Stories indexed with the term ‘Ann Arbor planning commission’

Sustainability Goals Shape Corridor Study

Ann Arbor planning commission meeting (Sept. 18, 2012): Two projects converged at the most recent planning commission meeting: A draft report of a South State Street corridor study, and next steps toward incorporating the city’s new sustainability goals into its master plan.

Ann Arbor planning commission work session

The Sept. 18, 2012  Ann Arbor planning commission work session focused on South State Street – an aerial map of the corridor is spread out on the table. To the right is Kristin Baja, who provided staff support for the project. She’ll be leaving the city to take a job in Baltimore, and was praised by commissioners for her work. (Photos by the writer.)

Eric Mahler recalled that both projects had been highlighted at a planning commission retreat two years ago, and that in some ways their completion marked a new era in city planning. The corridor study is the first project that incorporates the sustainability goals. The study’s recommendations are organized into the four main sustainability categories: resource management; land use and access; climate and energy; and community.

The recommendations themselves cover a wide spectrum of issues, from traffic and walkability to public art and zoning. [.pdf of draft report] Planning commissioners spent nearly two hours reviewing the recommendations in a working session immediately following their regular Sept. 18 meeting. They’ll likely address the project again before it’s forwarded to city council.

Also during the Sept. 18 meeting, planning manager Wendy Rampson reviewed highlights from an annual report of planning activities for the fiscal year 2012, which ended June 30, 2012. The report reflected an increase in development activity within the city. As one example, there were 28 site plans submitted during the year, up from 13 in FY 2011.

Several University of Michigan students attended the commission’s regular meeting on Sept. 18. Responding to a query from Tony Derezinski, they reported that they are graduate students in urban planning, taking a class from professor Dick Norton. Coming to this meeting had been part of a class requirement. [Norton had also been a speaker on some of the panel discussions related to the city's sustainability efforts.] [Full Story]

City’s Sustainability Framework Disseminated

Ann Arbor’s sustainability framework – an ambitious project that began in early 2011 – will be distributed to neighboring jurisdictions as the next step toward incorporating these goals into the city’s master plan. At its Sept. 18, 2012 meeting, the Ann Arbor planning commission recommended that the city council take this action. The commission had previously recommended approval of the 16 overarching sustainability goals, which are organized into four categories: resource management; land use and access; climate and energy; and community. [.pdf of sustainability document]

State law requires that changes to a community’s master plan must be communicated to adjacent jurisdications and other stakeholders to allow the opportunity for feedback. The sustainability framework will be distributed to these entities: the … [Full Story]

South State St. Corridor Report Drafted

A draft report of the South State Street corridor plan will be considered at the Sept. 18, 2012 meeting of the Ann Arbor planning commission. [.pdf of draft report] The plan includes more than 40 overall recommendations for improving the corridor, which stretches about 2 miles between Stimson Street at the north end down to Ellsworth in the south.

Recommendations are organized into categories of the city’s recently adopted sustainability framework: Land use and access, community, climate and energy, and resource management. Among the recommendations are: (1) Evaluate use of vacant parcels for alternative energy generation; (2) Evaluate integrating public art along the corridor; (3) Evaluate use of open land for community gardens; (4) Assess and improve high crash areas along the corridor; … [Full Story]

Food Gatherers, Fiat Projects Move Forward

Ann Arbor planning commission meeting (Aug. 21, 2012): Projects related to food, Fiats and housing all won recommendations for approval at the most recent planning commission meeting.

Wendy Rampson, Wendy Woods

Ann Arbor’s planning manager, Wendy Rampson stands next to planning commissioner Wendy Woods before the start of the commission’s Aug. 21, 2012 meeting. (Photos by the writer.)

Food Gatherers hopes to expand its large warehouse, adding cooler and freezer space to accommodate its focus on fruits, vegetables and other fresh food. The Carrot Way site, on Ann Arbor’s far north side, is a hub for the nonprofit’s food distribution – staff and volunteers distributed about 5.75 million pounds tons of food in the last fiscal year to those in need. Several commissioners praised the work. They had only a few questions or comments about the project, including a suggestion to use graywater for irrigating gardens on the site.

Also winning approval was a plan to build a new Fiat showroom next to the post office on West Stadium Boulevard, now owned by the Suburban Collection of Troy. The color scheme for Fiat is scarlet and gray, which elicited some ribbing from commissioners that the building’s designer had heard before. And no, he said, there’s no maize-and-blue dealership being planned for Columbus, Ohio.

