Stories indexed with the term ‘Broadway bridges’

Broadway Bridge

New railroad track being laid near the Broadway bridge. This view is looking down to the southeast [photo], next to Gandy Dancer. [photo] A closer view, with the new rail next to the old. [photo]

A2: Broadway Photos

On his blog Michigan Exposures, Mikoyan has uploaded a set of photos taken in the Broadway bridges area of Ann Arbor, including shots of the St. Vincent de Paul building and the Gandy Dancer. [Click on a photo and arrow through the set to view the larger-sized images] [Source]

Planning Group Revisits Huron River Report

Ann Arbor master plan revisions committee meeting (March 8, 2012): At the request of planning commissioner Kirk Westphal, a committee charged with reviewing changes to the city’s master plan is looking at a recommendation related to land near the Huron River.

Ann Arbor master plan revisions committee

Members of the Ann Arbor planning commission, from left: Eleanore Adenekan, Kirk Westphal and Diane Giannola. At the right is Wendy Rampson, head of the city's planning staff. Commissioners were attending the March 8, 2012 meeting of the master plan revisions committee. (Photos by the writer.)

The Huron River and Impoundment Management Plan, known as HRIMP, was completed in 2009. But in large part because of controversy related to Argo Dam – centered on whether or not the dam should be removed – none of the 30 other recommendations were implemented.

Only one of the HRIMP recommendations relates to land use, and is therefore in the purview of the planning commission. That recommendation calls for limited commercial development – such as a restaurant or other publicly-used entity – in the Broadway bridge/Argo area.

Much of the discussion at the March 8 committee meeting centered on the property now owned by MichCon, a subsidiary of DTE Energy, located north of Broadway Street, between the Huron River and the railroad tracks that run past the Amtrak station. A state-supervised cleanup effort is underway at that site, but its future use – including the possibility that it could be acquired by the city and turned into a park – is unclear.

Remediation of the MichCon site was also a topic at the March 12, 2012 Ann Arbor city council work session, where the property’s potential future use was discussed. That presentation also included an update on a whitewater river feature that DTE Energy is paying for. The whitewater section to be built in the Huron River was originally part of the same project as the city’s Argo Dam bypass reconstruction. The bypass, which has been recently named the Argo Cascades, is nearly complete.

This article includes a summary of the council working session related to the MichCon cleanup, as well as a report on the master plan revisions committee meeting. Based on discussions at that committee meeting, it seems likely that a proposal will be forwarded to the full planning commission to add the HRIMP recommendation to the city’s master plan. Any changes to the master plan would also require city council approval. [Full Story]

Ann Arbor Council OKs Re-Funding Bonds

At its Feb. 6, 2012 meeting, the Ann Arbor city council approved the issuance of $2,850,000 of bonds to refinance the outstanding principal amount of Michigan Transportation Fund Bonds for the Broadway Bridges project. After factoring in bond issuance costs, the city expects to save around $185,000 over the next 11 years.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link]