Traffic light at Platt & Washtenaw is operating; store signs are up in the new shopping center.
Stories indexed with the term ‘Arbor Hills Crossing’
Platt & Washtenaw Easements Approved
The Ann Arbor city council has approved three separate land-related items in connection with the Arbor Hills Crossing project at Platt & Washtenaw.
Two of the items were easements – for a sidewalk and for bus shelters and bus pullouts.
The other item was the dedication of additional public right-of-way, so that Platt Road can be widened at that intersection. New traffic signals have been installed at the intersection, but they are not yet operational.
The council had approved the site plan for Arbor Hills Crossing at its Nov. … [Full Story]
Arbor Hills Crossing Revisions OK’d
At its April 2, 2012 meeting, the Ann Arbor city council approved revisions to the building plans for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw.
The project involves tearing down three vacant commercial structures and putting up four one- and two-story buildings throughout the 7.45-acre site – a total of 90,700-square-feet of space for retail stores and offices. Three of the buildings would face Washtenaw Avenue, across the street from the retail complex where Whole Foods grocery is located. The site would include 310 parking spaces.
According to the planning staff memo accompanying the resolution, the buildings are proposed to remain in the same configuration that the city council approved at its Nov. 21, 2011 … [Full Story]
County OKs Arbor Hills Brownfield Plan
At its Jan. 18, 2012 meeting, the Washtenaw County board of commissioners gave final approval to a brownfield plan for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw in Ann Arbor. The Ann Arbor city council approved the plan at its Nov. 21, 2011 meeting, and the county board had given initial approval on Dec. 7.
The project involves tearing down three vacant commercial structures and putting up four one- and two-story buildings throughout the 7.45-acre site – a total of 90,700-square-feet of space for retail stores and offices. Three of the buildings would face Washtenaw Avenue, across the street from the retail complex where Whole Foods grocery is located. The site would include 310 parking … [Full Story]
County Board Votes on Brownfield Plans
Action was taken on two brownfield plans during the Dec. 7, 2011 meeting of the Washtenaw County board of commissioners.
The board gave final approval to a brownfield plan for Ford Motor Co’s Rawsonville plant, after holding a public hearing on the plan earlier in the meeting. The plan would allow Ford to apply for $625,000 in Michigan Business Tax credits. According to a staff memo, the plan – with the potential tax credits – would allow the company to retain 260 jobs by bringing back work that’s currently done in China and Mexico. Investment in 2012 would be about $20 million, with total jobs stabilized at about 700 workers.
Commissioners also give initial approval to a brownfield plan for Arbor Hills … [Full Story]
Initial OK: Less Art Money, Bigger Greenbelt
Ann Arbor city council meeting (Nov. 21, 2011): After the ceremonial swearing in of councilmembers who won their elections on Nov. 8, the council devoted more time to deliberations on modifying its public art ordinance than on any other item on its agenda.
In the end, the council gave initial approval to an ordinance amendment that would temporarily reduce the required allocation to public art from city capital improvement projects – from 1% to 0.5% for a period of three years. After three years, the percentage would automatically revert to 1%. Of the various amendments to the ordinance, the percentage of the required allocation was the focus of the most controversy during council deliberations. A bid by Jane Lumm (Ward 2) to lower the percentage further to 0.25% gained little support.
Other art ordinance amendments given the council’s initial approval include a requirement that public art money be returned to its fund of origin after three years, if not encumbered by a specific art project. The amendment also included a definitional change that effectively excludes sidewalk repair from the public art ordinance. The amendments also addressed the general fund, making explicit the exclusion of general fund projects from the public art ordinance.
During deliberations, city staff confirmed that at least a portion of the public art allocation required from the new municipal building (aka the police/courts building) could be associated with the general fund – about $50,000 out of the $250,000. [This is for art in the interior of the building, and is separate from the outdoor fountain designed by German artist Herbert Dreiseitl.]
As part of her Ward 2 election campaign, Jane Lumm had argued that general fund dollars were connected to supporting public art at the new municipal building – an idea that had been, until Monday’s meeting, poo-pooed by some councilmembers, including mayor John Hieftje, who had said no general fund money had been used for the public art program.
Lumm was active in her first council meeting since serving in the 1990s. During deliberations on a revision to the ordinance on the city’s greenbelt boundaries, she prompted extended discussion on the part of the revision dealing with the boundary expansion. A less controversial part of the proposed revision involved allowing parcels adjacent to the boundary to be eligible for protection. In the end, the council gave initial approval to both parts of the greenbelt boundary change.
Also related to land use were two site plans on the agenda. The council gave initial approval to altering the University Bank site plan for its property at 2015 Washtenaw Ave., known as the Hoover Mansion. And the council signed off on the site plan, as well as the brownfield plan, for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw.
Because the content of a proposed revision to the city’s littering and handbill law was not available to the public until late in the day Monday, just before the council met, the council postponed its consideration of that item. The ordinance amendment would allow residents to prevent delivery of unwanted newspapers to their homes by posting a notice on their front doors.
In other business, the council expressed its opposition to a bill pending in the Michigan legislature that would nullify an Ann Arbor ordinance on non-discrimination against people based on sexual orientation, gender identity, or student status. At the meeting, the council also authorized acceptance of several grants for the 15th District Court for programs on domestic violence and substance abuse.