The third project on the commission’s Aug. 21 agenda was also competitively colored: Changes in the site plan for Plymouth Green Crossings. The owner is asking for several alterations to a 2006 plan – adding parking spaces, eliminating a proposed freestanding restaurant, and more than doubling the permitted amount of space that can be used for restaurants on the site. Currently, the complex includes a bank and two mixed-use buildings with housing and retail/commercial businesses.

All three projects will move on to the Ann Arbor city council for consideration. [Full Story]

Food Gatherers’ Expansion Approved

An expansion of the Food Gatherers’ facility in Ann Arbor moved ahead following action at the Ann Arbor planning commission’s Aug. 21, 2012 meeting. Commissioners unanimously recommended approval of changes to the nonprofit’s planned unit development (PUD), which will allow for a 12,646-square-foot addition to the back of the existing 16,977-square-foot building.

That building houses the nonprofit’s administrative offices, storage warehouse, and training space. The plan also will add 22 parking spaces to the site, and includes an expansion of produce-washing stations, used to clean vegetables grown at gardens on the site. The Carrot Way site is located on the north side of Ann Arbor off of Dhu Varren Road, east of Pontiac Trail.

According to a staff memo, the changes include a … [Full Story]

Planning Commission OKs Fiat Site Plan

The site plan for a new Fiat showroom at 2095 W. Stadium Boulevard was recommended for approval by the Ann Arbor planning commission at its Aug. 21, 2012 meeting.

The plan calls for demolishing a 2,505-square-foot automotive service building and constructing a 3,408-square-foot showroom. The 30,010-square-foot site is zoned C3 (fringe commercial) and is located next to the post office on the west side of Stadium between Federal Drive and East Liberty. It was recently acquired by the Suburban Collection of Troy, which operates a Chrysler Jeep dealership across the street at 2060 W. Stadium. Suburban also owns Cadillac and Chevrolet dealerships located on Jackson Avenue.

The planning staff had recommended this project for approval. It will now be forwarded to the city council for … [Full Story]

Plymouth Green Site Changes Approved

A request to change the site plan for Plymouth Green Crossings – a mixed-use complex off of Plymouth Road, west of Green Road – was unanimously recommended for approval by the Ann Arbor planning commissioners at their Aug. 21, 2012 meeting.

The original planned unit development (PUD) agreement was approved in early 2006. The site includes a bank, two mixed-use buildings (housing and retail/commercial) and attached garages.

The current request proposes six major changes: (1) allowing the ground floor of a proposed three-story mixed-use building – on the site’s northeast corner – to be used for parking or flexible space for special events; (2) increasing the use of potential restaurant space within the site from 7,000 square feet to 14,224 square feet; (3) eliminating … [Full Story]

Planning Group Briefed on William St. Project

At their recent working session, Ann Arbor planning commissioners got their first detailed look at the Connecting William Street project – an effort to coordinate planning for five city-owned sites in downtown Ann Arbor.

Cheryl Zuellig shows a slide of possible development on the Library Lane lot

Cheryl Zuellig of SmithGroupJJR shows a slide of a possible type of development on the Library Lane lot. It’s one of many scenarios that are being discussed as part of the Connecting William Street project, which aims to form a framework to guide future development of city-owned parcels along William Street between Ashley and Fifth. Zuellig is facilitating the project for the Ann Arbor Downtown Development Authority. (Photos by the writer.)

Led by the Ann Arbor Downtown Development Authority at the behest of city council, the project’s goal is to build a framework to guide possible development of those sites, which are primarily surface parking lots: (1) the Kline’s lot (on the east side of Ashley, north of William), (2) the lot next to Palio restaurant (northeast corner of Main & William), (3) the ground floor of the Fourth & William parking structure, (4) the old YMCA lot (on William between Fourth and Fifth), and (5) the top of the Library Lane underground parking garage on South Fifth, which recently opened north of the downtown library.

Amber Miller of the DDA and Cheryl Zuellig of SmithGroupJJR led the Aug. 14 discussion and solicited feedback on three development scenarios. Broadly speaking, the scenarios represent low density, moderate density and high density development, and all conform to current zoning. They were created based on input from interviews, focus groups, an online survey, and the work of land use economist Todd Poole. [.pdf of Poole's market study]

Miller stressed that these scenarios are not recommendations for development, but are being used as conversation starters to get additional feedback. The final recommendation to the city council, which is expected in late October, will likely be a hybrid of the ideas in these scenarios.

