Stories indexed with the term ‘Ann Arbor planning commission’

Planning Group Weighs R4C/R2A Report

Ann Arbor planning commission working session (May 8, 2012): Nearly a year after planning commissioners were briefed on a draft report for zoning changes for Ann Arbor’s near-downtown residential neighborhoods, commissioners were presented this month with the final report from the R4C/R2A zoning district study advisory committee, which has been working on the issue since December 2009.

Matt Kowalski

Matt Kowalski, right, gives a report on recommendations from the R4C/R2A advisory committee at a May 8, 2012 work session of the Ann Arbor planning commission. Next to him is Tony Derezinski, a planning commissioner and city council member who served on the advisory committee. To the left is Wendy Carman, an advisory committee member who took issue with some aspects of the final report. Two other committee members – Eppie Potts and Julie Weatherbee – attended the working session.

Both kinds of zoning districts were established in the 1960s, and applied to existing neighborhoods. R4C allows for multiple-family residential dwellings, such as apartment buildings, while R2A zoning limits density to two-family residential structures. Planning manager Wendy Rampson described the R4C zoning as “broken” –and most of the committee recommendations relate to R4C districts.

Concerns about R4C/R2A districts have been raised since at least the mid-1980s, and are tied to the question of how dense these areas can be. Although there were smaller projects that caused concern,  two more recent large housing proposals – The Moravian, and City Place – brought the issue to the forefront for people on both sides of the density debate.

In particular, the controversial City Place project on South Fifth Avenue, which combined multiple lots and demolished seven residential houses to build two apartment buildings, has been cited as an example of the need to address R4C zoning. City Place changes the streetscape of that neighborhood, but is analyzed as conforming to current zoning code.

The final committee report includes 10 recommendations, with accompanying analysis. [.pdf of recommendations] The major recommendations relate to: (1) rebuilding structures that don’t conform to existing zoning; (2) rezoning certain areas from R4C to R2A; (3) reducing minimum lot sizes and minimum lot widths; (4) exploring the creation of zoning overlay districts; (5) revising density calculations; (6) revising parking standards; and (7) changing requirements for lot combinations.

Commissioners praised the work of the committee, but much of the discussion related to future process: What are the next steps to take, now that the report has been completed? It’s likely that the group’s ordinance revisions committee will tackle the job of making recommendations for specific ordinance language to implement the changes. Those ordinance revisions would then be reviewed by the planning commission, which would forward its recommendations to city council.

In terms of content, commissioners mostly focused on the idea of overlay districts, which would be a way of preserving the character of different, distinct R4C neighborhoods. Commissioner Bonnie Bona floated the concept of form-based code as an option. Described in a very general way, a form-based approach tends to be more proscriptive regarding the types of buildings that the community wants to see in a particular district, including their design. In contrast, traditional zoning typically sets an allowable range of uses, sizes, placements, and other aspects for a development, but generally leaves the details of those decisions to the developer.

It was generally acknowledged that either approach – form-based or one with overlay districts – would be a complex issue to tackle.

Three advisory committee members – Wendy Carman, Ethel “Eppie” Potts, and Julie Weatherbee – attended the May 8 session. Carman and Potts spoke during public commentary to amplify written comments they had provided as supplements to the report, expressing concerns that some aspects of the report don’t accurately reflect the committee’s views.

During the May 8 session, commissioners also were updated on the city’s sustainability goals, which they’ll be asked to vote on at their May 15 meeting. This report focuses only on the R4C/R2A portion of the working session. [Full Story]

Action on DTE Site Plan Postponed

Action on a site plan for a new DTE Buckler electrical substation at 984 Broadway near Canal Street was postponed by Ann Arbor planning commissioners at their May 15, 2012 meeting. City planning staff had recommended postponement to allow more time to review several outstanding issues. For example, staff has recommended that DTE seek a variance from the city’s zoning board of appeals for a 100-year detention requirement – the proposed site plan would require such a variance. The site is located within the Huron River’s 100-year floodplain.

The project also needs a variance to the 15-foot conflicting land use buffer requirements along the east side property line, adjacent to Riverside Park. DTE is requesting a variance that would allow 33 trees and 38 … [Full Story]

Planning Group OKs MichCon Remediation

A site plan for remediation of the MichCon property at 841 Broadway was unanimously approved by the Ann Arbor planning commission at its May 15, 2012 meeting. The proposal was made in conjunction with a site plan for a new DTE Buckler electrical substation on the opposite side of Broadway. Planning commissioners voted to postpone action on that site plan at the same May 15 meeting. MichCon is a subsidiary of DTE.

