624 Church Street Gets Parking Permit Extension

The  developer of the future 624 Church St. project in downtown Ann Arbor will now be able to extend for up to 15 years – for a total of 30 years – the contracts for 48 already-approved parking permits under the city’s contribution-in-lieu (CIL) program.

The Ann Arbor Downtown Development Authority board’s action to approve up to three five-year extensions came at its Jan. 8, 2014 meeting.

At its meeting on Nov. 6, 2013, the DDA board had already approved the purchase of 48 parking permits under the contribution-in-lieu (CIL) program – for a new version of the proposed residential development at 624 Church St. in downtown Ann Arbor. The spaces were approved to be provided in the Forest Avenue parking … [Full Story]

Revised 624 Church St. Gets Parking OK

A revision to a proposed residential development at 624 Church St. in downtown Ann Arbor has resulted in approval by the Ann Arbor Downtown Development Authority board for the purchase of additional monthly parking permits – up to 48 such permits. The action was taken at the DDA board’s Nov. 6, 2013 meeting. The spaces will be provided in the Forest Avenue parking structure.

The original proposal for 624 Church, which received site plan approval from the city council at its March 4, 2013 meeting, was for a 13-story, 83-unit apartment building with approximately 181 beds. And for that version, the Ann Arbor DDA had authorized the project to purchase up to 42 monthly permits through the city’s contribution-in-lieu (CIL) … [Full Story]

Varsity Allowed to Purchase Parking Permits

The Varsity residential development has been granted the right to purchase two monthly permits in Ann Arbor’s public parking system, in order to satisfy the project’s 76-space parking requirement under the city’s zoning regulations. The project, located on East Washington Street, is a 13-story, 173-unit, 178,380-square-foot apartment building for approximately 418 people. Construction on the project is well underway.

The vote by the Ann Arbor Downtown Development Authority board came at its Jan. 9, 2013 meeting. The DDA manages the public parking system – including parking permits – under contract with the city. The DDA in turn subcontracts out the day-to-day parking operations to Republic Parking.

The developer of The Varsity had originally planned to satisfy its parking requirement through a contract … [Full Story]