Preschool, Gas Station Expansions Approved

Ann Arbor planning commission meeting (April 17, 2012): Action items at the recent planning commission meeting were dispatched with relative speed – the session lasted less than an hour.

Eric Mahler

Eric Mahler, chair of the Ann Arbor planning commission. (Photos by the writer.)

Approval was given for (1) zoning changes allowing an expansion of the Shell station’s retail store at Ann Arbor-Saline and West Eisenhower Parkway, (2) a site plan and special exception use for the Allen Creek Preschool, located at 2350 Miller Ave.; and (3) a slight revision to the special exception use for the Michigan Alpha Chapter of Sigma Phi Epsilon house at Tappan and Hill – increasing by one the number of beds allowed at the fraternity.

The brevity of recent planning commission meetings will be offset by packed agendas anticipated in May. The May 1 agenda items will likely include: (1) review of a possible revision to the city’s medical marijuana zoning ordinance, as directed by city council at their April 2 meeting; (2) update of the city’s capital improvements plan (CIP); (3) a master plan review; and (4) reconsideration of the Maple Cove project, after it was discovered that notices hadn’t been mailed out to all nearby residents for the previous planning commission meeting.

Two other major items that have been in the works since 2009 will be making their way back to planning commissioners soon. A draft report from the R4C/R2A zoning district advisory committee is nearly completed and might be reviewed as soon as the commission’s May 8 working session. Also, a consultant’s report on a zoning ordinance reorganization effort known as ZORO will be presented to planning commissioners in the coming weeks. Rampson told commissioners that the consultant described Ann Arbor’s current zoning ordinances as some of the worst he’s seen – complex, convoluted, and conflicting.

After being briefed on upcoming topics at an April 10 working session, planning commission chair Eric Mahler quipped, “The days of the marathon meetings are back.” Commissioner Diane Giannola gave this advice to the newer commissioners: “Come prepared with snacks.”

At least one new member will be joining the commission this summer. Following the April 17 regular meeting, commissioner Erica Briggs told The Chronicle that because of other time commitments, she would not be seeking reappointment when her term ends this July. She said she wanted to alert others who might be interested in applying for the position. [Full Story]

Allen Creek Preschool Plan OK’d

A site plan for the Allen Creek Preschool, located at 2350 Miller Ave., was recommended unanimously for approval by the Ann Arbor planning commission at its April 17, 2012 meeting. The commission also granted a special exception use for the project.

The project entails building a one-story, 929-square-foot addition onto the west end of an existing 3,111-square-foot preschool building, for a new total of 4,040 square feet. The preschool has an agreement with the Korean Methodist Church at 1526 Franklin Street to use eight parking spaces at the church lot. On-street parking is available on Miller Avenue and Franklin Street.

The special exception use is required because the project is located on a site zoned R1C (single-family dwelling district). According to a staff memo, the … [Full Story]

Tim Hortons Plan Gets Council Approval

At its April 16, 2012 meeting, the Ann Arbor city council unanimously approved a site plan for a new Tim Hortons restaurant at 3965 S. State St. The site plan had received a unanimous recommendation for approval by the Ann Arbor planning commission at its March 6, 2012 meeting. The site is located on the east side of the street, near the intersection of State and Ellsworth.

The plan calls for demolishing a vacant building on the 2.23-acre site where previous restaurants, including Enzo’s and Gallagher’s, were located. In its place, a one-story 1,953-square-foot restaurant with drive-thru facilities would be built on a 1.18-acre site divided from the current parcel. The building would face West Ellsworth and use an existing shared drive on South … [Full Story]

Les Voyageurs Site Plan OK’d by Council

At its April 2, 2012 meeting, the Ann Arbor city council unanimously approved the site plan for a renovation to the Habe Mills Pine Lodge, owned by the Society of Les Voyageurs.

The site had also required a rezoning, which the city council had approved at its March 19, 2012 meeting.

The property owned by the society, at 411 Long Shore Drive near Argo Pond, had been previously zoned public land, even though it’s owned by a private entity. The council approved the rezoning as a planned unit development (PUD), which allowed the group to build a a 220-square-foot, one-story addition to the rear of the existing lodge, on its east side. The site plan for that addition was the subject of the council’s April 2 … [Full Story]

Noodles Site Plan Gets Council OK

At its April 2, 2012 meeting, the Ann Arbor city council gave unanimous approval to a site plan for a new Noodles & Co. restaurant at 2161 W. Stadium Blvd. – site of the former Sze-Chuan West, a building adjacent to Bell’s Diner and Stadium Hardware.