The planning commission had a wide-ranging discussion, floating questions and suggestions. Ideas included: (1) creating spaces for food carts to give downtown workers more low-cost lunch options; (2) building structures that are adaptable, and that could easily be transformed from office to residential space; and (3) incorporating aspects of the city’s recently approved sustainability framework, as well as elements of a climate action plan that’s being developed.

Wendy Rampson, the city’s planning manager, raised concerns over Ann Arbor becoming a “Disneyland of foodies,” and stressed the importance of diversity for a healthy downtown. Poole’s market study indicates that Ann Arbor residents spend 1.6 times the national average on dining out and entertainment.

Eric Mahler, a planning commissioner who served on a committee that had recommended a development on top of the Library Lot, cautioned that the public’s response to any proposal can’t be underestimated. People will likely challenge any assumptions related to market demand, he said, such as demand for a conference center. He also indicated that parking and traffic concerns shouldn’t be underestimated – people will raise those issues, too.

Miller noted that one of the lessons they’ve learned from previous unsuccessful efforts is the importance of having conversations in advance of specific proposals, and of reaching out to a more diverse group of people. That’s what they’ve been doing with Connecting William Street, she said, and it’s what they’ll continue to do in the coming weeks as they gather input for a final recommendation. [Full Story]

Review of New Blake Transit Center Continues

Ann Arbor planning commission meeting (July 17, 2012): Two projects – one public, one private – dominated discussion at the most recent planning commission meeting.

Kirk Westphal

Kirk Westphal oversees a vote at the July 17, 2012 Ann Arbor planning commission meeting. He was elected chair at the start of the meeting. In the foreground is commissioner Eleanore Adenekan. (Photos by the writer.)

Commissioners reviewed a site plan for the new Blake Transit Center (BTC), the main downtown hub for the Ann Arbor Transportation Authority. A new two-story transit center will be constructed on the same parcel as the existing center, midblock between Fourth and Fifth avenues, north of William and south of the federal building. But the new building will be located on the east side of that site – near Fifth Avenue, opposite its current location – and the direction of the current bus lane will be reversed. Buses will enter Fourth Avenue into an eastbound lane that exits onto Fifth.

Commissioners voiced a variety of concerns and feedback, centered on improving the pedestrian experience and the appearance of the building and landscaping. They elicited the fact that although zoning would allow for a structure up to 180 feet tall – about 16 stories – the foundation for the new BTC is planned to accommodate only four stories, with a two-story structure to be built initially.

Kirk Westphal said he’d been a bit surprised by news that the AATA is interested in buying the adjacent Fifth & William lot from the city. That possibility was mentioned as part of a design review committee report. He urged AATA’s CEO, Michael Ford, to talk with the Ann Arbor Downtown Development Authority about the AATA’s plans for Fifth & William, and to see if the DDA might be interested in collaborating to increase the footings and allow for a taller structure in the future. He noted that the DDA’s Connecting William Street effort, focused on plans to possibly develop certain city-owned sites, includes the Fifth & William lot.

As a public entity, the AATA does not have to follow the process for site plan approval that is required of private-sector property owners. The process is being conducted for review and input only. However, the planning commission did take a vote, unanimously affirming that the project does meet city requirements for private development, except for interior landscaping and driveway width. It will next be reviewed by the city council.

Another project that drew discussion is a private development proposed by Tom Fitzsimmons, for a three-story townhouse with five housing units at 922-926 Catherine St. During public commentary, several neighbors – including residents of the adjacent Catherine Commons condominiums – spoke in support of the project. However, some of them raised concerns about backups in the stormwater system, which is already a problem along Catherine Street. Staff indicated that those issues are likely tied to design flaws on the site of Catherine Commons. Members of the development team for the new project told commissioners that an underground stormwater detention system on their site could improve the situation along the street, and at the least would not make it worse.

Also at the July 17 meeting, three projects that had previously been considered by commissioners were back for various reasons. A site plan for a Speedway gas station at the northeast corner of North Maple and Miller had been postponed at the commission’s June 5 meeting, but was approved on July 17. Also approved by commissioners was a revised site plan for 2161 W. Stadium Blvd., where a Noodles & Co. restaurant is planned. Commissioners had signed off on the original project at their March 6, 2012 meeting – the revision involves shifting the building’s location 21 feet to the north. The former Sze-Chuan West restaurant there has already been demolished.

