Bonds OK’d for Allen Creek Drain Project

Washtenaw County commissioners authorized backing bonds for a drain project along Miller Avenue in Ann Arbor – in the Allen Creek drainage district – with the county’s full faith and credit. The unanimous vote took place at the county board’s Feb. 20, 2013 meeting, following initial approval on Feb. 6, 2013.

The backing is for up to $1.58 million in bonds for the project, which will repaid through a special assessment against the city of Ann Arbor. The project is being handled by the office of the Washtenaw County water resources commissioner, led by Evan Pratt. It’s the first project brought forward by Pratt, who took office in January.

According to a staff memo, the funds will be used “to … [Full Story]

County Backs Bond for Ann Arbor Drain Project

Funding for a drain project along Miller Avenue in Ann Arbor – in the Allen Creek drainage district – took a step toward being backed by Washtenaw County’s full faith and credit, following initial approval at the county board’s Feb. 6, 2013 meeting. A final vote is expected on Feb. 20.

The backing is for up to $1.58 million in bonds for the project, which will repaid through a special assessment against the city of Ann Arbor. The project is being handled by the office of the Washtenaw County water resources commissioner, led by Evan Pratt. It’s the first project brought forward by Pratt, who took office in January. Pratt attended the Feb. 6 meeting but did not formally address the … [Full Story]

Four County Drain/Water Projects OK’d

At its July 11, 2012 meeting, the Washtenaw County board of commissioners approved backing the bonds for four projects proposed by the county’s water resources commissioner, including three in Ann Arbor.

The three Ann Arbor projects are: (1) stabilizing Traver Creek as it runs through the Leslie Park Golf Course, costing up to $1.805 million; (2) providing stormwater retention and infiltration from the road surface using porous asphalt on Willard Street, in the Allen Creek drain district and costing up to $345,000; and (3) providing bio-retention and stormwater capture via reforestation as part of a Huron River “green infrastructure” project, costing up to $345,000.

The Ann Arbor projects require the county to give its full faith and credit, although the payment of bonds … [Full Story]

Initial OK for Sugar Creek Drain Bonds

Acting on a request from water resources commissioner Janis Bobrin, the Washteanw County board of commissioners gave initial approval to pledge the county’s full faith and credit for up to $270,000 in bonds to fund an extension of the Sugar Creek drainage district.

The project – which in total is budgeted at $349,899 – was requested by the Washtenaw County road commission. It entails relocating a portion of the county drain, including a section of 1,850 feet adjacent to Platt Road between Judd and Stoney Creek roads in York Township. A second phase includes removing sediment and vegetation, as well as making wingwall repairs, at the drain crossings of US-23, McCrone Road, and Gooding Road.

The Sugar Creek drainage district covers parts of York … [Full Story]

Commission OKs FY 2013 Parks Budget

Ann Arbor park advisory commission meeting (April 17, 2012): The action items at this month’s PAC meeting focused on the upcoming fiscal year, with parks-related budget recommendations for July 1, 2012 through June 30, 2013. Sam Offen, who chairs PAC’s budget and finance committee, observed that the FY 2013 budget is in better shape than in recent years.

Christopher Taylor, Sam Offen

At left is city councilmember Christopher Taylor (Ward 3), who also serves as an ex officio member of the Ann Arbor park advisory commission. To the right is Sam Offen, chair of PAC's budget and finance committee. (Photos by the writer.)

This is the second year of a two-year budget cycle, and commissioners had recommended approval of budgets for both years at their April 2011 meeting. The recent recommendations for FY 2013 include: (1) increasing the frequency of the mowing cycle from every 19 days to every 14 days; (2) increasing seasonal staffing between April 15–October 15 to maintain active recreation areas better; (3) establishing three seasonal park steward/supervisor positions to improve park maintenance and enforcement; and (4) increasing seasonal staffing at the ice arenas to improve facility cleanliness.

Fee increases at several parks and rec facilities are also part of the budget recommendations, but most have already been implemented in the current fiscal year.

The April 17 meeting included a public hearing on the renewal of the city’s park maintenance and capital improvements millage, which will likely be on the November 2012 ballot. No one spoke at the hearing. In general, “there seems to be a great deal of relative silence” about the millage, parks and rec manager Colin Smith told commissioners. Few people have attended the recent public forums held by parks staff. The final forum is set for Thursday, April 26 from 6:30-7:30 p.m. at the Ann Arbor District Library’s Traverwood branch, 3333 Traverwood Drive.

