Ann Arbor Area Transportation Authority board meeting (Oct. 17, 2013): The main business of the board’s meeting was the approval of a funding agreement with the city of Ypsilanti – a new member of the AAATA, and the first jurisdiction to join the authority outside of the city of Ann Arbor.
The funding agreement between the AAATA and the city of Ypsilanti formalizes the existing arrangement under which Ypsilanti passes its dedicated transit millage through to the AAATA. The board approved it unanimously. The Ypsilanti city council will consider the agreement on Nov. 5.
In another piece of business that came at the end of the meeting, after a closed session that lasted about an hour and a half, the board voted to establish a subcommittee to meet with whichever developer might make the winning bid on the city-owned property at Fifth and William – known as the old Y lot. That’s an alternative to the AAATA attempting to bid on the property itself, which was listed at $4.2 million. Bids were due by Oct. 18. The city paid $3.5 million for the property 10 years ago and still owes that much on a balloon payment due at the end of this year.
An item that simply authorized the purchase of additional vehicles for the AAATA’s vanpool program had some complex history behind it – involving the federal government shutdown. The shutdown prevented the AAATA from completing its pursuit of a waiver from the Federal Transit Administration for the Buy America requirement. And the Buy America requirements were pointing the AAATA toward purchasing more expensive vehicles (Chevrolet Traverses) that did not fit the needs of passengers as well as the non-qualifying vans (Dodge Caravans). So the board opted to use local millage revenue, and to backfill the operational expenses that the millage money was covering – by using federal preventive maintenance dollars.
In a final routine item, the board authorized the AAATA’s chief executive officer to execute contracts with MDOT that are less than $1 million.
A common thread among public commentary and other board communications was the 5-year service improvement plan the AAATA has developed, and the schedule of public meetings to introduce that plan.
Editor’s note: For the AAATA’s Oct. 17 meeting, The Chronicle hired a CART (Communications Across Real Time) professional to provide a real-time “text” stream of the meeting that was accessible online through The Chronicle. The resulting transcript from that live text stream is available here: [link]. The Chronicle is experimenting with ways to make public meetings more accessible to a broader segment of the community, and to provide archival transcripts of those meetings. [Full Story]
Transit Center Elevator Price: Going Down
New contracts for millwork and an elevator for the new Blake Transit Center – currently under construction on Fifth Avenue in downtown Ann Arbor – have been approved. The Ann Arbor Transportation Authority board voted on the contracts at its Feb. 21, 2013 meeting.
The AATA had originally awarded a $139,451 contract to ThyssenKrupp for the elevator. But when ThyssenKrupp made changes to the scope of the project that had an impact on the price, the AATA decided to rebid the project. The winner of the rebid work was Otis Elevator, which will install an elevator for $108,100.
The board also approved an $80,255 contract with SBD Commercial Interiors for manufacture and installation of custom millwork in the new transit center. The budget had allowed … [Full Story]