And parking for the Chalmers Place retail center on Washtenaw Avenue emerged again at the July 17 meeting. Commissioners approved a plan to increase the number of parking spaces on the center’s site from 88 to 112. A different parking plan had been rejected by the planning commission on May 1, after several neighbors spoke against it. There was no opposition to the new proposal. [Full Story]

AATA’s Transit Center Gets Planning Review

At its July 17, 2012 meeting, the Ann Arbor planning commission reviewed the plan for a new Blake Transit Center, the main downtown hub for the Ann Arbor Transportation Authority. Commissioners voted to affirm that the project meets city requirements for private development, with two exceptions involving landscaping and driveway width.

The new transit center will be constructed on the same site as the existing center, midblock between Fourth and Fifth avenues, north of William and south of the federal building. However, the new center will be built on the opposite side of that site.

Currently a one-story building, built in 1986, is located on the northwest corner of the site, near Fourth Avenue. Buses enter the facility from Fifth Avenue … [Full Story]

Modified Noodles & Co. Site Plan OK’d

A site plan for 2161 W. Stadium Blvd. – where a Noodles & Co. restaurant is planned – received approval from the Ann Arbor planning commission at its July 17, 2012 meeting.

A site plan for that location – site of the former Sze-Chuan West, adjacent to Bell’s Diner and Stadium Hardware – had been previously approved by commissioners at their March 6, 2012 meeting, and subsequently by city council in April. But the future tenant wanted to revise the site plan and shift the building 21 feet to the north. The new location provides space for one row of parking along the south side of the building, to be accessed from the Big M car wash site at 2151 W. Stadium.

The existing … [Full Story]

Housing on Catherine St. Gets Planning OK

The rezoning and site plan for a three-story townhouse with five housing units at 922-926 Catherine St. was recommended for approval at the July 17, 2012 meeting of the Ann Arbor planning commission. The two vacant parcels are on the south side of Catherine between Ingalls and Glen, across from the University of Michigan School of Nursing building. The lots are located in the Old Fourth Ward historic district.

The development – which according to the owner, Tom Fitzsimmons, will be marketed to students, UM employees, young homebuyers, and empty nesters – entails rezoning the parcels from PUD (planned unit development) to R4C (multi-family residential). The PUD zoning is tied to a previous development that was approved but never built. The … [Full Story]

Chalmers Place Parking Project Approved

Ann Arbor planning commissioners have approved a site plan for the Chalmers Place employee parking lot, increasing the number of spaces there. The commissioners took the action at their July 17, 2012 meeting, when they also approved a landscaping modification for the project. The retail/office center is located at the intersection of Chalmers and Washtenaw Avenue, west of Arborland Mall.

The project does not require additional approval by the city council. However, it will need to go before the city’s zoning board of appeals.

A different parking plan had been rejected by the planning commission on May 1, after several neighbors spoke against it during public commentary. That plan had entailed building a new 43-space parking lot at the back of the … [Full Story]

Speedway Station Gets Planning Approval

The site plan for a Speedway gas station at the northeast corner of North Maple and Miller was recommended for approval by the Ann Arbor planning commission at its July 17, 2012 meeting. The plan had been initially considered at the commission’s June 5 meeting, but was postponed.

The project is located at 1300 N. Maple on a 1.39-acre site. The proposal also included a request to rezone a portion of the site from PL (public land) to C3 (fringe commercial). Planning commissioners recommended that for approval as well. The recommendations will be forwarded to the city council.

The plan calls for demolishing an existing 1,500-square-foot vacant service station building, which was built in the 1950s, and constructing a new 3,968-square-foot, … [Full Story]

Environmental, Planning, Greenbelt Appts. OK’d

Four nominations to three different commissions were confirmed by the Ann Arbor city council at its July 2, 2012 meeting. Ken Clein and Kirk Westphal were confirmed for the city planning commission. John German was confirmed for the city’s environmental commission. And Archer Christian was confirmed for the greenbelt advisory commission. All appointments were made on unanimous votes by the council, which is typical.

The nominations for all four appointments were made at the council’s previous meeting, on June 21, 2012. The city planning commission nominations are made by the mayor, which is the case for the vast majority of board and commission appointments. Nominations to the environmental commission and the greenbelt advisory commission are made by the council as … [Full Story]

Townhome Project Raises Density Concerns

Ann Arbor planning commission meeting (June 19, 2012): A proposal to build townhomes on a parcel along Ellsworth Road drew harsh criticism from nearby residents, who argued that this part of Ann Arbor already has more housing units than the city’s services and infrastructure can support.

Claudia Myszke

Claudia Myszke, managing agent of the Forest Hills Cooperative, spoke on behalf of residents there who have concerns about a proposed townhome project on Ellsworth. (Photos by the writer.)

