FEMA Grant to Fund 721 N. Main Demolition

Two buildings on the city-owned 721 N. Main property near downtown Ann Arbor will now be demolished, using $87,704 in funds granted by the Federal Emergency Management Agency (FEMA).

721 N. Main site showing the two buildings to be demolished, which are located in the floodway.

721 N. Main site showing the two buildings to be demolished, which are located in the floodway.

The unanimous vote to accept the funds came at the council’s March 4, 2013 meeting. The 721 N. Main site is a former city maintenance yard, and is part of a … [Full Story]

Ann Arbor Council Adopts Hazard Plan

The city of Ann Arbor’s updated hazard mitigation plan was approved by the city council at its Sept. 17, 2012 meeting.

The plan submitted to the council for approval included some information that had not been updated. For example, the plan describes options for a structure located at 3432 Platt Road: “Sell structure if possible, otherwise demolish and lump with other Springbrook properties Study Swift Run to determine flood levels; if no study, remove structure to be safe, convert to open space use. Remove structures; study Swift Run to assess possibility for unoccupied use on part of parcel.” However, the 3432 Platt Road house was demolished in 2008.

The plan is required by the Federal Emergency Management Agency for grant funding. The city … [Full Story]

Burrowing Under Railroad Berm: Feasible?

On Wednesday, Ann Arbor city staff led a tour of property starting from the city-owned 721 N. Main site, northwards to the entrance ramp of M-14. On the tour were some members of a recently established North Main-Huron River corridor task force.

BirdsEye view of railroad berm

View of Depot Street from the south. The railroad track curves northward as it passes by Argo Dam, visible at the top of this image.

They were briefed on the status of the 721 N. Main property’s status with respect to potential environmental contamination – which is apparently less certain than what’s been portrayed recently by elected officials.

Task force members were also briefed on a related project that’s in its initial stages: a feasibility study for opening up the railroad berm separating the area south of Depot Street (including 721 N. Main) from the Huron River. The railroad tracks run along the top of the berm. The idea is to study the possible impact of replacing the solid berm – which acts as a dam for stormwater flow from the Allen Creek creekshed – with a culvert or a trestled system for suspending the tracks.

The primary impetus behind the berm project is stormwater management and flood mitigation. That’s reflected by the fact that the source of funds for the roughly $50,000 feasibility study would be from the city’s stormwater utility. The feasibility study would move ahead only if it’s approved by the city council, which will likely have the item on its agenda in about two months.

But the railroad berm study also has implications for pedestrian connections and riverside access – which the task force is supposed to study. The task force is asked to create a vision that, among other things, improves pedestrian and bicycle connections to Bandemer Park and increases public access to riverside parks.

So the railroad berm feasibility study has been coordinated with the goal of pedestrian accessibility. The RFP (request for proposals) for the study includes among its tasks a study of the potential for non-motorized access through the railroad berm.

The problematic character of pedestrian movement on the North Main corridor was evident during the July 25 tour. As the tour group made its way northward toward the M-14 entrance ramp, it repeated a pattern of fracturing into smaller clusters and re-grouping. That was partly a function of the size of the group (about 10 people), but also the corridor itself.

The relatively narrow walkable space – between the road to the left, and fences, buildings or vegetation on the right – features sidewalk slabs in need of repair and sections of dirt path that require single-file passage. Noise from rush hour traffic made conversation difficult along the way.

A year from now, on July 31, 2013, the task force is supposed to deliver its report on a vision for the corridor. Earlier than that, by the end of 2012, the task force has been asked to provide a recommendation on the use of 721 N. Main.

For task force members and members of the public, the same tour will be repeated on Aug. 1, starting at 5 p.m. from 721 N. Main. [Full Story]

New Flood Map: Ann Arbor Gives Final OK

At its March 5, 2012 meeting, the Ann Arbor city council gave final approval to an ordinance change that will adopt a new Flood Insurance Rate Map (FIRM) for the city.

By way of background on those maps, the National Flood Insurance Program (NFIP) makes flood insurance available for properties in participating communities – Ann Arbor is a participant. If a building has a federally-backed mortgage and it’s located within the “1% annual change floodplain” (previously called the “100-year floodplain) then flood insurance is required.

Ann Arbor’s most recent FIRM dates from Jan. 2, 1992. In 2004, the Federal Emergency Management Agency (FEMA) began a map revision process for Washtenaw County. Various drains in the city were re-analyzed, using updated data, and … [Full Story]

Ann Arbor Flood Maps Get Initial OK

At its Feb. 21, 2012 meeting, the Ann Arbor city council gave initial approval to an ordinance change that will adopt a new Flood Insurance Rate Map (FIRM).

By way of background on those maps, the National Flood Insurance Program (NFIP) makes flood insurance available for properties in participating communities – Ann Arbor is a participant. If a building has a federally-backed mortgage and it’s located within the “1% annual change floodplain” (previously called the “100-year floodplain) then flood insurance is required.

Ann Arbor’s most recent FIRM dates from Jan. 2, 1992. In 2004, the Federal Emergency Management Agency (FEMA) began a map revision process for Washtenaw County. Various drains in the city were re-analyzed, using updated data, and on July 27, 2007, FEMA issued preliminary maps. After required public review, appeal and revisions, on Oct. 3, 2011, FEMA issued a letter with a final determination, indicating that the new maps would become effective on April 3, 2012. [.pdf of Oct. 3, 2011 letter] [.pdf of Dec. 20, 2011 reminder letter]

Compared to the previous 1992 maps, 321 parcels are no longer analyzed as lying within a floodplain. However 116 parcels that were previously not analyzed as in a floodplain are now in a floodplain, according to the new maps. Building-wise, 452 structures are no longer analyzed as lying within a floodplain, while 88 buildings are now in a floodplain, according to the new maps. [See also Chronicle coverage: "Column: Digital Information Flood."]

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link] [Full Story]