The MichCon site plan approval is contingent on three things: (1) obtaining variances from the city’s zoning board of appeals (ZBA) to exempt MichCon from providing a new stormwater management system; (2) obtaining a Michigan Dept. of Environmental Quality (MDEQ) permit for work within the floodplain and Huron River; and (3) indicating water main … [Full Story]

Wintermeyer Parking Expansion Approved

At its May 15, 2012 meeting, the Ann Arbor planning commission unanimously approved an expansion to the Wintermeyer office parking lot at 2144 and 2178 South State St., south of Stimson and east of the University of Michigan golf course. The commission also voted to approve a landscape modification on the 1.8-acre site, contingent on administrative approval of relocated plantings between the site and a home to the north.

Two two-story office buildings are currently located on the site, along with an 85-space parking lot. The parcel is zoned O (office). After the expansion, there will be a total of 101 parking spaces on the site. A maximum of 111 parking spaces are allowed for the existing office development.

Modifications to the landscaping … [Full Story]

Phantom Fireworks Gets Special Exception

At its May 15, 2012 meeting, the Ann Arbor planning commission unanimously voted to grant a temporary retail sales special exception use for Phantom Fireworks, a firm based in Youngstown, Ohio.

According to a staff report, the business is proposing to put up a 40×40-foot tent and an 8×40-foot storage pod in the parking lot of Colonial Lanes at 1950 South Industrial Highway. The tent would be set back 25 feet from South Industrial and take up 24 parking spaces on 2.96-acre site, leaving 203 parking spaces for the bowling alley and Cubs A.C. restaurant.

The northeast, two-way traffic entrance would be temporarily closed by placing four orange traffic cones and yellow tape in the parking lot. The remaining four entrances to the … [Full Story]

Action on Knight’s Market Postponed

Ann Arbor planning commissioners, following advice from city staff, voted unanimously to postpone action on a request from Knight’s Market. The rezoning and site plan proposal – which would allow the neighborhood market to expand and add a bakery – was on the agenda for the commission’s May 15, 2012 meeting.

Knight’s Market is located at the northeast corner of Spring and Miller. The market’s owner, Ray Knight, also owns two separate, adjacent parcels. (Knight is perhaps best known for his family’s restaurant, Knight’s Steakhouse, located at 2324 Dexter Ave.) The grocery store is on land zoned zoned C1 (local business) and M1 (light industrial). Another parcel at 306-308 Spring St. is zoned R2A (two-family dwelling) and M1, and contains two single-family … [Full Story]

No on Chalmers Parking, Maple Cove Delayed

Ann Arbor planning commission meeting (May 1, 2012): A nearly 3.5-hour meeting was devoted in large part to public commentary – hearings on two projects drew two dozen speakers.

Len Nadolski, Tony Derezinski

Len Nadolski, left, talks with city councilmember Tony Derezinski before the start of the May 1, 2012 Ann Arbor planning commission meeting. Nadolski owns the Chalmers Place Retail Center on Washtenaw Avenue and hopes to add a parking lot behind the center. The proposal was rejected by the planning commission, on which Derezinski serves. (Photos by the writer.)

About half of those speakers came out to oppose a parking project for the Chalmers Place Retail Center on Washtenaw Avenue, located next to Paesano restaurant in the former Arbor Dodge lot. The owner – Len Nadolski of Howell – asked to rezone a vacant parcel behind the center to P (parking), from its current single-family residential zoning. He said the center has been unable to lease all of its stores because tenants are concerned about a lack of parking.

Commissioners expressed sympathy for the owner, but voted against recommending the rezoning. The majority of commissioners did not feel that the situation warranted overriding the master plan, which calls for that property to be zoned residential. Erica Briggs said the situation added urgency to plans to make the Washtenaw Avenue corridor more safe and amenable to walking and biking.

Eric Mahler cast the lone vote in favor of rezoning. He said he normally wouldn’t support a proposal that was essentially “spot zoning,” but in this case he voted for the plan because he didn’t see any viable alternatives for the owner.

Another project that drew public commentary had previously been recommended for approval by the commission: Maple Cove Apartments & Village development, located on North Maple near Miller Road. The commission had approved the project at its March 20, 2012 meeting. But that vote was rescinded when it was discovered that Scio Township residents on Calvin Street had not been included in an original public notice mailed out for the commission’s March meeting.

