Stories indexed with the term ‘park maintenance and capital improvements millage’

West Park Possible Location for New Dog Park

Ann Arbor park advisory commission meeting (Oct. 16, 2012): Creation of a new, more centrally located Ann Arbor dog park moved forward this month, as park commissioners reached an informal consensus to explore West Park for that purpose.

Ann Arbor parks millage renewal, Ann Arbor park advisory commission, The Ann Arbor Chronicle

Signs for Ann Arbor parks millage renewal. PAC member Ingrid Ault has formed a campaign committee – called Friends of the Parks – to support the renewal. (Photos by the writer.)

A committee that has focused on identifying possible locations for a new dog park recommended the West Park site – specifically, a parcel in the park’s northeast corner, where the city recently bought and demolished a house near the entrance off of Chapin Street. No formal vote was taken, but PAC’s support means that staff will bring back a proposal for PAC’s consideration, and hold a public meeting for community input.

PAC members did formally vote on a recommendation to relocate tennis courts within Windemere Park, to the east of the current location. Several residents of the neighborhood surrounding Windemere Park attended the meeting and advocated for a postponement on the decision. They noted that the option being recommended by staff had not been presented at an Oct. 8 neighborhood meeting. Colin Smith, the city’s parks and recreation manager, later explained that the fourth option had emerged from a consensus of ideas at the meeting.

Berla, who voted against the PAC resolution, felt there was nothing to lose in giving residents another month to review the proposal. But other commissioners believed that moving ahead was the best approach, and that no option would satisfy all residents – especially people with property facing the park. The resolution also recommended incorporating input from residents regarding landscaping around the courts, which was a concern raised by some of the homeowners.

In an unusual move, PAC member Ingrid Ault spoke to her fellow commissioners during public commentary. Telling them that she was speaking as a citizen, not a commissioner, Ault said she had formed a campaign committee – called Friends of the Parks – to support the park maintenance & capital improvements millage renewal, which is on the Nov. 6 ballot. The current 1.1 mill tax expires this year. A renewal would run from 2013-2018 and raise about $4.9 million next year. Ault brought yard signs to distribute, and encouraged commissioners and the public to support the renewal. PAC had passed a resolution in support of the millage at their June 2012 meeting.

As part of his manager’s report, Colin Smith noted that city staff will be meeting with representatives from the state on Nov. 2 to get a better understanding of concerns that have been raised regarding a planned whitewater section of the Huron River, near Argo Cascades. He said he’d have an update on that situation at PAC’s November meeting. [See Chronicle coverage: “EPA, Others Object to Whitewater Project.”]

Commissioners held their annual officer elections, re-electing Julie Grand as chair. Ingrid Ault was elected vice chair and Tim Doyle was tapped as chair of PAC’s budget and finance committee. All nominations were uncontested, and the votes were unanimous. PAC also welcomed Missy Stults to her first meeting as commissioner. Her nomination had been confirmed by the city council earlier this month. [Full Story]

Park Maintenance Millage on Ann Arbor Ballot

Ann Arbor voters will be asked on Nov. 6, 2012 to renew the parks maintenance and capital improvements millage at the rate of 1.1 mills. The vote to place the question on the Nov. 6 ballot was taken by the Ann Arbor city council at its Aug. 9 meeting. It was a unanimous vote.

The city’s park advisory commission had voted at its June 19, 2012 meeting to recommend that the council put the millage renewal on the ballot. The current 1.1 mill tax expires this year. A renewal would run from 2013-2018 and raise about $5 million next year. The recommended allocation of revenues is 70% for park maintenance activities, and 30% for park capital improvement projects. Of that allocation, up to … [Full Story]

Parks Group Acts on Skatepark, Millage

Ann Arbor park advisory commission meeting (June 19, 2012): Park commissioners took action on three items that now will likely be on the Ann Arbor city council’s July 16 agenda: (1) a contract for the design of a proposed Ann Arbor skatepark, (2) path renovations at Leslie Science & Nature Center, and (3) a parks millage renewal.

Francie Krawcke with a snowy owl

Francie Krawcke, raptor program director with the Leslie Science & Nature Center, brought a snowy owl to the June 19, 2012 meeting of the Ann Arbor park advisory commission. The owl did not fly around council chambers, but did enjoy a few snacks at the meeting. (Photos by the writer.)