The annexation request for the site of the Summit Townhomes project was recommended for city council approval by the planning commission. However the planning commission postponed action on a related zoning and area plan proposal.

The 2.95-acre site at 2081 E. Ellsworth Road, east of Stone School Road, is currently located in Pittsfield Township. The developer wants to remove an existing single-family home and detached garage, and build 24 townhomes in four, two-story buildings, with attached single-car garages for each unit. The plan calls for R3 (townhouse dwelling district) zoning.

Several residents from the nearby Forest Hills Cooperative townhouse complex came to the June 19 meeting to speak in opposition to the project. They argued that this area is already densely developed, with several major housing developments and a lack of services, like places for children to play. Traffic along Ellsworth was also a concern, especially in light of the soon-to-open Costco on that road, west of South State Street.

In part based on that feedback, commissioners unanimously voted to postpone the zoning and area plan proposals, and asked city planning staff a range of questions that they’d like to have answered before considering those requests. The concerns related to zoning options, traffic volume, the location and amount of parkland in that area, and the capacity of utilities to handle increased density. However, the annexation request will move forward to be considered by the Ann Arbor city council. It was recommended for approval on a 6-1 vote, with Erica Briggs dissenting. Eric Mahler and Wendy Woods were absent.

Briggs also dissented on another request considered by the the planning commission at its meeting – to approve the rezoning and site plan for an expansion of Knight’s Market, and Spring and Miller. The proposal – which had been originally discussed, but ultimately postponed, at the planning commission’s May 15, 2012 meeting – won approval from the other six commissioners, and will be forwarded to the city council for their consideration. Several commissioners expressed concerns, but felt comfortable enough to approve the rezoning and site plan. Briggs said the potential for future commercial expansion and other issues made it impossible for her to support the project.

In other action, the commission unanimously approved their annual work plan, as well as a resolution affirming the city’s master plan. Both actions are required annually under the planning commission’s bylaws.

It was the final meeting for Briggs, who is ending her term this month. She did not request reappointment. Her colleagues on the commission praised her work, with Bonnie Bona saying: ”You may not realize it, but you’ve had a strong influence on all of us.” Ken Clein – a principal with Quinn Evans Architects – has been nominated to replace her and will likely receive city council confirmation at the council’s July 2 meeting. [Full Story]

Planning Group OKs Master Plan Review

Completing an annual requirement, the Ann Arbor planning commission voted at its June 19, 2012 meeting to approve the city’s master plan resolution. The planning commission’s bylaws require that the group review the city’s master plan each May. At its May 1 meeting, the commission held a public hearing on the item – though no one attended – and postponed action until after it held a  planning retreat on May 29.

The resolution approved by commissioners affirmed the existing master plan, which consists of (1) Land Use Element (2009); (2) Downtown Plan (2009); (3) Transportation Plan Update (2009); (4) Non-motorized Transportation Plan (2007); (5) Parks and Recreation Open Space Plan (2011); and (6) Natural Features Master Plan (2004). These documents can be … [Full Story]

Summit Townhomes Project Postponed

An annexation request for the site of the Summit Townhomes project was recommended for approval by the Ann Arbor planning commission on a 6-1 vote, with dissent from Erica Briggs. But the group unanimously voted to follow staff advice by postponing action on a related zoning and area plan. The votes came during the commission’s June 19, 2012 meeting.

The 2.95-acre site at 2081 E. Ellsworth Road, just east of Stone School Road, is currently located in Pittsfield Township. The developer wants to remove an existing single-family home and detached garage, and build 24 townhomes in four, two-story buildings, with attached single-car garages for each unit. The plan calls for R3 (townhouse dwelling district) zoning. The developer is Shawn Barrow of Orlando, Fla.

The development … [Full Story]

Planning Group’s Annual Work Plan OK’d

A work plan for a wide range of city planning commission and staff projects in fiscal 2013 was approved by the Ann Arbor planning commission at its June 19, 2012 meeting. [.pdf of work plan]

The plan, covering the fiscal year that begins July 1, 2012, had been reviewed at a June 12 working session. Items include  development of (1) corridor plans for Washtenaw Avenue and South State Street, (2) a sustainability framework action plan, (3) Zoning Ordinance Re-Organization (ZORO) amendments, and (4) R4C/R2A amendments. Among other things, the plan also includes evaluation of the city’s citizen participation ordinance and A2D2 zoning.