Nearby residents voiced several concerns about the project – including density, flooding, aesthetics, traffic and a lack of sidewalks from North Maple back to the seven houses. Those issues were echoed by some of the commissioners, who also complained about the lack of responsiveness from the property owner, Muayad Kasham of Dynasty Enterprises. He has not attended the commission’s meetings to address concerns.

But it was the two proposed entrances off of North Maple – separate entrances for the apartments and the single-family homes – that prompted the most discussion among commissioners, and ultimately the move to postpone. Wendy Woods pointed out that the city’s traffic engineer had advised that a single entrance would be preferable. The city code allows for two entrances, however, based on the property’s lineal frontage. The owner has indicated a commitment to two entrances in order to market the apartments and single-family homes separately, and the city code allows for two entrances based on the property’s lineal frontage.

No date has been set for when the project will next appear on the planning commission agenda.

The commission also approved the city’s 2013-2018 capital improvements plan (CIP), with only minor modifications from the previous year. But commissioners voted to postpone action on a master plan update – they’re expected to discuss it at a retreat set for Tuesday, May 29.

The final item of the meeting was dispatched quickly, as commissioners recommended rejecting a proposed revision to the city’s medical marijuana zoning ordinance. The proposal – recommended by the medical marijuana licensing board – was to strike one sentence from the zoning ordinance: “Medical marijuana dispensaries and medical marijuana cultivation facilities shall be operated in compliance with the MMMA (Michigan Medical Marijuana Act).” Commissioners expressed caution about the implications of eliminating the sentence, with Mahler stating that the change would authorize illegal uses, and would have severe consequences for the city. [Full Story]

Commission Votes against Marijuana Revision

On a unanimous vote, the Ann Arbor planning commission recommended denial of a proposed change to the city’s zoning code for medical marijuana dispensaries and cultivation facilities. The vote came at the end of the commission’s May 1, 2012 meeting.

The city’s medical marijuana licensing board had recommended one change – to strike the following sentence from the zoning ordinance: “Medical marijuana dispensaries and medical marijuana cultivation facilities shall be operated in compliance with the MMMA (Michigan Medical Marijuana Act).” [.pdf of the recommended zoning ordinance change]

The board’s recommendation had been sent to Ann Arbor city council. But at their April 2, 2012 meeting, councilmembers voted 9-1 to instead direct the planning commission to review the medical marijuana zoning ordinance. … [Full Story]

Chalmers Place Parking Plan Rejected

At its May 1, 2012 meeting, the Ann Arbor planning commission recommended denial of three resolutions related to a  proposal for Chalmers Place, at 2090 Chalmers Drive near the intersection with Washtenaw Avenue: (1) rezoning a vacant lot from R1B (single-family residential) to P (parking); (2) authorizing the disturbance of a 25-foot natural features open space; and (3) a site plan for the parking lot. The site is west of Arborland Mall. All votes were 1-7, with support only from commission chair Eric Mahler. Bonnie Bona was absent.

The city’s planning staff had also recommended denial of the proposal because it did not conform to the city’s master plan for that area, and because a parking lot would cause greater disturbance to the … [Full Story]

On Second Vote, Maple Cove Postponed

At its May 1, 2012 meeting, the Ann Arbor planning commission rescinded its previous action regarding a site plan for the Maple Cove Apartments & Village development and reconsidered the proposal. The reconsideration resulted in a postponement, to get more information from the traffic engineer about whether the proposed two separate entrances to the property created a health, safety and welfare hazard. The vote to postpone was 7-1, with dissent from commission chair Eric Mahler. Bonnie Bona was absent.

The commission had previously approved the project at its March 20, 2012 meeting. But that vote was rescinded because Scio Township residents on Calvin Street had not been included in an original public notice mailed out for the commission’s March meeting. There were no changes … [Full Story]

Preschool, Gas Station Expansions Approved

Ann Arbor planning commission meeting (April 17, 2012): Action items at the recent planning commission meeting were dispatched with relative speed – the session lasted less than an hour.

Eric Mahler

Eric Mahler, chair of the Ann Arbor planning commission. (Photos by the writer.)

Approval was given for (1) zoning changes allowing an expansion of the Shell station’s retail store at Ann Arbor-Saline and West Eisenhower Parkway, (2) a site plan and special exception use for the Allen Creek Preschool, located at 2350 Miller Ave.; and (3) a slight revision to the special exception use for the Michigan Alpha Chapter of Sigma Phi Epsilon house at Tappan and Hill – increasing by one the number of beds allowed at the fraternity.

