The Ann Arbor Chronicle » North Main task force http://annarborchronicle.com it's like being there Wed, 26 Nov 2014 18:59:03 +0000 en-US hourly 1 http://wordpress.org/?v=3.5.2 Council Commits Up to $750,000 for 721 N. Main http://annarborchronicle.com/2013/06/18/council-commits-up-to-750000-for-721-n-main/?utm_source=rss&utm_medium=rss&utm_campaign=council-commits-up-to-750000-for-721-n-main http://annarborchronicle.com/2013/06/18/council-commits-up-to-750000-for-721-n-main/#comments Tue, 18 Jun 2013 05:16:21 +0000 Chronicle Staff http://annarborchronicle.com/?p=114832 A commitment of up to $750,000 from the city’s general fund – to undertake planned improvements to the city-owned property at 721 N. Main – has been made by the Ann Arbor city council in action taken at its June 17, 2013 meeting. The commitment is a requirement for a grant application that the city is making to the Michigan Natural Resources Trust Fund for $300,000.

If the city’s plan unfolds as it expects, then none of the $750,000 in general fund money would be needed.

The improvements to 721 N. Main have resulted from work done by a North Main corridor improvement task force that has been working at the direction of the city council since the summer of 2012 to make recommendations for the corridor.

Of the $1.2 million estimated cost for the planned trail and stormwater improvements to the site, the city plans to use $150,000 from the city’s stormwater fund. To cover part of the remaining $1.05 million, the city hopes to use $600,000 from a grant it it’s applied for from the Michigan Dept. of Transportation (MDOT) and the Southeast Michigan Council of Governments (SEMCOG) – through SEMCOG’s transportation alternatives program (TAP).

The council approved the application for the SEMCOG grant at its April 15, 2013 meeting. To cover the remaining $450,000, the city hopes to use $150,000 from a Washtenaw County Parks & Recreation Connecting Communities grant and $300,000 from the Michigan Natural Resources Trust Fund (MNRTF) grant. The council approved the application for those last two grants at its Dec. 17, 2012 meeting.

The council’s resolution passed on June 17 comes in response to an MNRTF grant requirement that the council commit the city to funding the other grants itself – from general fund money – if the grants fail to materialize. The $750,000 figure comes from adding the $600,000 SEMCOG grant to the $150,000 Washtenaw County Parks & Recreation grant.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link]

]]>
http://annarborchronicle.com/2013/06/18/council-commits-up-to-750000-for-721-n-main/feed/ 0
Grant Applications Recommended for 721 N. Main http://annarborchronicle.com/2012/12/04/grant-applications-recommended-for-721-n-main/?utm_source=rss&utm_medium=rss&utm_campaign=grant-applications-recommended-for-721-n-main http://annarborchronicle.com/2012/12/04/grant-applications-recommended-for-721-n-main/#comments Tue, 04 Dec 2012 22:47:07 +0000 Chronicle Staff http://annarborchronicle.com/?p=101862 The Ann Arbor park advisory commission has voted to recommend applying for two grants related to the city-owned 721 N. Main property. PAC took the action on Dec. 4, 2012, before its land acquisition committee meeting.

The grants would come from the Washtenaw County Parks and Recreation Commission’s Connecting Communities program, and the Michigan Department of Natural Resources trust fund. No amounts were indicated in the resolutions that were approved by PAC, but up to $300,000 could be requested from the state, and at least that much could be requested from the county. The amounts in the applications will be determined after a phase 2 environmental assessment is completed later this year. That environmental study will give the city a clearer indication of how much it will cost to remediate the site.

Both grants would focus on the roughly 2.5 acres of the 5-acre site that are in the floodway. The grant from the county would be used for constructing non-motorized trails, while the state grant would be used for general park improvements. If the county funds are received, they might count as matching funds for the state grant. Several city staff members – including community services area administrator Sumedh Bahl and Connie Pulcipher of the city’s systems planning unit – were on hand at the Dec. 4 PAC meeting to give an overview of the project and answer questions.

Deadlines to apply for the grants are driving the timing of this process. Applications for Connecting Communities must be received by year’s end, and the city council – which has only one more meeting this year, on Dec. 17 – must authorize any application. The MDNR trust fund grant application is due at the end of March 2013.

More generally, the city’s North Main/Huron River corridor task force is developing a recommendation to bring to the city council on Dec. 17. According to a memo from Colin Smith, the city’s parks and recreation manager, the task force recommendation is expected to focus on converting the floodway portion of that site to a park use. Trails would give access to the site from Felch, Summit, and Main streets, and “would also create a first step in a greenway with a vision toward connecting to the Huron River and the Border-to-Border trail network.”

