The Ann Arbor Chronicle » capital http://annarborchronicle.com it's like being there Wed, 26 Nov 2014 18:59:03 +0000 en-US hourly 1 http://wordpress.org/?v=3.5.2 AATA Amends Capital Plan http://annarborchronicle.com/2011/08/24/aata-amends-capital-plan/?utm_source=rss&utm_medium=rss&utm_campaign=aata-amends-capital-plan http://annarborchronicle.com/2011/08/24/aata-amends-capital-plan/#comments Wed, 24 Aug 2011 22:30:11 +0000 Chronicle Staff http://annarborchronicle.com/?p=70565 At its Aug. 24, 2011 meeting, the Ann Arbor Transportation Authority board approved a revision to its capital and categorical grant program to accommodate three projects: the Blake Transit Center (BTC) reconstruction in downtown Ann Arbor, the bus storage facility expansion, and the bus maintenance facility upgrade.

The scope of the BTC has expanded, with a total estimated cost of $5.5 million. The estimate is based on a schematic design that is not yet complete. Already secured is $4.195 million in grant funds, which leaves a balance of $1.044 million.

The bus storage expansion was AATA’s final project approved for federal stimulus funds – $1.01 million in stimulus funds were allocated to the project. With a current cost estimate of $2.404 million, there is a balance of $1.394 million.

The bus maintenance facility upgrade includes the addition of a urea filling station. Already approved in grants for that work is $0.598 million. The total cost will be $1.244 million, leaving a balance of $0.647 million.

The board’s action on Aug. 24 revised the AATA’s capital and categorical grant program to provide a total of $2,676,678 for the three projects from the AATA’s federal formula funds.