cost of materials from their taxes. But after they die, their estate is taxed on the market value of that artwork. “So these artists, at this point in their lives, have a financial incentive to find a good place for their artwork,” he said. “If we can make that process simple and easy for Jim – and pleasant – then I’m sure he’s willing to go to his friends” and encourage them to donate too.

He reported that the Ann Arbor Downtown Development Authority has offered a $500 honorarium to Pallas for each donated piece. Kotarski said the three pieces have a total estimated value of $100,000. He also mentioned that Pallas’ daughter, a law professor, knows city attorney Stephen Postema and that they’ve “made arrangement to resolve any legal issues necessary to facilitate this donation.”

Kotarski told commissioners that he’s tried to assure Pallas that this will work out, but “that’s why I’m a little nervous giving him these assurances, only to have this fall through at the last minute. That’s not going to be pleasant.”

Marsha Chamberlin said she recognized the benefits of encouraging Michigan artists to donate their work. “But we are a public body, and we have procedures. I just think it’s important that we observe those rules because we don’t want to make an exception for one thing, then hold someone’s feet to the fire for something else.”

Commissioners agreed that AAPAC chair Bob Miller would work with Aaron Seagraves, the city’s public art administrator, to set up a gift selection committee to review this proposal and make a recommendation to AAPAC.

In other action, the commission approved its annual art plan for fiscal 2015, which begins on July 1, 2014. The plan includes projects that are already underway, as well as proposed capital projects to be enhanced with public art. The ongoing projects are: (1) artwork for East Stadium bridges; (2) public art at Arbor Oaks Park; (3) Canoe Imagine Art; and (4) the Coleman Jewett memorial. The proposed enhanced capital projects are street and sidewalk stamping, painting or stenciling in four locations to be determined, for a total cost of $30,000. The city council would need to approve these projects before they would move forward.

Commissioners also approved applying for a $10,000 National Endowment for the Arts Challenge America Fast Track grant. The money, if awarded, would require matching funds in an equivalent amount from other sources for a public art project at Arbor Oaks Park in southeast Ann Arbor, located near Bryant Elementary School and the Bryant Community Center.

Fundraising continues for the Coleman Jewett memorial at the Ann Arbor farmers market, but Canoe Imagine Art has stalled. The community art project is intended as a temporary art display in downtown Ann Arbor using old canoes from the city that would be repurposed as public art. The city had hoped that the Ann Arbor Convention & Visitors Bureau would take administrative responsibility for the project, but the CVB has declined. Chamberlin, who’s taking the lead on this effort, said that if workarounds can’t be found for some of the administrative issues, “we have to kiss this project good-bye.” [Full Story]

Art Commission Weighs Transitional Role

Ann Arbor public art commission meeting (March 26, 2014): At its first meeting since the city council transferred most of the money out of the public art fund, public art commissioners discussed their role as the city transitions to a new model for managing public art. The former Percent for Art program had set aside 1% for art in capital project budgets, drawing on a range of different funds. The council’s March 3, 2014 action transferred that money back to its funds of origin.

Jim Simpson, Ann Arbor public art commission, The Ann Arbor Chronicle

Jim Simpson, the newest member of the Ann Arbor public art commission, attended his first AAPAC meeting on March 26. (Photos by the writer.)

Before the council’s action on March 3, about $943,000 had been available for future public art projects. The council had halted the Percent for Art funding mechanism last year, and subsequently directed city staff to develop a transition plan for public art. The plan will be delivered to the council in October, and will likely include an emphasis on partners in the private sector and fundraising from the community. Meanwhile, future city public art will be “baked in” to selected capital projects and approved by council on a case-by-case basis.

The proposed 2015 budget – for the fiscal year beginning July 1, 2014 – includes $80,000 to cover transitional costs for public art administration. The contract for the current part-time public arts administrator, Aaron Seagraves, runs through June 30, 2014. At AAPAC’s March 26 meeting, Craig Hupy – a senior city staff member who’s drafting the transition plan – mentioned the need for a consultant to help guide this process.

Commissioners questioned what their role might be during this interim period, now that former Percent for Art funding is unavailable for future public art projects. After the discussion, AAPAC chair Bob Miller said he had initially considered suggesting that they just shut down the commission, but he’d heard input to the contrary from other commissioners. The consensus was to move forward with meetings, at least for now. AAPAC’s next meeting is on April 23 at city hall.

In other action, commissioners postponed adopting an annual public art plan, and directed Seagraves to make revisions to the draft he had proposed. They’ll consider a new version at their April meeting.