The brevity of recent planning commission meetings will be offset by packed agendas anticipated in May. The May 1 agenda items will likely include: (1) review of a possible revision to the city’s medical marijuana zoning ordinance, as directed by city council at their April 2 meeting; (2) update of the city’s capital improvements plan (CIP); (3) a master plan review; and (4) reconsideration of the Maple Cove project, after it was discovered that notices hadn’t been mailed out to all nearby residents for the previous planning commission meeting.

Two other major items that have been in the works since 2009 will be making their way back to planning commissioners soon. A draft report from the R4C/R2A zoning district advisory committee is nearly completed and might be reviewed as soon as the commission’s May 8 working session. Also, a consultant’s report on a zoning ordinance reorganization effort known as ZORO will be presented to planning commissioners in the coming weeks. Rampson told commissioners that the consultant described Ann Arbor’s current zoning ordinances as some of the worst he’s seen – complex, convoluted, and conflicting.

After being briefed on upcoming topics at an April 10 working session, planning commission chair Eric Mahler quipped, “The days of the marathon meetings are back.” Commissioner Diane Giannola gave this advice to the newer commissioners: “Come prepared with snacks.”

At least one new member will be joining the commission this summer. Following the April 17 regular meeting, commissioner Erica Briggs told The Chronicle that because of other time commitments, she would not be seeking reappointment when her term ends this July. She said she wanted to alert others who might be interested in applying for the position. [Full Story]

Allen Creek Preschool Plan OK’d

A site plan for the Allen Creek Preschool, located at 2350 Miller Ave., was recommended unanimously for approval by the Ann Arbor planning commission at its April 17, 2012 meeting. The commission also granted a special exception use for the project.

The project entails building a one-story, 929-square-foot addition onto the west end of an existing 3,111-square-foot preschool building, for a new total of 4,040 square feet. The preschool has an agreement with the Korean Methodist Church at 1526 Franklin Street to use eight parking spaces at the church lot. On-street parking is available on Miller Avenue and Franklin Street.

The special exception use is required because the project is located on a site zoned R1C (single-family dwelling district). According to a staff memo, the … [Full Story]

Fraternity’s Special Exception Use Tweaked

A slight revision to a special exception use for the Michigan Alpha Chapter of Sigma Phi Epsilon – increasing by one the number of beds allowed in its house at 730 Tappan – was granted unanimously by the Ann Arbor planning commission at its April 17, 2012 meeting. The change now allows for 45 beds, including an additional separate bedroom for the required in-house manager.

The commission had granted the original special exception use more than a year ago, at its March 1, 2011 meeting. That had allowed the fraternity to convert a church at the northwest corner of Tappan and Hill into a fraternity house. The building previously had been the home of the Memorial Christian Church, which is now located … [Full Story]

Shell Station PUD Recommended for Approval

The Ann Arbor planning commission voted unanimously to recommend approval of a request from owners of the Shell service station at the northeast corner of Ann Arbor-Saline and West Eisenhower Parkway – to revise the zoning regulations associated with the parcel. The vote took place at the commission’s April 17, 2012 meeting.

Owners of the station are asking for revisions to the site’s planned unit development (PUD), which would allow them to build additions onto the existing 1,000-square-foot convenience store. The new additions would total 4,089 square feet, including 2,189 square feet to the north and east of the store. Their plan also calls for converting the 900-square-foot carwash area into new retail space. The existing access drive to the carwash would be … [Full Story]

Despite Concerns, North Maple Housing OK’d

Ann Arbor planning commission meeting (March 20, 2012): After raising a series of concerns about a new residential development on North Maple Road, a majority of planning commissioners recommended it for approval on a 6-2 vote.

Public hearing sign posted for the proposed Maple Cove housing project

A public hearing sign posted at the site of the proposed Maple Cove residential development on North Maple, north of Miller Road on the city's west side. The project includes seven single-family homes and two apartment buildings. (Photos by the writer.)

The Maple Cove Apartments & Village development is proposed on nearly 3 acres at 1649 N. Maple, north of Miller Road on the west side of North Maple. It would consist of a small court with seven single-family homes, as well as two 3-story apartment buildings each with 18 one-and two-bedroom apartments. There will be two separate entrances off of North Maple – one for the houses, and another for the apartments. This was one of the issues raised by commissioners, as several of them preferred a single entrance to minimize conflicts between pedestrians and vehicles.

Pedestrian safety was also a concern for the drive into the single-family housing section of the development – there are no plans for a sidewalk on that street. Another concern raised by a neighbor during the public hearing – and echoed by some commissioners – was the potential for crime at the apartments, and whether crime data from nearby complexes should be requested to help evaluate the Maple Cove project. Tony Derezinski, a city councilmember who also serves on the planning commission, called using crime data as one of the criteria for approval a “slippery slope” and advised against it.

