Miller Avenue to Be Resurfaced and More
There was grumbling among some residents before the meeting even started: “They’re going to do what they’re going to do, it’s already a done deal.”
But the half-dozen city staffers who met with neighbors at Forsythe Middle School last Wednesday presented a variety of different options for how the resurfacing of Miller Avenue between Maple and Newport roads could be undertaken. Construction on the project could begin as soon as 2010, but far more likely is a 2011 start, according to project manager Nick Hutchinson, who’s a civil engineer with the city.