Updates about ongoing projects focused on efforts that had started before the city council pulled funding. The funds for those projects were not affected. Sculptures for a rain garden at Kingsley & First will be installed in May, and more contributions are being sought for a Coleman Jewett memorial at the Ann Arbor farmers market. A public forum to seek input on the final design for artwork at East Stadium bridges will be held on Monday, April 21 at 7 p.m. at the downtown library, 343 S. Fifth. And work on Canoe Imagine Art – a temporary art display in downtown Ann Arbor using old canoes from the city that would be repurposed as public art – continues to move forward.

It was the first meeting for Jim Simpson, who was appointed to AAPAC in February. He works for the Ann Arbor start-up Duo Security, and is an assistant at Baron Glassworks in Ypsilanti. [Full Story]

Public Art Projects Move Forward

Ann Arbor public art commission special meeting (March 7, 2013): Because attendance was low at AAPAC’s regular meeting in late February, commissioners held a special meeting the following week to wrap up items that hadn’t been addressed.

Deb Polich, Bob Miller, Ann Arbor public art commission, Arts Alliance, The Ann Arbor Chronicle

Bob Miller, right, is the new chair of the Ann Arbor public art commission. To the left is Deb Polich, executive director of the nonprofit Arts Alliance. They were attending the March 15 meeting of the city council’s public art committee, which is developing revisions to the city’s public art ordinance. (Photos by the writer.)

Commissioners voted to accept a memorial for Coleman Jewett as an official AAPAC project and to approve Sarah Gay as a volunteer project manager. Her duties would be to lead efforts for city council approval, donor relations and fundraising. John Kotarski advocated for less involvement from AAPAC, saying he hoped to streamline the project.

However, other commissioners felt it should be handled like other projects, with oversight by AAPAC. The proposal is for a bronze Adirondack chair at the Ann Arbor farmers market. The city’s market manager, Sarah DeWitt, attended the March 7 meeting and will help coordinate the project.

Commissioners also voted to increase the honorariums for artists who have been selected as finalists for a $400,000 project at the East Stadium bridge. The overall project amount remains unchanged, but honorariums were raised from $2,000 to $3,000 for each of the four finalists: Volkan Alkanoglu, based in Atlanta, Georgia; Sheila Klein of Bow, Washington; Rebar Group of San Francisco; and Catherine Widgery of Cambridge, Mass. They will be in town on April 1 for a site visit and public open house.

Another effort that’s in the early phases got a vote of support from commissioners, but no financial commitment at this point. The project will use old aluminum canoes from the city of Ann Arbor’s Argo canoe livery, which artists and community groups will turn into artwork that will be displayed throughout the downtown in 2014. Partners in the project include the Ann Arbor Area Convention & Visitors Bureau (CVB), the Main Street Area Association (MSAA), the Arts Alliance, and the Huron River Watershed Council. AAPAC is involved only in a supportive role, to help with public engagement.

The role of public engagement was part of a discussion regarding AAPAC’s annual public art plan, which is due to the city council on April 1. Some commissioners expressed frustration at the process, given the uncertainty of the public art program’s future. Ultimately, they gave guidance to Aaron Seagraves, the city’s public art administrator, to draft a plan that includes projects in highly-visible, highly-used locations, currently underserved in terms of public art.

The March 7 meeting also included the election of officers. Bob Miller was elected the new chair, replacing Marsha Chamberlin. Kotarski abstained from voting. He noted that the commission will soon be at only 40% capacity – a reference to the fact that there are three vacancies on the nine-member commission, with an additional resignation expected by Wiltrud Simbuerger in the near future.

Two of those vacancies will likely be filled shortly. Nominations are on the city council’s March 18 agenda for confirmation: Nick Zagar, an artist and commercial real estate agent who serves on the Ann Arbor Art Center board; and Ashlee Arder, programs coordinator at ArtServe Michigan.

All of these actions come in the context of the city council’s ongoing review of the city’s public art program, which began in early December of 2012. This article begins with a report on the most recent meeting of the council’s public art committee on Friday, March 15. An update of their work will be attached to the council’s March 18 agenda as an item of communication. Their next committee meeting is scheduled for March 28. [Full Story]

Long-Term Planning for Ann Arbor Public Art

Ann Arbor public art commission meeting (March 28, 2012): With four of the nine commissioners absent, AAPAC approved the budget for its next major project, allocating up to $400,000 for art tied to the East Stadium bridges reconstruction.

