Sugar Creek Drain Bonds Get Final OK
At its May 16, 2012 meeting, the Washtenaw County board of commissioners gave final approval to pledge the county’s full faith and credit for up to $270,000 in bonds to fund an extension of the Sugar Creek drainage district. The financing request came from water resources commissioner Janis Bobrin, whose office is managing the project. It had been given initial approval at the board’s May 2 meeting.
The project – which in total is budgeted at $349,899 – is being done at the behest of the Washtenaw County road commission. It entails relocating a portion of the county drain, including a section of 1,850 feet adjacent to Platt Road between Judd and Stoney Creek roads in York Township. A second phase includes removing sediment and vegetation, as well as making wingwall repairs, at the drain crossings of US-23, McCrone Road, and Gooding Road.
The Sugar Creek drainage district covers parts of York Township, Augusta Township and the city of Milan. The bonds will be repaid in part by assessing property owners in the district – 70% of the cost of the bonds will be paid in this way. [.pdf map of drainage district] The remainder of the funds will come from York and Augusta townships, the city of Milan, Washtenaw County, the Michigan Dept. of Transportation, and two railroads – Ann Arbor Railroad and Norfolk Southern Railroad. The county’s share of the cost is $24,203 – half of that will be paid by the county road commission.
A contract for the work has been awarded to Mead Brothers Excavating of Springport, Mich., the lowest responsible bidder.
This brief was filed from the boardroom of the county administration building, 220 N. Main in Ann Arbor. A more detailed report will follow: [link]