An $89,560 contract with Wally Hollyday Skateparks – for design and construction oversight of a new skatepark at Veterans Memorial Park – was unanimously recommended for approval. Trevor Staples, president of the Friends of the Ann Arbor Skatepark, was on hand to answer questions, and several commissioners congratulated him for spearheading this project. Staples noted that fundraising is still underway, focused now on building a $100,000 endowment for future maintenance. Funding for design and construction of the skatepark has been secured primarily from a $300,000 state grant and $400,000 from the Washtenaw County parks & recreation commission.

PAC also unanimously recommended approval of a $115,309 contract with JB Contractors Inc. to build barrier-free pathways at the Leslie Science & Nature Center. The recommendation includes a 10% contingency, for a total project cost of $126,840.

This first phase of a broader renovation project on the center’s grounds will include making the raptor enclosures – housing owls, falcons, a bald eagle and other birds of prey – more accessible. The center, located at 1831 Traver Road, was previously part of the city’s parks system, but since 2007 has operated as an independent nonprofit. However, the city still owns and maintains the buildings and property.

Also unanimously recommended for approval was placement of a millage renewal on the Nov. 6 ballot. The current 1.1 mill Ann Arbor park maintenance and capital improvements millage expires this year. A renewal would run from 2013-2018 and is expected to generate about $4.9 million next year.

The June 19 meeting included a quarterly financial update, and the election of Tim Doyle as chair of PAC’s budget and finance committee. Commissioners also were briefed on a Traver Creek streambank stabilization project at Leslie Park golf course, designed to improve the water quality of this Huron River tributary.

Other water-related issues were brought up during the parks and recreation manager’s report. Colin Smith told commissioners that final repairs on swirl concentrators at West Park – designed to help stormwater management – will start later this month, with final renovations of the park occurring over the summer. And city staff will be harvesting Eurasian watermilfoil from about 6-7 acres around the Gallup Park canoe livery, using what Smith described as a “Zamboni on the water.” The aquatic plants have overgrown the area around the livery, making it hard for people to use paddleboats, canoes and kayaks.

During public commentary, Alan Haber urged commissioners to support the Library Green project, a citizen-led effort to put a public commons on top of the new city-owned Library Lane underground parking structure. He invited PAC to a July 14 “Imagine a Park” block party on the site, from noon until 5 p.m. Later in the meeting, park commissioner Tim Berla picked up the idea, saying he wasn’t advocating for that particular project but that he felt PAC should be “in the game” for discussions of a downtown park.

The June 19 meeting was the last one for commissioner David Barrett, who is term-limited after serving two three-year terms. PAC chair Julie Grand praised his work, particularly in advocating for renovations to the city’s athletic fields and ballparks. The mayor has not yet publicly put forward a nomination for Barrett’s replacement. [Full Story]

Parks Group Recommends Tax Renewal

A 1.1 mill renewal of the Ann Arbor park maintenance and capital improvements millage will be on the Nov. 6 ballot, if the city council follows a unanimous recommendation of the Ann Arbor park advisory group. PAC voted at its June 19, 2012 meeting to recommend that the council put the millage renewal on the ballot.

The current 1.1 mill tax expires this year. A renewal would run from 2013-2018 and raise about $4.9 million next year. The recommended allocation of revenues is 70% for park maintenance activities, and 30% for park capital improvement projects. Of that allocation, up to 10% can be shifted between the two categories as needed.

Examples of park maintenance activities include “forestry and horticulture, natural area preservation, park operations, … [Full Story]

Commission OKs FY 2013 Parks Budget

Ann Arbor park advisory commission meeting (April 17, 2012): The action items at this month’s PAC meeting focused on the upcoming fiscal year, with parks-related budget recommendations for July 1, 2012 through June 30, 2013. Sam Offen, who chairs PAC’s budget and finance committee, observed that the FY 2013 budget is in better shape than in recent years.

Christopher Taylor, Sam Offen

At left is city councilmember Christopher Taylor (Ward 3), who also serves as an ex officio member of the Ann Arbor park advisory commission. To the right is Sam Offen, chair of PAC's budget and finance committee. (Photos by the writer.)

This is the second year of a two-year budget cycle, and commissioners had recommended approval of budgets for both years at their April 2011 meeting. The recent recommendations for FY 2013 include: (1) increasing the frequency of the mowing cycle from every 19 days to every 14 days; (2) increasing seasonal staffing between April 15–October 15 to maintain active recreation areas better; (3) establishing three seasonal park steward/supervisor positions to improve park maintenance and enforcement; and (4) increasing seasonal staffing at the ice arenas to improve facility cleanliness.

Fee increases at several parks and rec facilities are also part of the budget recommendations, but most have already been implemented in the current fiscal year.

