Speedway Rezoning Gets Initial Okay
The rezoning for a Speedway gas station at the northeast corner of North Maple and Miller got initial approval from Ann Arbor city council at its Sept. 4, 2012 meeting. The site plan and the rezoning for the gas station had been recommended for approval by the Ann Arbor planning commission at its July 17, 2012 meeting.
The council gave its approval to the site plan on Sept. 4, but the rezoning issue will need to come back for a second and final approval, as all rezoning requests must. Rezoning of land is a change to the city’s ordinances, and because of that an initial vote of the council is required, followed by a public hearing and a second vote at a subsequent meeting.
The project is located at 1300 N. Maple on a 1.39-acre site. The rezoning request would change the zoning from PL (public land) to C3 (fringe commercial).
The plan calls for demolishing an existing 1,500-square-foot vacant service station building, which was built in the 1950s, and constructing a new 3,968-square-foot, single-story gas station and convenience store with five pumps. The gasoline pumps will be covered by a 28-foot by 121-foot canopy. Fourteen parking spaces will be provided next to the convenience store, and six bicycle hoops will be located on the south side of the building, adjacent to a sidewalk leading to Miller.
According to a staff report, underground storage tanks have been removed and an environmental analysis of the site is underway. If any environmental contamination is found, the owner will be required to remediate the site to meet requirements of the Michigan Dept. of Environmental Quality.
The staff report states that the city’s traffic engineer has reviewed a revised landscaping plan and confirmed that traffic issues have been addressed and the site plan meets the requirements of Chapter 47 (Streets) of the city code.
The plan will preserve all existing trees within the 25 feet at the back of the property, an area that includes an existing 5-foot-wide pedestrian path. In addition, seven oak trees will be planted along the sides of the proposed building, and required landscaping within the site will be provided.
This brief was filed from the city council’s chambers on the second floor of city hall at 301 E. Huron. A more detailed report will follow: [link]