This brief was filed from the second-floor city council chambers at city hall, 301 E. Huron, where the planning commission meets. … [Full Story]

Knight’s Market Project Moves to Council

An expansion plan for Knight’s Market – which includes converting a single-family home into a bakery – won a recommendation of approval from the Ann Arbor planning commission at its June 19, 2012 meeting. The vote was 6-1, with Erica Briggs dissenting. Commissioners Eric Mahler and Wendy Woods were absent. The rezoning and site plan requests will be considered next by city council.

The project had first been discussed, but ultimately postponed, at the commission’s May 15, 2012 meeting. The market is located at the northeast corner of Spring and Miller. The market’s owner, Ray Knight, also owns two separate, adjacent parcels. (Knight is perhaps best known for his family’s restaurant, Knight’s Steakhouse, located at 2324 Dexter Ave.) The grocery store … [Full Story]

Clein Nominated for Planning Commission

At its June 18, 2012 meeting, Ann Arbor mayor John Hieftje announced his nomination to replace Erica Briggs on the city planning commission: Ken Clein, a principal with Quinn Evans Architects. Briggs did not seek re-appointment.

Among the architectural projects Clein has worked on locally are the University of Michigan’s Hill Auditorium renovation, the new Ann Arbor municipal center, and the Zingerman’s Deli expansion.

It was also announced that Kirk Westphal is nominated for re-appointment to the planning commission.

The city council will vote on the appointments of Clein and Westphal at its July 2 meeting. City planning commissioners serve three-year terms.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. … [Full Story]

DTE Project Prompts Questions on Energy Use

Ann Arbor planning commission meeting (June 5, 2012): Planning commissioners acted on two items at their recent meeting that have implications for the city’s future energy use: A proposal for a new DTE Energy substation, and recommendations for a set of sustainability goals.

Erica Briggs

Erica Briggs is ending her term on the Ann Arbor planning commission at the end of June, and is not seeking reappointment. At the June 5 meeting, she lobbied unsuccessfully to postpone a DTE Energy project, arguing that the community needs a broader discussion about whether providing unlimited energy fits the city’s long-term goals of energy reduction.

The estimated $10 million project by DTE to build a new electrical substation was met with caution by commissioner Erica Briggs, who urged her colleagues to postpone the proposal. DTE is building the substation to meet increased energy demands in the city.

The project – called the Buckler substation – had previously been discussed at the commission’s May 15, 2012 meeting, which Briggs did not attend. When the item came up again at the June 5 meeting, she argued that a broader conversation about the community’s energy needs is needed. It’s a rare opportunity for that, she noted, given that projects like this don’t occur frequently – the last Ann Arbor substation was built in the 1960s. She used an analogy to transportation: If a proposal came in to widen all the roads in the community, that idea wouldn’t automatically move forward – because people would stop to discuss whether this is what they want for the city. The DTE project will essentially widen the energy capacity for the city, she said, at a time when the community is talking about the need to reduce its energy use.

As examples, Briggs noted that the city is moving forward with sustainability goals, as well as with a climate action plan. Later in the meeting, the commission unanimously recommended approval of 16 sustainability goals, including three that relate to climate and energy. One of the goals calls for the city to “reduce energy consumption and eliminate net greenhouse gas emissions in our community.”

Briggs made a motion to postpone the substation proposal, but it died for lack of a second as none of the other commissioners at the meeting were supportive of another postponement. A possible ally on the issue – commissioner Bonnie Bona, who works for the nonprofit Clean Energy Coalition – did not attend the June 5 meeting. The project was approved on a 5-1 vote, with Briggs dissenting and three commissioners absent. It does not require further approval by city council.

Another proposal that had been postponed from an earlier meeting in May – Maple Cove Apartments & Village development – was taken up again on June 5. The two apartment buildings and seven single-family homes are proposed at 1649 N. Maple, north of Miller Road between North Maple and Calvin Street on the city’s west side. Safety concerns over two planned entrances off of North Maple had caused the previous postponement, but planning staff reported that the entrances conform to city code.

Two residents of Calvin Street spoke during a public hearing, both of them objecting to the project. Several commissioners also expressed disappointment in the project, as they had at earlier meetings. But they noted that because it conforms to the city’s ordinances, they had no choice but to approve it. Briggs said it pointed to the need to reexamine some problems in the city code that led to this situation. The commission’s unanimous recommendation of approval will be forwarded to city council for consideration.

The vote on a project located near Maple Cove – a proposed Speedway gas station at the northeast corner of Maple and Miller – was postponed by commissioners. City planning staff had recommended postponement, to allow the owner to make requested revisions in a landscaping plan and traffic impact statement.