The possibility was floated to postpone action on the project until some of these concerns could be addressed, but no one made a formal motion to that effect. Brad Moore, a representative for the developer, pointed out that the project as proposed conforms with the city’s zoning ordinances.

Voting against the project were Bonnie Bona and Eric Mahler. The site plan will now be considered by the city council for approval.

Commissioners dispatched a second project on the agenda relatively quickly. After posing a few minor questions, they unanimously recommended approval of a new pump station at the city’s water treatment plant, on Sunset east of Newport Road. [Full Story]

Maple Cove Site Plan Gets Planning OK

On a 6-2 vote, the site plan for the Maple Cove Apartments development was recommended for approval by the Ann Arbor planning commission at its March 20, 2012 meeting. The project is located on 2.96 acres at 1649 N. Maple, north of Miller Road between North Maple and Calvin Street on the city’s west side. Voting against the project were Bonnie Bona and Eric Mahler. The project will now be considered by the city council for approval.

The plan calls for combining two sites – 1649 N. Maple and 1718 Calvin – and demolishing an existing single-family home and detached garages there. Two 3-story apartment buildings would be built with a 64-space parking lot and eight bike spaces. The project also includes building … [Full Story]

Site Plan for Water Pump Station Approved

The site plan for a new pump station at the city’s water treatment plant – needed to serve increased demand in Scio Township – was unanimously recommended for approval by the Ann Arbor planning commission at its March 20, 2012 meeting. The recommendation will be forwarded to the city council.

The 5,114-square-foot structure will be located on the east side of the existing administration building at 919 Sunset, east of Newport Road. Only one floor of the three-level station will be above ground. The city’s water treatment plant provides water to all of Ann Arbor and parts of Scio Township.

This brief was filed from the second-floor council chambers at city hall, 301 E. Huron St., where the planning commission holds its … [Full Story]

Planning Group Revisits Huron River Report

Ann Arbor master plan revisions committee meeting (March 8, 2012): At the request of planning commissioner Kirk Westphal, a committee charged with reviewing changes to the city’s master plan is looking at a recommendation related to land near the Huron River.

Ann Arbor master plan revisions committee

Members of the Ann Arbor planning commission, from left: Eleanore Adenekan, Kirk Westphal and Diane Giannola. At the right is Wendy Rampson, head of the city's planning staff. Commissioners were attending the March 8, 2012 meeting of the master plan revisions committee. (Photos by the writer.)

The Huron River and Impoundment Management Plan, known as HRIMP, was completed in 2009. But in large part because of controversy related to Argo Dam – centered on whether or not the dam should be removed – none of the 30 other recommendations were implemented.

Only one of the HRIMP recommendations relates to land use, and is therefore in the purview of the planning commission. That recommendation calls for limited commercial development – such as a restaurant or other publicly-used entity – in the Broadway bridge/Argo area.

Much of the discussion at the March 8 committee meeting centered on the property now owned by MichCon, a subsidiary of DTE Energy, located north of Broadway Street, between the Huron River and the railroad tracks that run past the Amtrak station. A state-supervised cleanup effort is underway at that site, but its future use – including the possibility that it could be acquired by the city and turned into a park – is unclear.

Remediation of the MichCon site was also a topic at the March 12, 2012 Ann Arbor city council work session, where the property’s potential future use was discussed. That presentation also included an update on a whitewater river feature that DTE Energy is paying for. The whitewater section to be built in the Huron River was originally part of the same project as the city’s Argo Dam bypass reconstruction. The bypass, which has been recently named the Argo Cascades, is nearly complete.

This article includes a summary of the council working session related to the MichCon cleanup, as well as a report on the master plan revisions committee meeting. Based on discussions at that committee meeting, it seems likely that a proposal will be forwarded to the full planning commission to add the HRIMP recommendation to the city’s master plan. Any changes to the master plan would also require city council approval. [Full Story]

Planning Action: Cars, Noodles, Donuts & Gas

Ann Arbor planning commission meeting (March 6, 2012): Site plans for two food chains – a Tim Hortons at State and Ellsworth, and Noodles & Co. on West Stadium Boulevard, south of Liberty – were recommended for approval at the most recent planning commission meeting.

Former Szechwan West building

A car pulls into West Stadium Boulevard from a driveway next to the former Sze-Chuan West restaurant. The Ann Arbor planning commission recommended approval of a proposal to tear down the structure and build a Noodles & Co. restaurant there. (Photos by the writer.)

