Ann Arbor OKs $10M for Wastewater Project
At its Jan. 23, 2012 meeting, the Ann Arbor city council authorized a $10,802,423 contract with Malcolm Pirnie Inc. for engineering services related to the facilities renovation project (FRP) at the city’s wastewater treatment plant.
The city’s wastewater treatment facility includes an East Plant and West Plant. The West Plant has been taken offline due to its dilapidated condition and is planned to be demolished and replaced. The project also includes a number of improvements throughout the facility, including a new electrical distribution system, new emergency power generators, utilities relocation, and replacement of stormwater collection system equipment.
The total project cost is well over $100 million and is expected to be financed in part with low-interest loans through Michigan’s state revolving fund program, which is administered by the Michigan Dept. of Environmental Quality. [For additional background on the project, see The Ann Arbor Observer's "The Flow Never Stops" from April 2009.]
This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link]