Two other requests were approved, both related to rezoning of land acquired by the city: (1) two parcels for an expansion of the Bluffs Nature Area, and (2) a site adjacent to the Bryant Community Center. In both cases, commissioners recommended that city council rezone the sites to PL (public land). [Full Story]

South State Corridor Gets Closer Look

As one of Ann Arbor’s primary north-south corridors, South State Street is being studied with an eye toward improving what some see as a congested, unwelcoming gateway to the city. City planning staff are seeking input and developing recommendations for changes along that 2.5-mile stretch, from Stimson at the north end – where The Produce Station is located – all the way south to Ellsworth.

The intersection of South State and Stimson, looking north

The intersection of South State and Stimson, looking north. A study of the South State corridor runs south from Stimson to Ellsworth. (Photos by the writer.)

A diverse range of land uses can be found between those two points, including small commercial enterprises, a large apartment complex, University of Michigan sports facilities, an auto dealership, high-rise office buildings, Briarwood Mall, the snarled I-94 exchange, sprawling research and industrial parks, and the soon-to-open Costco at the southern end, in Pittsfield Township.

The city held a forum recently to update the public about plans for improving South State and to seek input for possible changes. And the Ann Arbor planning commission’s retreat last week focused on the corridor, and included a van tour of the area.

This report covers both of those meetings.

Observations made by planning commissioners about the South State Street corridor at their retreat included: a lack of cohesion; a negative environment for pedestrians and bicyclists; and a sense that the corridor doesn’t reflect the character of Ann Arbor. Several commissioners noted that the stretch is just plain ugly – not an area that evokes the street as a major gateway into Ann Arbor. Suggestions ranged from improved landscaping and wayfinding signs to updating the city’s master plan, reflecting land use goals more in line with the city’s current priorities and sustainability efforts.

This isn’t the only corridor that’s getting attention – efforts to take a strategic look at North Main and Washtenaw Avenue are also underway.

For the South State study, the planning staff expects to develop draft recommendations by the end of this year, with additional public meetings, review by the planning commission, and consideration by the city council. If approved by the council, city staff would begin implementing recommendations. [Full Story]

Land Rezoned for Bryant Community Center

The Ann Arbor planning commission has unanimously recommended rezoning a 0.2-acre site at 5 W. Eden Court from R1C (single-family dwelling) to PL (public land). The vote came at the commission’s June 5, 2012 meeting.

This land was recently purchased for $82,500 using funds from the city’s open space and parkland preservation millage – a purchase approved by the Ann Arbor city council at its Sept. 6, 2011 meeting. It’s located next to the city’s Bryant Community Center.

The recommendation will be forwarded to the city council for its consideration.

This brief was filed from the second-floor council chambers of city hall at 301 E. Huron, where planning commission meetings are held. A more detailed report will follow: [link]

Planning Group OKs Sustainability Goals

A set of 16 sustainability goals could be incorporated into the city’s master plan, if the Ann Arbor city council follows a recommendation made unanimously by the planning commission at its June 5, 2012 meeting.

The commission voted to recommend sustainability goals in four categories: resource management; land use and access; climate and energy; and community. The goals were culled from more than 200 already found in existing city planning documents, as part of a project that began in early 2011. It’s been funded by the Home Depot Foundation grant. [.pdf of sustainability goals]

This work by city staff was initially guided by volunteers who serve on four city advisory commissions: park, planning, energy and environmental. Members from those groups met at … [Full Story]

Rezoning Approved for Bluffs Expansion

At its June 5, 2012 meeting, the Ann Arbor planning commission recommended rezoning two parcels that were recently acquired for expansion of the Bluffs Nature Area at 1099 N. Main St., north of Sunset Road.

A 1.12-acre parcel to the north of the Bluffs – connecting the existing parkland to Huron View Boulevard – is currently zoned O (office), and had been donated to the city by a nursing home near that site. A 0.57-acre addition to the south connects the existing parkland to Sunset Road and is currently zoned R4C (multiple-family dwelling). It had been purchased by the city from the Elks lodge, using funds from the open space and parkland preservation millage. Both parcels are recommended to be rezoned as PL … [Full Story]

Speedway Gas Station Site Plan Postponed

Following a planning staff recommendation, the site plan for a Speedway gas station was postponed by the Ann Arbor planning commission at its June 5, 2012 meeting. The project is located at the 1.39-acre site on the northeast corner of Miller and North Maple roads. Also postponed was a request to rezone a portion of the site at 1300 North Maple from PL (public land) to C3 (fringe commercial).