Much of the discussion about the Tim Hortons site focused on a proposed roundabout at that intersection. Though the coffee and donut shop will likely be built by late summer – about a year before the roundabout is expected to be in place – a spokesman for the company said they’ll be designing the site with the roundabout in mind.

Commissioners also recommended approval of a new AAA branch on South Main, across from Michigan Stadium. The plan calls for rezoning a portion of the site to accommodate more parking than the current office zoning would allow – a total of 35 spaces. That’s a reduction from the amount of parking currently on the site, which was approved in the mid-1970s, but it no longer conforms with existing zoning.

Commissioners Bonnie Bona, Erica Briggs and Kirk Westphal expressed concerns about rezoning an area along Main Street for parking. They also wondered whether 35 spaces were necessary, especially when there are alternative parking options – at a park-and-ride at Pioneer High, and in the nearby neighborhood. Briggs noted that it ran counter to the city’s efforts to encourage alternative transportation. Those three commissioners voted against the rezoning, but the resolution passed on a 6-3 vote. It will still require city council approval.

Also at the March 6 meeting, commissioners postponed action on a request from owners of the Shell service station at the northeast corner of Ann Arbor-Saline and West Eisenhower Parkway. Owners of the station hope to build additions onto the existing 1,000-square-foot convenience store, but planning staff recommended postponement in order to gather additional information and analysis about the plan. [Full Story]

AAA Project Gets Planning Group OK

A site plan and rezoning for two Main Street parcels owned by the Automobile Club of Michigan – where an AAA branch is currently located – were recommended for approval by the Ann Arbor planning commission at its March 6, 2012 meeting.

The requests relate to 1100 and 1200 S. Main, across from Michigan Stadium. An AAA branch built in the 1950s is located there. The owner wants to build a new branch on a different part of the site, tear down the existing building, and reconfigure parking spaces.

The two parcels are part of a 1.5-acre site containing four parcels owned by AAA and all zoned O (office). Located on the 1200 S. Main parcel is the current one-story branch building with … [Full Story]

Revised Shell Station PUD Postponed

The Ann Arbor planning commission voted unanimously to postpone action on a request from owners of the Shell service station at the northeast corner of Ann Arbor-Saline and West Eisenhower Parkway. The vote took place at the commission’s March 6, 2012 meeting.

Owners of the station are asking for revisions to the site’s planned unit development (PUD), which would allow them to build additions onto the existing 1,000-square-foot convenience store. The new additions would total 4,089 square feet, including 2,189 square feet to the north and east of the store. Their plan also calls for converting the 900-square-foot carwash area into new retail space. The existing access drive to the carwash would be landscaped, and the parking lot would be reconfigured for a … [Full Story]

Planning Group OKs State St. Tim Hortons

A site plan for a new Tim Hortons restaurant at 3965 S. State St. was unanimously recommended for approval by the Ann Arbor planning commission at its March 6, 2012 meeting. The site is located on the east side of the street, near the intersection of State and Ellsworth.

The plan calls for demolishing a vacant building on the 2.23-acre site where previous restaurants, including Enzo’s and Gallagher’s, were located. In its place, a one-story 1,953-square-foot restaurant with drive-thru facilities would be built on a 1.18-acre site divided from the current parcel. The building would face West Ellsworth and use an existing shared drive on South State, as well as a relocated drive onto West Ellsworth. An outdoor seating area is proposed on the … [Full Story]

Site Plan for Noodles Restaurant OK’d

A plan for a new Noodles & Co. restaurant at 2161 W. Stadium Blvd. – site of the former Sze-Chuan West, a building adjacent to Bell’s Diner and Stadium Hardware – received a unanimous recommendation of approval from the Ann Arbor planning commission at its March 6, 2012 meeting. The plan will be forwarded to the city council for approval.

The proposal calls for demolishing the existing 4,300-square-foot restaurant and building a new 2,679-square-foot one-story restaurant with a 615-square-foot enclosed patio at the front of the building. The 1.15-acre site is located on the west side of West Stadium, south of Liberty. The project would also reconfigure the existing parking lot and provide additional landscaping.

The site plan approval would be contingent on a … [Full Story]

Lack of Quorum Stymies Planning Meeting

Ann Arbor planning commission meeting (Feb. 23, 2012): The planning commission did not achieve a quorum of members on Thursday evening and therefore could not conduct its full meeting.

