The Ann Arbor Chronicle » stormwater study http://annarborchronicle.com it's like being there Wed, 26 Nov 2014 18:59:03 +0000 en-US hourly 1 http://wordpress.org/?v=3.5.2 Ann Arbor to Complete Stormwater Study http://annarborchronicle.com/2012/06/18/ann-arbor-to-complete-stormwater-study/?utm_source=rss&utm_medium=rss&utm_campaign=ann-arbor-to-complete-stormwater-study http://annarborchronicle.com/2012/06/18/ann-arbor-to-complete-stormwater-study/#comments Tue, 19 Jun 2012 02:18:47 +0000 Chronicle Staff http://annarborchronicle.com/?p=90354 At its June 18, 2012 meeting, the Ann Arbor city council approved a $822,700 contract with CDM Michigan Inc. for a stormwater analysis project. The project has five phases: (1) collect stormwater GIS data; (2) integrate the GIS with the model information and gather general monitoring data; (3) engage the public and perform preliminary model calibration; (4) gather comprehensive monitoring data and finalize model calibration; and (5) analyze modeling results and engage creekshed groups/neighborhoods.

In 2007, CDM was hired to complete the first two phases of the project. The contract approved by the council on June 18 is supposed to allow completion of the project.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link]

]]>
http://annarborchronicle.com/2012/06/18/ann-arbor-to-complete-stormwater-study/feed/ 0