Parks staff gave an update on deteriorating conditions at Windemere Park’s two tennis courts, and provided an initial estimate on costs to replace one or both courts at that location. No formal recommendation has been made, but options include moving the courts to another park. Commissioners discussed the need to assess the distribution and conditions of all of the city’s public courts – including ones in the public school system – as well as their overall usage, to get a better idea of where the greatest needs are.

Another update came from an engineer at the Washtenaw County water resources commissioner’s office, who described a drain replacement project that will affect Veterans Memorial Park later this year. Also related to Veterans Memorial, the request for proposals (RFP) for a skatepark there has been issued. [.pdf of skatepark RFP] The goal is to solicit proposals for a consultant to handle design and oversee construction of the skatepark, which will be located on city-owned property.

During public commentary, commissioners were given an update on the nonprofit Project Grow, which has several gardens located in city parks and is celebrating its 40th anniversary this year. Another speaker urged commissioners to take control of the parking lots in city parks, and possibly increase revenues by installing metered parking. [Full Story]

Bonds OK’d for York Twp. Drain Project

At its Dec. 7, 2011 meeting, the Washtenaw County board of commissioners authorized the county’s full faith and credit to back the payment of bonds used to repair sinkholes and replace broken tile in a drain along Saline-Milan Road in York Township. [.pdf of map showing project area]

The amount of the bonds is not to exceed $235,000, and will be retired in part through special assessments against the property owners in that area’s drainage district. Money from assessments will account for 69.16% of the project cost, with remaining project costs prepaid by York Township (20%), and Washtenaw County (10.84%). The Wasthenaw County road commission will pay half of the county’s portion of this project, which is being managed by the county … [Full Story]

Ann Arbor Drain Projects Get Initial OK

At its June 1, 2011 meeting, the Washtenaw County board of commissioners gave initial approval to five projects planned by the county’s water resources commissioner.

The projects, which require the county to back bond payments totaling up to $6.54 million, are all located in Ann Arbor: (1) Allen Creek drain cistern installation, downspout disconnection and tree planting – up to $330,000; (2) County Farm drain stream bank stabilization – up to $1.2 million; (3) Malletts Creek drain/Burns Park porous alley; Malletts Creek cistern installation, downspout disconnection, and tree planting; and Malletts Creek stream bank stabilization – up to $3.48 million; (4) Swift Run cistern installation, downspout disconnection, and tree planting – up to $75,000; and (5) Traver Creek cistern installation, downspout … [Full Story]

Loan Request Pulled for Packard Square

Washtenaw County board of commissioners chair’s briefing (May 24, 2011): Developers for the Packard Square project in Ann Arbor have decided not to apply for a state loan that had spurred debate among county commissioners. The board was told of the decision at a May 24 agenda briefing.

At their meeting last week on May 18, Washtenaw County commissioners had postponed action on a request to approve a $1 million loan application to the state Dept. of Environmental Quality for brownfield cleanup at the former Georgetown Mall site. Developers were asking to use the county’s full faith and credit as a guarantee for the loan – a request that caused concern over entering into a relationship with a private developer that might pose a financial risk for the county.

The board was expected to take up the request again at their June 1 meeting, along with consideration of a broader public-private investment policy they’re developing, which was also postponed from the May 18 meeting. But now that there’s no loan in play, commissioners seemed inclined to defer action on the policy as well, giving the county’s attorney more time to analyze the issue.

Other items previewed from the June 1 agenda include: (1) five drain projects in the city of Ann Arbor that require bonds backed by the county’s full faith and credit, totaling $6.54 million; (2) acceptance of $455,000 in federal stimulus funds for the county’s weatherization program, which has already received over $4 million in grants over the past three years, and (3) approval of a new public health medical director. The current director, Diana Torres-Burgos, recently announced her resignation – she’ll be leaving her job at the end of June. [Full Story]

Water Main Project Set for Bryant Area

Jerry Hancock

Jerry Hancock, Ann Arbor's stormwater and floodplain programs coordinator, explains how soil composition in the Bryant neighborhood factors in the area's water problems. (Photos by the writer.)

A major project to replace water mains and resurface roads in the Bryant neighborhood will get under way this spring, part of a broader plan to address the area’s chronic drainage problems and other issues.

At a Jan. 14 neighborhood meeting, Ann Arbor city staff gave an overview of the project, which included an historical look at the subdivision off  Stone School Road, just south of I-94.

The meeting at the Bryant Community Center – organized by the nonprofit Community Action Network and attended by residents, city and county elected officials and staff, among others – is the latest in a series of efforts to deal with a wide range of challenges to one of the city’s predominantly low-income neighborhoods.

At the end of Thursday’s two-hour session, a question raised by one of the residents – “Is there a happy ending to all of this?” – might best be summarized by the answer, “It depends.” [Full Story]