The land around the trails would be wet meadow, prairie grass, and other storm water management features. Other possible uses for the non-floodway portion of the site might include a dog park or community gardens. The possibility of using a portion of the 721 N. Main site as a dog park was most recently discussed at PAC’s Oct. 16, 2012 meeting.

The North Main/Huron River task force is expected to vote on its overall recommendation for the 721 N. Main site at a task force meeting on Dec. 5, 2012. That task force has a broader mandate than just the 721 N. Main site, and is charged with bringing a recommendation on the corridor itself – including future uses of the MichCon property between the Huron River and the railroad tracks – by summer 2013.

This brief was filed from the second-floor city council workroom at city hall, where the park advisory commission meeting was held.

]]>
http://annarborchronicle.com/2012/12/04/grant-applications-recommended-for-721-n-main/feed/ 0
North Main Task Force Gets New Member http://annarborchronicle.com/2012/11/08/north-main-task-force-gets-new-member/?utm_source=rss&utm_medium=rss&utm_campaign=north-main-task-force-gets-new-member http://annarborchronicle.com/2012/11/08/north-main-task-force-gets-new-member/#comments Fri, 09 Nov 2012 04:32:00 +0000 Chronicle Staff http://annarborchronicle.com/?p=100363 A task force that’s looking at future planning for the North Main Street and Huron River corridor has been expanded so that it eventually can include outgoing councilmember Sandi Smith (Ward 1). She was appointed to represent the council on the group, but did not seek re-election to her council seat. The vote to expand the task force came at the council’s Nov. 8, 2012 meeting. Smith was also nominated and confirmed in a one-step process serve as an additional citizen member.

Mayor John Hieftje had indicated at the council’s Oct. 15, 2012 meeting that he would be moving to expand the task force in this way. The resolution was sponsored by Smith’s Ward 1 cohort, Sabra Briere. At the meeting, Briere was also appointed to replace Smith as the council representative to the task force.

Smith’s last meeting was Oct. 15, because she was unable to attend the final meeting of her term, which was Nov. 8. New councilmembers – including Sumi Kailasapathy, who’ll take the seat held by Smith – will be ceremonially sworn in at the council’s Nov. 19 meeting.

The task force is due to make a recommendation on a use for the city-owned 721 N. Main Street parcel by the end of the year. That comes in the context of a planned application by the city to the Michigan Dept. of Natural Resources Trust Fund next year for a grant in connection with 721 N. Main. The group’s broader recommendation for the entire corridor is not due until mid-year 2013.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link]

]]>
http://annarborchronicle.com/2012/11/08/north-main-task-force-gets-new-member/feed/ 0
Burrowing Under Railroad Berm: Feasible? http://annarborchronicle.com/2012/07/26/burrowing-under-railroad-berm-feasible/?utm_source=rss&utm_medium=rss&utm_campaign=burrowing-under-railroad-berm-feasible http://annarborchronicle.com/2012/07/26/burrowing-under-railroad-berm-feasible/#comments Thu, 26 Jul 2012 18:36:25 +0000 Dave Askins http://annarborchronicle.com/?p=93408 On Wednesday, Ann Arbor city staff led a tour of property starting from the city-owned 721 N. Main site, northwards to the entrance ramp of M-14. On the tour were some members of a recently established North Main-Huron River corridor task force.

BirdsEye view of railroad berm

View of Depot Street from the south. The railroad track curves northward as it passes by Argo Dam, visible at the top of this image.

They were briefed on the status of the 721 N. Main property’s status with respect to potential environmental contamination – which is apparently less certain than what’s been portrayed recently by elected officials.

Task force members were also briefed on a related project that’s in its initial stages: a feasibility study for opening up the railroad berm separating the area south of Depot Street (including 721 N. Main) from the Huron River. The railroad tracks run along the top of the berm. The idea is to study the possible impact of replacing the solid berm – which acts as a dam for stormwater flow from the Allen Creek creekshed – with a culvert or a trestled system for suspending the tracks.

The primary impetus behind the berm project is stormwater management and flood mitigation. That’s reflected by the fact that the source of funds for the roughly $50,000 feasibility study would be from the city’s stormwater utility. The feasibility study would move ahead only if it’s approved by the city council, which will likely have the item on its agenda in about two months.

But the railroad berm study also has implications for pedestrian connections and riverside access – which the task force is supposed to study. The task force is asked to create a vision that, among other things, improves pedestrian and bicycle connections to Bandemer Park and increases public access to riverside parks.

So the railroad berm feasibility study has been coordinated with the goal of pedestrian accessibility. The RFP (request for proposals) for the study includes among its tasks a study of the potential for non-motorized access through the railroad berm.