The April 17 meeting included a public hearing on the renewal of the city’s park maintenance and capital improvements millage, which will likely be on the November 2012 ballot. No one spoke at the hearing. In general, “there seems to be a great deal of relative silence” about the millage, parks and rec manager Colin Smith told commissioners. Few people have attended the recent public forums held by parks staff. The final forum is set for Thursday, April 26 from 6:30-7:30 p.m. at the Ann Arbor District Library’s Traverwood branch, 3333 Traverwood Drive.

Parks staff gave an update on deteriorating conditions at Windemere Park’s two tennis courts, and provided an initial estimate on costs to replace one or both courts at that location. No formal recommendation has been made, but options include moving the courts to another park. Commissioners discussed the need to assess the distribution and conditions of all of the city’s public courts – including ones in the public school system – as well as their overall usage, to get a better idea of where the greatest needs are.

Another update came from an engineer at the Washtenaw County water resources commissioner’s office, who described a drain replacement project that will affect Veterans Memorial Park later this year. Also related to Veterans Memorial, the request for proposals (RFP) for a skatepark there has been issued. [.pdf of skatepark RFP] The goal is to solicit proposals for a consultant to handle design and oversee construction of the skatepark, which will be located on city-owned property.

During public commentary, commissioners were given an update on the nonprofit Project Grow, which has several gardens located in city parks and is celebrating its 40th anniversary this year. Another speaker urged commissioners to take control of the parking lots in city parks, and possibly increase revenues by installing metered parking. [Full Story]

Park Commission Briefed on Millage Renewal

Ann Arbor park advisory commission meeting (March 20, 2012): At their monthly meeting, park advisory commissioners were briefed on two millages that help fund Ann Arbor’s park system, including one that will likely be on the November ballot for renewal.

Ducks in West Park

Creatures in West Park will not be able to participate in the November millage vote, even though they apparently can get their ducks in a row. A parks millage that's up for renewal helped pay for some of the recent renovations to the park, including the boardwalk, bandshell plaza and entry stairs. (Photos by the writer.)

The park maintenance and capital improvements millage, a six-year tax, brings in about $5 million annually and accounts for about 45% of the parks budget – including the entire funding for the natural areas preservation (NAP) program. Voters will likely be asked to renew it at 1.1 mills from 2013-2018, assuming the city council votes to put the millage on the Nov. 6 ballot at that rate. PAC chair Julie Grand – who has served on a working group to strategize about the renewal – said concerns about the economic climate are a major reason why an increase isn’t being recommended.

During the millage discussion, city councilmember Mike Anglin said he supports the millage but has concerns about Fuller Park, noting that talks regarding Fuller Road Station aren’t over. Parks manager Colin Smith pointed out that no millage funds have been or would be spent on Fuller Road Station. Grand cautioned against connecting the millage renewal to Fuller Road Station, saying it’s important to inform the public clearly about what the renewal means.

To provide that information, the city plans to hold four public forums in April, and a public hearing on the millage will be scheduled for PAC’s April 17 meeting. The city also plans to launch a website in early April with more information about the millage.

Also at the March 20 meeting, commissioners got a mid-year update about the open space and parkland preservation millage, which funds the greenbelt program and park acquisitions. Fuller Road Station was a backdrop to this discussion too, when commissioner Gwen Nystuen asked about protections that are afforded land acquired through this millage.

Land acquisition also came up in two other contexts during the meeting. The future of property owned by MichCon – located north of Broadway Street, between the Huron River and the railroad tracks – was part of the discussion during an update on environmental cleanup at the site. A DTE Energy representative indicated that senior management sees the potential for redevelopment there, but no plans are finalized. It’s expected that DTE Energy, which owns the property through its MichCon subsidiary, will eventually sell the site.

And speaking during public commentary, Ann Arbor resident Larry Baird advocated for the city to acquire land to fill gaps in the Border-to-Border Trail, which roughly follows the Huron River. Specifically, he characterized a connection between Bandemer Park and Barton Nature Area as the top priority, and urged the city to focus more on this project than on high-speed rail.

In the agenda’s one action item, commissioners recommended awarding a $79,980 contract to Michigan Recreational Construction Inc. to handle renovations at Placid Way Park. The resolution also recommends an additional 10% contingency of $7,998 for a total project cost of $87,978. The 1.32-acre neighborhood park is located on the city’s north side near the larger Dhu Varren Woods Nature Area and Foxfire South Park. The project would be funded from the park maintenance and capital improvements millage. [Full Story]

Parks Tax Renewal Likely on Fall Ballot

At a March 12, 2012 work session, the Ann Arbor city council received a presentation on the city’s park maintenance and capital improvements millage, a six-year tax that expires this year. The recommendation presented to the council is to ask voters this November to renew the 1.1 mill tax for another six years. The rationale for renewing, instead of increasing or decreasing it, was based on the assessment that the funding is sufficient, but also that it is well used to maintain infrastructure in the parks.

