Park Commission Reviews Pool Contract
Ann Arbor park advisory commissioners have recommended awarding a contract with Renosys Corp. to install PVC pool liners at Buhr and Fuller pools. The action took place during PAC’s May 20, 2014 meeting.
The value of the contract is $205,055 plus a 10% construction contingency of $20,506. That brings the project’s total budget to $225,561. Renosys was the lowest of two bidders. Natare Corp. submitted a bid of $211,965.
The work will be done in the fall, so the summer swimming season won’t be disrupted. Funding is available from the approved FY2014 park maintenance and capital improvement millage revenues. [.pdf of staff memo]
This brief was filed from the second-floor council chambers at city hall, 301 E. Huron. A more detailed report will follow.