Stories indexed with the term ‘downtown library’

Downtown Library to Reopen Friday, Aug. 22

The downtown Ann Arbor District Library at 343 S. Fifth Ave. will reopen on Friday, Aug. 22 after being closed over the past week for repairs to its public elevator. There will be another temporary closing next week, however, as that work continues.

In a post on her director’s blog, Josie Parker stated: ”The last phase of the work is scheduled for next week, and we anticipate another closure for the installation of the new jack. That work is scheduled to occur on Wednesday, August 27.”

On Aug. 13, the library announced that its downtown building would be closed indefinitely starting the following day. The elevator has been out of commission since this spring, after leaks had developed in the hydraulic piston, causing … [Full Story]

AADL Makes Infrastructure Investments

Ann Arbor District Library board meeting (July 21, 2014): Action at the July board meeting allocated in total nearly $570,000 toward three infrastructure projects, mostly related to the downtown library. A special meeting on July 29 added $75,000 to that amount.

Rachel Coffman, Ann Arbor District Library, The Ann Arbor Chronicle

Rachel Coffman spoke during public commentary to earn points in the AADL summer game. (Photos by the writer.)

Most of the funding was for renovations of the downtown library’s front entrance. The board authorized a $425,523 construction budget for that project at 343 S. Fifth Ave., which has been in the works for several months. The budget covers new doors, a redesigned facade, and heated sidewalks, among other changes. The construction manager is O’Neal Construction of Ann Arbor.

Also related to the downtown library, trustees authorized a $93,598 contract with Schindler Elevator Corp. to repair the public elevator, which has been out of commission since this spring.

A week after the July 21 meeting, the board called a special meeting for July 29 to address additional issues related to the elevator. The four board members present at that meeting voted to authorize an additional $75,000 for elevator work.

Because of the elevator repair work, the Friends of the AADL bookshop is now located in the main first-floor lobby of the downtown building, rather than its normal location in the lower level, which is closed. It’s been in the lobby since June 30, and is open all of the hours that the building is open. Books are sold at the circulation desk.

The third infrastructure project approved on July 21 was $50,000 for carpet replacement in parts of the downtown library, as well as at the branch located at the Westgate Shopping Center.

The money for all three projects will be taken from the fund balance, which stood at $8.17 million as of June 30.

In other action on July 21, the board approved five adjustments to the 2013-14 budget, for the prior fiscal year ending June 30, 2014. The adjustments totaled $96,300.

Public commentary was dominated by fans of AADL’s summer game – in part because they could earn points by speaking to the board. Other issues raised during public commentary included concerns about communication, outreach to underserved populations, the cost of renovations to the downtown library entrance, and the “purging” of reference books.

The board’s August meeting is canceled. The next scheduled board session is on Sept. 15. [Full Story]

Library Entrance Project Takes Next Step

The Ann Arbor District Library board has authorized the library director to negotiate with O’Neal Construction Inc. for work related to the downtown library entrance. The action came at the board’s May 19, 2014 meeting.

O’Neal would be contracted to provide construction management services. This is the next step in a process that began several months ago.

At the board’s April 21, 2014 meeting, the board had authorized the library director, Josie Parker, to hire a construction manager for the project. Board members also allocated $18,580 from the fund balance to pay InForm Studio for construction documents. InForm Studio, the architecture firm that previously designed AADL’s Traverwood branch, gave an update on the process at that same meeting.

The existing teal porcelain panels that … [Full Story]

Library Moves Ahead on Downtown Facade

A renovation of the downtown library’s front entrance took a step forward, following action by the Ann Arbor District Library board at its April 21, 2014 meeting.

Ann Arbor District Library, InForm Studio, The Ann Arbor Chronicle

Rendering of the new design for the Ann Arbor District Library’s downtown building entrance. (Image by InForm Studio.)

The board authorized the library director, Josie Parker, to hire a construction manager for the project. Board members also allocated $18,580 from the fund balance to pay InForm Studio for construction documents. InForm Studio, the architecture firm that previously designed AADL’s Traverwood branch, has been working on this project for several months. An update was given … [Full Story]

New Entrance Planned for Downtown Library

Plans for a major redesign to the exterior front entrance of the Ann Arbor District Library’s downtown building at 343 S. Fifth Ave. will move forward, following approval by the AADL board at its Feb. 17, 2014 meeting.

Ann Arbor District Library, The Ann Arbor Chronicle

Rendering of new entrance design for the downtown location of the Ann Arbor District Library.

The vote followed a presentation of the redesign by Cory Lavigne of InForm Studio, which is handling the project. The architecture firm designed AADL’s Traverwood branch. A final design will likely be brought forward for approval at the board’s April meeting, following a public forum in mid-March.

The entrance … [Full Story]