Although last year one councilmember had expressed interest in possibly funding all parks expenses from the millage, the council as a whole did not subsequently express much interest in that scenario, which would have required roughly … [Full Story]

Ann Arbor Park Improvements In the Works

Ann Arbor park advisory commission meeting (Feb. 28, 2012): Commissioners took action on several parks projects at their most recent meeting, and were briefed on others already in the works.

Colin Smith

Colin Smith, Ann Arbor's parks and recreation manager, signs sheets from more than a dozen local high school students attesting that they had attended the Feb. 28, 2012 meeting of the city's park advisory commission, as part of a class assignment. (Photos by the writer.)

The largest of the action items was a $865,190 contract for road, parking, pathway and other exterior renovations at Buhr Park and Cobblestone Farm. The work will include resurfacing the entry road off of Packard, and improving the path system to allow better access within the park area, as well as a connection from Essex Street into the park. The city council later approved the project at its March 5 meeting.

Commissioners also recommended approval of a 15-foot landscaping buffer in Riverside Park, next to a proposed new DTE Energy substation that abuts the park. DTE is seeking a variance from the city code, which requires a land use buffer for any commercial site that’s adjacent to a park – without the variance, that buffer would need to be located on DTE property. The new substation, to be located in the utility company’s Ann Arbor service center at 984 Broadway, will provide more electrical power to the downtown area due to increased demand.

Also recommended for approval was a $35,200 contract for restroom renovations at the Ann Arbor Senior Center. The facility will be closed in May while the project is completed, and activities will be scheduled at other locations. When PAC chair Julie Grand said she was impressed to see that so many companies had bid on the project, parks manager Colin Smith noted that it might reflect changes related to CUB agreements.

To comply with new state legislation, last summer the city council rescinded a resolution that had previously required contractors for city projects to execute Construction Unity Board (CUB) agreements. The agreements are negotiated between local trade unions and contractors, and require that contractors abide by terms of collective bargaining agreements for the duration of the construction project.

At their Feb. 28 meeting, park commissioners were also updated on a project to make exterior improvements – primarily related to pedestrian pathways – at the Leslie Science & Nature Center. The center, located at 1831 Traver Road, was previously part of the city’s parks system but since 2007 has operated as an independent nonprofit. However, the city still owns and maintains the buildings and property. The first stage of the project will focus on making pathways to the center’s popular raptor enclosures more accessible.

Commissioners also learned that during the week of March 12, the city will begin to install a new pedestrian bridge at the end of the Argo Dam bypass. Because of the construction, the recently renovated bypass will be temporarily closed. A stoplog will be put in to stop the flow of water into the bypass – the project will likely take a couple of weeks. The path along the bypass is expected to be paved later in April, with the end in sight for the entire project by May.

Smith reported that Argo Cascades will be the new name for the bypass – a series of drop pools that eliminates the need to portage along that stretch.

During an update on the parks and recreation budget, Smith reported that due to extra funds available from the park operations budget, plans are in the works to: (1) restore mowing to a 14-day cycle – the cycle has in recent seasons been every 19 days; (2) increase seasonal staffing between April 15 and Oct. 15; and (3) hire three park rangers from May through September, to deal better with maintenance and enforcement issues in the parks.

Several items were also raised during the time set aside for communications. Smith noted that the six-year, 1.1 mill parks maintenance and capital improvements millage will be coming up for renewal this fall. Staff has already started working on the renewal process, gathering materials in preparation for a March 12 city council working session. The millage was last approved in 2006.

It was also noted that two key staff members are leaving their jobs soon. Molly Notarianni, the city’s market manager, is stepping down at the end of March after about four years on the job. The position has already been posted. And long-time Rec & Ed director Sara Aeschbach will be retiring this summer. Both were praised for their service.

At the end of the meeting, commissioner Gwen Nystuen reminded her PAC colleagues about an upcoming sustainability forum on Thursday, March 8 at 7 p.m. in the downtown Ann Arbor District Library building. It’s the third in a series of four, this one focusing on climate and energy, and is part of a broader sustainability project that began last year and includes developing sustainability goals for the city. [See Chronicle coverage of the first and second forums in the series.] A public forum on the forums is also scheduled for March 29 from 6-8 p.m. at the downtown Ann Arbor District Library building, 343 S. Fifth Ave. [Full Story]