In routine business for the first council meeting after newly elected councilmembers take office, the council elected Marcia Higgins (Ward 4) as mayor pro tem. Committee appointments and rule changes were postponed until Dec. 5. [Full Story]
City Council OKs Arbor Hills Crossing Plan
At its Nov. 21, 2011 meeting, the Ann Arbor city council approved the site plan for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw.
The project involves tearing down three vacant commercial structures and putting up four one- and two-story buildings throughout the 7.45-acre site – a total of 90,700-square-feet of space for retail stores and offices. Three of the buildings would face Washtenaw Avenue, across the street from the retail complex where Whole Foods grocery is located. The site would include 310 parking spaces.
The city’s planning commission unanimously recommended approval of the site plan at its Oct. 18, 2011 meeting. Action had been postponed at the commission’s June 7, 2011 meeting so that the developer – Campus Realty – could address some outstanding issues with the plan.
The council also approved the brownfield plan for the project, which includes $6.7 million in tax increment financing to be paid back over a 19-year period. The Washtenaw County board of commissioners will still need to sign off on the brownfield plan. Commissioners scheduled a public hearing on the brownfield plan to be held at their meeting on Jan. 18, 2012.
This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link] [Full Story]
Washtenaw Sets Brownfield Plan Hearings
At its Nov. 16, 2011 meeting, the Washtenaw County board of commissioners set two public hearings regarding brownfield plans for projects in Ann Arbor and Ypsilanti Township. Because Ann Arbor and Ypsilanti Township are members of the Washtenaw County Brownfield Redevelopment Authority, the brownfield plans require approval by the county board.
A public hearing for a brownfield redevelopment at Ford Motor Co’s Rawsonville plant was set for Wednesday, Dec. 7 during the county board meeting, which begins at 6:45 p.m. in the administration building at 220 N. Main St., Ann Arbor. The brownfield plan would allow Ford to apply for $625,000 in Michigan Business Tax credits. According to a staff memo, the plan – with the potential tax credits – would allow the … [Full Story]
Commission OKs Arbor Hills Crossing
Ann Arbor planning commission meeting (Oct. 18, 2011): In its main business of the evening, the planning commission recommended approval of the site plan for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw.
Action had been postponed at the commission’s June 7, 2011 meeting so that the developer – Campus Realty – could address some outstanding issues with the plan.
Commissioners were satisfied with the revisions the developer had undertaken to the plan in response to their comments made at the June 7 meeting. Commissioner Bonnie Bona characterized the site plan as essentially a disguised strip shopping center, but allowed that it was a good strip shopping center.
Arbor Hills Crossing will next go before the city council for its approval.
The commission also granted three separate requests for flexible application of the new landscape ordinance approved by the city council in June 2011. Those requests were from: (1) Gallup One Stop gas station and convenience store; (2) the University of Michigan Credit Union (formerly the Ann Arbor News building); and (3) Glacier Hills.
The commission meeting included its usual range of updates on city council and planning staff activity. [Full Story]
Planning Group OKs Arbor Hills Site Plan
At its Oct. 18, 2011 meeting, the Ann Arbor planning commission recommended approval of the site plan for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw. Action had been postponed at the commission’s June 7, 2011 meeting so that the developer – Campus Realty – could address some outstanding issues with the plan.
The project involves tearing down three vacant commercial structures and putting up four one- and two-story buildings throughout the 7.45-acre site – a total of 90,700-square-feet of space for retail stores and offices. Three of the buildings would face Washtenaw Avenue, across the street from the retail complex where Whole Foods grocery is located. The site would include 310 parking spaces.
According to city planning … [Full Story]
Approval Postponed on Arbor Hills Crossing
Ann Arbor planning commission meeting (June 7, 2011): The main action item on the planning commission’s agenda was a resolution to approve the site plan for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw.
The project involves tearing down several vacant structures and putting up four one- and two-story buildings throughout the 7.45-acre site – a total of 90,700-square-feet of space for retail stores and offices. Three of the buildings would face Washtenaw Avenue, across the street from the retail complex where Whole Foods grocery is located. The site is also directly north of the new location for Summers-Knoll School. Planning commissioners had approved the Summers-Knoll project at their May 17 meeting.
Comments from commissioners about Arbor Hills Crossing ranged from disappointment in the lack of density to concerns about pedestrian safety. Commissioners generally expressed the sense that they were glad to see the site developed.
Citing some outstanding issues, planning staff recommended postponing action on the plan. Several commissioners raised other issues they’d like to see addressed before the site plans come back to the commission for approval. Among those issues: future plans for bike lanes along Washtenaw Avenue, as identified in the city’s non-motorized transportation plan; and possible pedestrian access to a wetland area. The vote to pospone was unanimous.
Later in the meeting, planning manager Wendy Rampson got feedback on a draft memo to Pittsfield Township, providing input from the commission on the township’s draft master plan. In part, the memo states an objection to the township’s description of itself as “providing an Ann Arbor mailing address while placing a much lower tax burden on businesses.” The memo points out that the plan could be improved by emphasizing regional cooperation. [Full Story]