The problematic character of pedestrian movement on the North Main corridor was evident during the July 25 tour. As the tour group made its way northward toward the M-14 entrance ramp, it repeated a pattern of fracturing into smaller clusters and re-grouping. That was partly a function of the size of the group (about 10 people), but also the corridor itself.

The relatively narrow walkable space – between the road to the left, and fences, buildings or vegetation on the right – features sidewalk slabs in need of repair and sections of dirt path that require single-file passage. Noise from rush hour traffic made conversation difficult along the way.

A year from now, on July 31, 2013, the task force is supposed to deliver its report on a vision for the corridor. Earlier than that, by the end of 2012, the task force has been asked to provide a recommendation on the use of 721 N. Main.

For task force members and members of the public, the same tour will be repeated on Aug. 1, starting at 5 p.m. from 721 N. Main.

721 N. Main

The July 25 tour began at the city-owned 721 N. Main site. City staff discussed two issues with task force members: where the floodway and floodplain lines are for the property; and the status of the site’s environmental clearance.

721 N. Main: Environmental

Compared to 415 W. Washington – another city-owned property that’s the focus of attention regarding its future disposition – 721 N. Main has been portrayed by mayor John Hieftje at recent meetings of the city council as not suffering from environmental contamination. And that’s the basis of a decision to try to make 721 N. Main the city’s first greenway park – an effort that would be supported through an eventual grant application by the city to Michigan’s Department of Natural Resources Trust Fund.

It’s the annual spring application deadline for the DNR trust fund grant that is driving the earlier timeline for the task force recommendation on 721 N. Main – Dec. 31, 2012, instead of six months later for a recommendation on the whole North Main-Huron River corridor.

Fluid lines for vehicle repair facility in 721 N. Main building.

Fluid lines formerly used for vehicle repair in 721 N. Main building, which previously served as the city's vehicle maintenance and repair facility.

But during the tour, city environmental coordinator Matt Naud addressed the possible perception that the 721 N. Main site has an environmental clearance and the idea that it has been certified as not contaminated. He traced that perception to the fact that the city had removed some underground gas storage tanks from the site – and for the confined area of those tanks, the soil had been remediated to the highest standard. So for the contamination that was known for a fact at 721 N. Main, Naud said, it had been cleaned up. But there was potentially contamination that was unknown in the rest of the site.

For the site as a whole, Naud told the group, 721 N. Main has not had a phase 1 environmental survey done – to study the history of past uses. Phase 2/3 environmental surveys would establish what contaminants are present, if any, and at what levels and locations.

From the quick peek the tour group was given inside the main building at 721 N. Main, the past use of that building as a vehicle maintenance and repair facility indicates the potential for lingering contamination at the site. Aside from possible actual environmental contamination, the building is filled with clutter, including the city councilmembers’ old chairs that were retired from service in May 2011.

Naud also indicated that the Allen Creek creekshed, as the creekshed with the most impervious surface in Ann Arbor, is also likely the “dirtiest.” And any environmental contamination from other sites in the creekshed would naturally migrate to the Allen Creek area – on which the 721 N. Main parcel sits. [The Allen Creek is conveyed underground through a pipe that exits into the Huron River just below the Argo Dam.]

721 N. Main: Floodplain and Floodway

Jerry Hancock, the city’s stormwater and floodplain programs coordinator, also accompanied the tour group. He reviewed the status of a grant from the Federal Emergency Management Agency (FEMA) to demolish two of the buildings at the 721 N. Main site – those that are located in the floodway. The main building is in the floodplain, not the floodway, and is not included in the FEMA grant, which has been awarded and is worth around $100,000. The main building wasn’t included, he said, due in part to the fact that there’s been no public process around what the future of the building should be.

721 N. Main Parcel. Blue area is FEMA floodway. Green area is FEMA floodplain. The FEMA grant for demolition of buildings does not include the main building, which is in the floodplain (green area).

The 721 N. Main parcel is west of Main Street. The main building on the site is oriented north-south, visible just north of the blue-shaded area (the FEMA floodway) and inside the green area (the FEMA floodplain). The FEMA grant for demolishing buildings at 721 N. Main does not include the main building. (Links to higher resolution image.)

Although the grant for demolishing buildings at 721 N. Main had already been awarded by FEMA, Hancock indicated that a delay by the Michigan Dept. of Transportation was long enough that the city’s All-Hazard Plan (for flood mitigation) had expired in the interim. The city is in the process of getting that plan renewed. The receipt of the FEMA funds is contingent on having an up-to-date All-Hazard Plan.