The plan calls for demolishing an existing 1,500-square-foot vacant service station building and constructing a new 3,968-square-foot, single-story gas station and convenience store with five pumps. The gasoline pumps will be covered by a 28-foot by 121-foot canopy. Fourteen parking spaces will be provided next to the convenience store, and six bicycle … [Full Story]

DTE Buckler Station Gets Planning OK

Following a previous postponement by the Ann Arbor planning commission, the site plan for a new DTE Buckler electrical substation at 984 Broadway near Canal Street got the go-ahead from commissioners at their June 5, 2012 meeting.

Commissioner Erica Briggs made a motion to postpone again, but it died for lack of a second. Briggs had not attended the commission’s May 15, 2012 meeting when this proposal was first discussed, and she expressed concern that the commission had not undertaken a broader conversation about the community’s energy needs. It was a rare opportunity for that, she noted, given that projects like this don’t occur frequently. She used an analogy to transportation – if a proposal came in to widen all the roads … [Full Story]

On Third Try, Maple Cove Project OK’d

At its June 5, 2012 meeting, the Ann Arbor planning commission recommended approval of a site plan for the Maple Cove Apartments & Village development. The project is located on 2.96 acres at 1649 N. Maple, north of Miller Road between North Maple and Calvin Street on the city’s west side.

The plan calls for combining two sites – 1649 N. Maple and 1718 Calvin – and demolishing an existing single-family home and detached garages there. Two 3-story apartment buildings would be built with a 64-space parking lot and eight bike spaces. The project also includes building a private street to serve seven new single-family houses near Calvin Street, but with an entrance off of North Maple. The apartment complex would … [Full Story]

Knight’s Market Plan Draws Neighbor Interest

Ann Arbor planning commission meeting (May 15, 2012): At 3.5 hours, the most recent meeting of the Ann Arbor planning commission reflected a trend that city staff say will likely continue: An uptick in projects coming through the city’s planning pipeline.

Sherry Knight Bedolla

Sherry Knight Bedolla speaks to the Ann Arbor planning commission at its May 15, 2012 meeting. Her father, Ray Knight, bought the former Ty's Market on the corner of Spring and Miller in 1952. Knight's Market is seeking to expand and add a bakery in the current single-family house. They are asking the city to rezone the property from residential to C1 commercial. (Photos by the writer.)

The city’s fiscal year ends June 30. Year to date, 10 zoning or planned unit development (PUD) applications have been received, compared to one in fiscal year 2011. Twenty-one site plans have been submitted this year, compared to 13 in FY 2011. And 494 zoning compliance reviews have been completed this year for building permits, up from 215 in FY 2011 – a 129% increase.

At the commission’s May 15 meeting, five projects were considered. The one drawing most interest from residents was a proposed expansion of Knight’s Market at the corner of Spring and Miller. The plan calls for an addition on the current market building, which has been run by the Knight family since 1952. Three parcels would be combined into one that would be rezoned as C1 (local business), allowing the Knights to turn one of two single-family homes next to the market into a bakery. The bakery wouldn’t have a retail space – it would be used to make products for the market and the family’s restaurants in Ann Arbor and Jackson.

Ten people spoke during a public hearing on the project,  mostly residents of the neighborhood. They expressed support and gratitude for the Knights and their business, but raised concerns about increased truck traffic and “commercial creep.” Residents were also cautious about the future of the site, if ownership changes hands after the property is rezoned for commercial uses.

Speaking on behalf of the family, Sherry Knight Bedolla assured commissioners that there are no plans to sell to a developer – the family simply needs to meet demand for its baked goods, she said. The bakery would also be used to repackage food from the restaurant into ready-to-eat meals that would be sold in the market. At the planning staff’s request, commissioners ultimately voted to postpone action on the project to allow time for additional review.

Also postponed was action on the site plan for DTE Energy’s Buckler electrical substation at 984 Broadway near Canal Street. DTE hopes to build the substation in the utility company’s Ann Arbor service center to provide an increase in electrical power to the downtown area, due to increased demand for electricity. The project is expected to be back on the planning commission’s June 5 agenda. A companion project – a site plan for remediation of the nearby MichCon property on Broadway – was unanimously approved, assuming that a list of contingencies are met.

Two other projects were also unanimously approved: (1) an expansion of parking for the Wintermeyer office complex on South State; and (2) a temporary retail sales special exception use for Phantom Fireworks, to sell fireworks in the parking lot of Colonial Lanes at 1950 South Industrial Highway. [Full Story]