Ann Arbor planning commissioners

Ann Arbor planning commissioners and staff talk to high school students in city council chambers on Feb. 23. From left: Wendy Woods, Bonnie Bona, city planner Alexis DiLeo, and Kirk Westphal. (Photos by the writer.)

Five of the nine commissioners are needed for a quorum to conduct business, and only four attended. In addition to those four, about 10 people showed up for the two main action items on the agenda, and several high school students were attending as part of a class assignment.

After waiting about 30 minutes, vice chair Kirk Westphal and Wendy Rampson, head of the city’s planning staff, conferred and decided to hear public commentary. One person spoke. John Chamberlain, an attorney representing the Automobile Club of Michigan, came to the podium only to say that he and his team would return for the commission’s next meeting, on March 6.

The club wants to tear down its existing AAA branch near Michigan Stadium and build a new one, and was requesting approval for a site plan. The other main action item on Thursday’s agenda was site plan approval to build a new Noodles restaurant on West Stadium Boulevard, at the location of the former Sze-Chuan West. Both projects will be considered at the planning commission’s March 6 meeting. [Full Story]

Land Use, Transit Factor Into Sustainability

How do Ann Arbor’s land use policies affect where people live and work, and the way they get from one place to another? What is the city doing to support sustainable approaches?

Joe Grengs Ginny Trocchio

Joe Grengs, a University of Michigan associate professor of urban and regional planning, and Ginny Trocchio, who manages the city's greenbelt program, were among the speakers at a Feb. 9 sustainability forum.

Issues of land use and accessibility were the topic of a sustainability forum on Feb. 9, the second in a series that’s part of a broader city sustainability initiative. During the forum, city staff also unveiled a set of draft goals for Ann Arbor related to four general sustainability themes: Resource management; land use and access; climate and energy; and community.

Wendy Rampson, head of the city’s planning staff, told the audience that the 15 draft goals were extracted from more than 200 that had been identified in existing city planning documents. The hope is to reach consensus on these sustainability goals, then present them to the city council as possible amendments to the city’s master plan.

Speakers at the Feb. 9 forum included Joe Grengs, a University of Michigan associate professor of urban and regional planning; Susan Pollay, executive director of the Ann Arbor Downtown Development Authority; Eli Cooper, the city’s transportation program manager and member of the Ann Arbor Transportation Authority board; Jeff Kahan of the city’s planning staff; Ginny Trocchio, who manages the city’s greenbelt program; and Evan Pratt of the city’s planning commission.

A Q&A followed presentations by the speakers and covered a wide range of topics, including thoughts on the proposed Fuller Road Station. The following day, Feb. 10, the city and University of Michigan announced plans to halt the initial phase of that controversial project – a large parking structure near the UM medical campus.

The topics of the series of forums reflect four general sustainability themes: Resource management; land use and access; climate and energy; and community. The first forum, held in January, focused on resource management, including water, solid waste, the urban forest and natural areas.

All forums are held at the downtown Ann Arbor District Library and are being videotaped by AADL staff. The videos will be posted on the library’s website. Additional background on the Ann Arbor sustainability initiative is on the city’s website. See also Chronicle coverage: “Building a Sustainable Ann Arbor,” and an update on the project given at the November 2011 park advisory commission meeting. [Full Story]

Planning Commission Upholds A2D2 Zoning

Ann Arbor planning commission meeting (Feb. 7, 2012): In their main action item at Tuesday’s meeting, planning commissioners voted unanimously against a rezoning request at 1320 S. University – reaffirming one of the decisions of the contentious, multi-year A2D2 initiative that was approved by the city council in 2009.

Gwen Nystuen, Bob Snyder, Walter

Bob Snyder, with his dog Walter, talks with Gwen Nystuen before the start of the Feb. 7 planning commission meeting. Both Snyder and Nystuen spoke during a public hearing to oppose rezoning of 1320 S. University. (Photos by the writer.)

Currently at the site – on the south side of South University, between Forest and Washtenaw avenues – is the three-story Park Plaza apartment building. It’s owned by Philip Sotiroff, who hoped to construct a mixed-use building  – retail and residential – as tall as 145 feet. That height would allow for a structure between 10-14 stories on the 0.82-acre site. The current zoning is D2 (downtown interface), which does not allow for a structure taller than 60 feet.

Sotiroff is asking the city to rezone the parcel to D1, a zoning district that allows for the greatest density development. Representatives from his development team noted that higher density zoning was allowed prior to 2009, and pointed out that initially the D1 designation had been recommended by the planning commission before the final version of A2D2 was adopted.