Removal of structures in the floodway – like the two buildings on the 721 N. Main site – is part of the city’s general strategy to reduce flood risk throughout Ann Arbor. Responding to questions from the tour group, Hancock explained that the FEMA flood maps aren’t merely an indicator of low areas – that is, the maps do not simply provide a topographical survey. Although the topography is a significant component of the data that factors into drawing flood maps, he said, the impact of built structures can be to push water into higher elevations.

Railroad Berm Feasibility Study

Hancock also briefed the tour group on a feasibility study for a project near Depot Street, that – if eventually constructed – could have an impact on the floodway maps for the area as far away as 721 N. Main. The project is also potentially connected to improvements in non-motorized transportation.

The idea is to open up some portion of the berm that the railroad track sits on – between Depot Street and the Huron River – to allow a less impeded flow of stormwater into the Huron River. It’s one of 56 different specific projects listed out in the city’s flood mitigation plan:

Project 51: Railroad Berm Fill Removal. Examine ways to remove the berm located between Depot St. and the Huron River, as well as other portions of the railroad berm in the Allen Creek corridor, to allow floodwater to travel to the river without a major barrier impeding the flow, acting like a dam. Examine the costs of creating a terraced rail system. Compare costs estimates to complete project with the estimated costs of removal/relocating

The city issued an RFP (request for proposals) with a deadline for response of June 25, 2012: “Allen Creek Railroad Berm Opening Feasibility Study” Representatives from 10 different firms attended a pre-bid meeting on June 12, 2012. The city received proposals from six of them.

Railroad track berm

The railroad track berm from the Depot Street side of the track, looking southeastward. The Broadway bridges are visible in the distance.

The top two firms in the scoring system were OHM and Spicer Group. The five tasks identified in the RFP are: (1) information gathering; (2) option development; (3) option analysis and stakeholder engagement; (4) conceptual design development; and (5) benefit-cost analysis.

At the city council’s March 19, 2012 meeting, public services area administrator Craig Hupy had responded to questions about flooding along Depot Street during a recent rainstorm. On that occasion, Hupy mentioned the physical, dam-like barrier presented by the railroad berm as a challenge in any improvements to the city’s ability to improve stormwater flow.

Hupy is serving as head of public services on an interim basis, after Sue McCormick’s departure. His permanent position is head of the “systems planning” unit for the city. Systems planning includes not just stormwater manager Jerry Hancock, but also the city’s transportation program manager, Eli Cooper. So according to Hancock, staff were easily able to see a potential connection between the flood mitigation function of a railroad berm project and the potential for non-motorized transportation access to the river, for pedestrians and bicyclists.

Underpass-No-Mo-Plann

The desire for pedestrian and bicycle access across the railroad track was identified separately from the impact that opening the berm could have on flood mitigation. Excerpt from the city's 2007 Non-Motorized Transportation Plan. (Image links to higher resolution file.)

One of the criteria to be applied in task #3 of the RFP, the option analysis, is this: “Possibilities for a shared-use non-motorized path through berm.” And as a part of task #4, the consultant is supposed to: “Develop a design concept for a shared-use non-motorized path through the berm and determine the safety issues due to the floodplain function.”

Hancock described to the tour group how he would be meeting the following morning with one of the respondents to the RFP. That meeting was with OHM, the city’s preferred firm as a result of the RFP review process, and was meant to finalize the details of the scope of work. If OHM and the city can settle on those details, OHM would be hired only after a contract is approved by the city council. It’s expected that the feasibility study would be on the city council’s agenda in about two months. Hancock told The Chronicle that the $50,000 project budget for the study would be drawn from the city’s stormwater utility fund.

On approval by the city council, the project would be completed in a timeframe that Hancock estimated at around 4-6 months.

Floodmap FEMA Depot Street

FEMA flood map that includes the area of study for the railroad berm feasibility study.

Depending on the result of the feasibility study and the resulting concept that the consultant produces, it could become a project that is added to the city’s formal capital improvements plan (CIP). The CIP includes projects the city has identified as useful, even if a funding mechanism for the actual capital project has not been identified.

Hancock told The Chronicle that the capital project itself would be very expensive – with costs driven in part by the fact that it involves a working railroad. Although there’s a pending transaction to transfer ownership from Norfolk Southern to the Michigan Dept. of Transportation, he said, the rail company will continue to have access rights to run its trains under whatever agreement is struck with MDOT.

The Chronicle could not survive without regular voluntary subscriptions to support our coverage of local government issues. Click this link for details: Subscribe to The Chronicle. And if you’re already supporting us, please encourage your friends, neighbors and colleagues to help support The Chronicle, too!

]]>
http://annarborchronicle.com/2012/07/26/burrowing-under-railroad-berm-feasible/feed/ 17