Rose White Park

Rose White Park, adjacent to East Stadium Boulevard, is one location being considered for public art in a $400,000 budget approved by public art commissioners for the East Stadium bridges project. The blue tarp on the fence in the background serves to separate the park from the bridge construction. (Photos by the writer.)

A task force had recommended that the project be well-funded, because the location would be a highly visible landmark marking an entrance into the city – it’s near Michigan Stadium and the Crisler Center, for example. No artist has been selected yet, nor has a request for proposals been issued – that’s under review by the city attorney’s staff.

The artist would have a large role in selecting locations for the artwork. Places for art might include the underpass and staircases at South State Street; the fence along Rose White Park, which is adjacent to East Stadium Boulevard; or the bridges themselves, spanning over railroad tracks and South State Street. Any final project and budget would require the city council’s approval.

The commission postponed action on a proposal related to artwork at Argo Cascades, the new Huron River bypass near Argo Pond. Neither of the two commissioners who serve on a task force for the project – Malverne Winborne and John Kotarski – attended the AAPAC meeting, and other commissioners felt more information was needed before moving forward.

Final touches were put on an annual public art plan for FY 2013, describing projects that AAPAC intends to work on between July 1, 2012 and June 30, 2013. [.pdf of FY 2013 annual public art plan] In addition to specific art projects like those for the East Stadium bridges and a mural at Allmendinger Park, the two-page document calls for developing a master plan for public art to guide future decision-making through 2016.

During the meeting, Aaron Seagraves – the city’s public art administrator – noted that nominations are being accepted through April 13 for the Golden Paintbrush awards, which recognize local contributions to public art. A nomination form can be downloaded from the commission’s website.

The March 28 meeting was attended by three people who were not affiliated with the commission, including Jack Urban, a Kalamazoo County commissioner and chair of the Kalamazoo public arts commission. He noted that unlike Ann Arbor, the Kalamazoo public art commission does not have a funding source. So the group is looking to establish itself and seek financial support, he said. [Full Story]

Art Commission OKs Annual Public Art Plan

At its March 28, 2012 meeting, the Ann Arbor public art commission unanimously approved a public art plan for the coming fiscal year, from July 1, 2012 through June 30, 2013. The plan had been the topic of a four-hour retreat in late February. The city’s public art ordinance requires that AAPAC submit an annual plan to the city council by April 1.

About $1.13 million in unencumbered funds remains in the current public art budget. [The city’s public art ordinance requires that 1% of all capital project budgets (up to a limit of $250,000 per project) be set aside for public art.] The plan includes a list of ongoing projects, including: (1) installation of Ed Carpenter’s “Radius” sculpture in the lobby … [Full Story]

Art Commission Retreat Set for Feb. 26

The Ann Arbor public art commission has cancelled its Wednesday, Feb. 22 meeting in lieu of a retreat scheduled for Sunday, Feb. 26 from 1-5:30 p.m. The retreat will be held at the NEW Center, 1100 N. Main St. in Ann Arbor.

No agenda has yet been posted for the retreat, but it was discussed at AAPAC’s Jan. 25, 2012 meeting in the context of developing an annual art plan for fiscal 2013, which by ordinance must be delivered to the city council by April 1. In addition to shaping the annual plan, the aim of the retreat is to develop a master plan that would provide a broader conceptual framework to guide AAPAC’s decisions.

The retreat will be open … [Full Story]

Transitions for Ann Arbor Art Commission

Ann Arbor public art commission meeting (Jan. 25, 2012): Two new commissioners – Bob Miller and John Kotarski – attended the art commission’s first meeting of 2012, and joined other AAPAC members in approving two public art projects.

Wiltrud Simbuerger

Ann Arbor public art commissioner Wiltrud Simbuerger, showing other commission members some proposals from artists for a mural at Allmendinger Park. A local artist, Mary Thiefels, has been selected for that project. (Photos by the writer.)

The group unanimously recommended selecting Ed Carpenter of Portland, Oregon for a $150,000 art project in the lobby of the city’s Justice Center, located at the corner of East Huron and Fifth Avenue. A task force had recommended the selection of Carpenter’s proposal from three finalists. It’s a sculpture called “Radius”.

Carpenter plans to create a hanging sculpture of dichroic glass, aluminum, stainless steel and lighting, including LED spot and flood lighting. Among the reasons for recommending Radius, the task force cited the sculpture’s metaphor: That the activities in the Justice Center have a “rippling” effect throughout the community, which echos the water sculpture by Herbert Dreiseitl that’s located in the plaza outside the building.

