State Street Village Gets Initial Zoning OK
Initial approval of the rezoning of the land for the State Street Village project has been given approval by the Ann Arbor city council. The 4.5-acre parcel is proposed to be rezoned from M1 (limited industrial district) to O (office district).
Action on the initial approval came at the city council’s July 21, 2014 meeting. A vote on the final enactment of the rezoning and on the site plan for the project will come at a future council meeting.
A recommendation for the rezoning was given at the June 17, 2014 meeting of the Ann Arbor planning commission.
At that meeting, commissioners recommended approval of a site plan, development agreement and rezoning for the project. It’s a $10 million project put forward by Ann Arbor-based McKinley Inc. at 2221-2223 S. State St. The plan calls for constructing two 4-story apartment buildings at the rear of the site, totaling 112,262 square feet, with 38 units each. Another 2,027 square foot building – for a leasing office with two apartments above it – would be built on the front of the parcel, on South State.
The front part of the site is currently a surface parking lot, and is zoned O (office). The rear parcel – 4.5 acres – is vacant, and zoned M1 (limited industrial). Residential developments are permitted in office-zoned areas. [.pdf of staff report]
The development will include 114 parking spaces in the rear of the site and 13 spaces for the front. Another 22 spaces in the surface parking lot will be shared by the existing office building just south of the site.
In addition, 44 covered bicycle spaces and 8 enclosed bicycle spaces will be provided near the entrances of the apartment buildings and 2 hoops will be placed near the entrance of the rental office building.
Instead of making a $48,360 requested donation to the city for parks, McKinley has proposed two 8×10-foot grilling patios with picnic tables and grills.
According to the staff memo, the footing drains of 18 homes, or flow equivalent to 71.91 gallons per minute, will need to be disconnected from the city’s sanitary sewer system to mitigate flow from this proposed development.
Only the initial consideration of the rezoning issue was before the council on July 21. The site plan approval will be considered at a future meeting, likely at the same meeting when the council gives final consideration to the rezoning.
This brief was filed from the city council’s chambers on the second floor of city hall located at 301 E. Huron.