The site is adjacent to a D1 parcel to the east, where the Landmark apartment building is being constructed, at 601 S. Forest. But the 1320 S. University property also abuts lower-density residential zoning. Single-family homes are located to the south of the site, and a fraternity is located to the west.

Fifteen people spoke during a public hearing about the rezoning. Most of them were residents and neighborhood leaders who objected to the proposed rezoning, though the request did receive letters of support from owners of the Landmark as well as from the South University Area Association, a merchants’ group.

Planning staff recommended denial. All of the planning commissioners spoke in support of the current zoning, saying that the community had reached a hard-won consensus that was not to be overturned lightly, especially since it was implemented fairly recently. A couple of commissioners noted that the owner could find flexibility within the existing zoning by submitting a planned project – like the 618 S. Main development that planning commission approved at its Jan. 19, 2012 meeting. [Full Story]

Rezoning Denial Recommended on South U.

At its Feb. 7, 2012 meeting, the Ann Arbor planning commission voted unanimously to recommend denial of a rezoning request for 1320 S. University Ave., where the three-story Park Plaza apartment building is located. The property – on the south side of South University, between Forest and Washtenaw avenues – is owned by Philip Sotiroff, who hoped to build a mixed-use (retail and residential) building as high as 145 feet. That height would allow for a structure of between 10-14 stories on the 0.82-acre site. The current zoning – D2 (downtown interface) – does not allow for a structure taller than 60 feet. The city’s planning staff had also recommended denial of the rezoning request.

Fifteen people spoke during a public hearing about the … [Full Story]

618 S. Main Project Gets Planning Support

Ann Arbor planning commission meeting (Jan. 19, 2012): A major development on the south edge of downtown Ann Arbor – between Main and Ashley, north of Mosley – was generally praised by planning commissioners at their most recent meeting, and unanimously recommended for approval.

618 South Main

Looking north from Mosley at the site of the proposed 618 S. Main apartment complex. The former Fox Tent & Awning building will be demolished. Ashley Street runs to the left of this photo, and borders the Old West Side historic district. (Photos by the writer.)

The 618 S. Main project is an apartment complex geared toward young professionals, according to developer Dan Ketelaar. The 7-story building would include 190 units for 231 bedrooms, plus two levels of parking for 121 vehicles.

The project borders the Old West Side historic district – the board of the Old West Side Association submitted a letter of support for the development. Parking and traffic concerns were raised by some commissioners, but the project received praise for its design and its potential to enliven that part of the city. The planning staff had recommended approval.

Two other projects gained approval from commissioners at their Jan. 19 meeting. Rezoning and a site plan for a small addition to the Habe Mills Pine Lodge – owned by the Society of Les Voyageurs – will move forward to the city council with a recommendation of approval. The lodge is adjacent to city parkland near Argo Pond, and had been erroneously zoned as public land.

The commission also signed off on a special exception use at 3645 Waldenwood, which would allow an accessory apartment to be added to the single-family house there. It’s located in the Earhart Estates neighborhood, west of Earhart and south of Glazier Way, in the city’s northwest side.

Several commissioners expressed support of this project and for accessory units in general. “Accessory dwelling units can be an asset to our community and I hope we see more in the future,” said commissioner Erica Briggs. [Full Story]

618 S. Main Project Moves to City Council

The site plan and development agreement for 618 S. Main – a major new residential project in downtown Ann Arbor – received a unanimous recommendation of approval from the Ann Arbor planning commission at its Jan. 19, 2012 meeting. The project now will be forwarded to the city council for consideration.

The planned project is located at the site of the former Fox Tent & Awning building, north of Mosley between Main and Ashley. It borders properties in the Old West Side historic district, but is not in the district itself. The proposal calls for demolishing two existing structures and erecting a 7-story, 153,133-square-foot apartment building with 190 units for 231 bedrooms.

The building would contain 70 studio apartments, 70 one-bedroom units, 42 … [Full Story]

Planning Group OKs Accessory Apartment

At its Jan. 19, 2012 meeting, the Ann Arbor planning commission unanimously approved a special exception use at 3645 Waldenwood, which will allow an accessory apartment to be added to the single-family house there. It’s located in the Earhart Estates neighborhood, west of Earhart and south of Glazier Way, in the city’s northwest side.

According to planning staff, this is only the second time a special exception use has been requested for an accessory unit since the accessory dwelling ordinance was crafted in the early 1980s. Several commissioners expressed support of this project and for accessory units in general. “Accessory dwelling units can be an asset to our community and I hope we see more in the future,” said commissioner Erica … [Full Story]