At its Sept. 6, 2011 meeting, the Ann Arbor city council approved a $550,040 increase to the contract with Barrett Paving Materials Inc. – the contractor that handles street repair work for the city. The money will be spent on additional work that can now be done because, according to the city, the 2011 street repair work is ahead of schedule.
The proposed additional work will be done on: the outbound lane of Miller Avenue between Seventh Street and Chapin; on North Division Street between Ann and Detroit streets; and on Oxford Street between Hill Street and South University Avenue.
The work on Oxford Street could start either during the 2011 construction season or in 2012, depending on how talks go with the University of Michigan about the university’s contribution to the project.
Part of the approval authorized by the city council included $80,000 worth of crack-sealing work to be done yet this year on several different streets.
The city’s original contract with Barrett Paving Materials Inc. was for $3,710,953.