Process Starts: Dexter Avenue Assessment
At its Sept. 19, 2011 meeting, the Ann Arbor city council voted to start the process for a special assessment on property owners along a stretch of Dexter Avenue, in order provide the required 20% local funding component for sidewalk, curb and gutter improvements. The other 80% of the project would be paid with federal funds.
There are several gaps in the sidewalks along the stretch. [photo] An administrative hearing for residents is planned for Oct. 3.
This first step by the council essentially directs the city administrator to prepare plans and provide an estimate of the cost. The project is part of the city’s capital improvement plan (CIP). A neighborhood meeting was held on the topic in June 2011.
Next steps, with their expected timing, include: Sept. 20 – mail administrative hearing invitation to residents; Oct. 3 – administrative hearing with residents; Nov. 10 – council approval of resolutions specifying costs to property owners, and a public hearing date; Dec. 5 – public hearing and a council vote on the special assessment.
This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link]