The Justice Center, a new building next to city hall, houses the 15th District Court and the Ann Arbor police department. The commission’s recommendation will be forwarded to the city council for approval.

In other action, the art commission voted to select Ann Arbor muralist Mary Thiefels for a mural project to be located on pillars at a building in Allmendinger Park. A task force had recommended her selection from among four finalists. Her proposal entails asking neighborhood residents for artifacts to create mosaics at the top and bottom of the pillars. The task force recommended that they continue to work with Thiefels on designing the remainder of the mural in the middle sections of the pillars.

Commissioners liked the concept of “found object” mosaics, but questioned whether the $10,000 budget was sufficient. They ultimately voted to approve selecting Thiefels for the project, contingent on her submission of a revised proposal and budget, with additional input from the task force. This project is the first one in a pilot mural program started last year by former commissioner Jeff Meyers.

AAPAC also discussed possible artwork for four sites connected to the East Stadium bridges, which are being reconstructed. The two commissioners who serve on a task force for that project – Wiltrud Simbuerger and Bob Miller – indicated that the budget recommendation will likely be at least $250,000 for artwork there. The task force is currently developing a request for proposals to be issued in the coming weeks.

In the context of developing their annual art plan for fiscal 2013, which by ordinance must be delivered to the city council by April 1, commissioners decided to hold a retreat next month. In addition to shaping the annual plan, the aim of the retreat is to develop a master plan that would provide a broader conceptual framework to guide AAPAC’s decisions. Input from an online survey of the public will also be used – the survey remains open until Feb. 20, and has garnered more than 400 responses so far. [Full Story]

Art Commission Plans for the Future

Ann Arbor public art commission meeting (Dec. 13, 2011): Marsha Chamberlin, who chairs the city’s public art commission, began the meeting by congratulating her colleagues on the recent defeat of a city council proposal to reduce funding for the Percent for Art program, which AAPAC oversees. “What that means is a lot of work in the next year,” she added.

Aaron Seagraves

Aaron Seagraves, Ann Arbor's public art administrator, goes over some ideas for possible programs to be funded through the city's Percent for Art program. (Photos by the writer.)

Most of AAPAC’s December meeting was spent looking forward to the coming year – discussing how to develop the next annual art plan, which is due to be delivered to the city council in April. Commissioners talked about how to increase the amount of public art funded through the city’s Percent for Art, including putting in place new programs that would expedite the process. Some city councilmembers have raised concerns that few public art projects have been completed since the Percent for Art was created in 2007. The program, overseen by AAPAC, allocates 1% for public art from all of the city government’s capital projects.

So far, only two projects have been installed: (1) a tree sculpture at West Park, and (2) a large water fountain in front of city hall. Updates on several other projects were reviewed at AAPAC’s December meeting, and several days after the meeting, action was taken toward the selection of artists for two projects. A task force for a mural in Allmendinger Park is recommending Ann Arbor muralist Mary Thiefels for that work, with a $10,000 budget. And a task force that’s selecting artwork for the lobby of the Justice Center is recommending Ed Carpenter of Portland, Oregon for that $150,000 project. AAPAC is expected to get more details and vote on both recommendations at its Jan. 25 meeting.

During Dec. 13 discussion of the annual plan, it emerged that there’s been a revision to a key constraint on Percent for Art spending: The aspect of permanence. Previously, city staff had told AAPAC that because all artwork needed to be capitalized, it had to last a minimum of five years. Now, Chamberlin reported, the city’s finance department has revised its definition of “permanent” to a minimum of two years, not five. “That does change things a lot,” she observed.

One item that fits the “permanent” requirement, but posed other concerns, was a proposed donation to the city via local attorney Kurt Berggren. The work is an eight-panel set of gates called the Global Peace Gateway, originally located at a cathedral in Los Angeles. Commissioners discussed several issues related to that donation, including the cost of transporting the work to Ann Arbor and the fact that the gates contain religious iconography. Ultimately, they voted to reject the donation.

One thing that wasn’t mentioned during the meeting: Margaret Parker’s decision to leave the commission one year before her term expired. The news was revealed later in the month at a city council meeting, when mayor John Hieftje put forward a nomination for her replacement – John Kotarski. Parker, a local artist, has served on AAPAC since its inception, including three years as its chair, and was instrumental in creating the Percent for Art program. [Full Story]