AATA Amends Capital Plan
At its Aug. 24, 2011 meeting, the Ann Arbor Transportation Authority board approved a revision to its capital and categorical grant program to accommodate three projects: the Blake Transit Center (BTC) reconstruction in downtown Ann Arbor, the bus storage facility expansion, and the bus maintenance facility upgrade.
The scope of the BTC has expanded, with a total estimated cost of $5.5 million. The estimate is based on a schematic design that is not yet complete. Already secured is $4.195 million in grant funds, which leaves a balance of $1.044 million.
The bus storage expansion was AATA’s final project approved for federal stimulus funds – $1.01 million in stimulus funds were allocated to the project. With a current cost estimate of $2.404 million, there is a balance of $1.394 million.
The bus maintenance facility upgrade includes the addition of a urea filling station. Already approved in grants for that work is $0.598 million. The total cost will be $1.244 million, leaving a balance of $0.647 million.
The board’s action on Aug. 24 revised the AATA’s capital and categorical grant program to provide a total of $2,676,678 for the three projects from the AATA’s federal formula funds.
This brief was filed from the downtown location of the Ann Arbor District Library, where the AATA board holds its meetings. A more detailed report will follow: [link]