The proposal calls for demolishing the existing 4,300-square-foot restaurant and building a new 2,679-square-foot one-story restaurant with a 615-square-foot enclosed patio at the front of the building. The 1.15-acre site is located on the west side of West Stadium, south of Liberty. The project would also reconfigure the existing parking lot and provide additional landscaping.

The planning commission had given a unanimous recommendation for approval at its March 6, 2012 meeting.

This brief was filed from the city council’s chambers … [Full Story]

Maple Cove Site Plan Gets Planning OK

On a 6-2 vote, the site plan for the Maple Cove Apartments development was recommended for approval by the Ann Arbor planning commission at its March 20, 2012 meeting. The project is located on 2.96 acres at 1649 N. Maple, north of Miller Road between North Maple and Calvin Street on the city’s west side. Voting against the project were Bonnie Bona and Eric Mahler. The project will now be considered by the city council for approval.

The plan calls for combining two sites – 1649 N. Maple and 1718 Calvin – and demolishing an existing single-family home and detached garages there. Two 3-story apartment buildings would be built with a 64-space parking lot and eight bike spaces. The project also includes building … [Full Story]

AAA Project Gets Planning Group OK

A site plan and rezoning for two Main Street parcels owned by the Automobile Club of Michigan – where an AAA branch is currently located – were recommended for approval by the Ann Arbor planning commission at its March 6, 2012 meeting.

The requests relate to 1100 and 1200 S. Main, across from Michigan Stadium. An AAA branch built in the 1950s is located there. The owner wants to build a new branch on a different part of the site, tear down the existing building, and reconfigure parking spaces.

The two parcels are part of a 1.5-acre site containing four parcels owned by AAA and all zoned O (office). Located on the 1200 S. Main parcel is the current one-story branch building with … [Full Story]

Planning Group OKs State St. Tim Hortons

A site plan for a new Tim Hortons restaurant at 3965 S. State St. was unanimously recommended for approval by the Ann Arbor planning commission at its March 6, 2012 meeting. The site is located on the east side of the street, near the intersection of State and Ellsworth.

The plan calls for demolishing a vacant building on the 2.23-acre site where previous restaurants, including Enzo’s and Gallagher’s, were located. In its place, a one-story 1,953-square-foot restaurant with drive-thru facilities would be built on a 1.18-acre site divided from the current parcel. The building would face West Ellsworth and use an existing shared drive on South State, as well as a relocated drive onto West Ellsworth. An outdoor seating area is proposed on the … [Full Story]

Site Plan for Noodles Restaurant OK’d

A plan for a new Noodles & Co. restaurant at 2161 W. Stadium Blvd. – site of the former Sze-Chuan West, a building adjacent to Bell’s Diner and Stadium Hardware – received a unanimous recommendation of approval from the Ann Arbor planning commission at its March 6, 2012 meeting. The plan will be forwarded to the city council for approval.

The proposal calls for demolishing the existing 4,300-square-foot restaurant and building a new 2,679-square-foot one-story restaurant with a 615-square-foot enclosed patio at the front of the building. The 1.15-acre site is located on the west side of West Stadium, south of Liberty. The project would also reconfigure the existing parking lot and provide additional landscaping.

The site plan approval would be contingent on a … [Full Story]

Lack of Quorum Stymies Planning Meeting

Ann Arbor planning commission meeting (Feb. 23, 2012): The planning commission did not achieve a quorum of members on Thursday evening and therefore could not conduct its full meeting.

Ann Arbor planning commissioners

Ann Arbor planning commissioners and staff talk to high school students in city council chambers on Feb. 23. From left: Wendy Woods, Bonnie Bona, city planner Alexis DiLeo, and Kirk Westphal. (Photos by the writer.)

Five of the nine commissioners are needed for a quorum to conduct business, and only four attended. In addition to those four, about 10 people showed up for the two main action items on the agenda, and several high school students were attending as part of a class assignment.

After waiting about 30 minutes, vice chair Kirk Westphal and Wendy Rampson, head of the city’s planning staff, conferred and decided to hear public commentary. One person spoke. John Chamberlain, an attorney representing the Automobile Club of Michigan, came to the podium only to say that he and his team would return for the commission’s next meeting, on March 6.

The club wants to tear down its existing AAA branch near Michigan Stadium and build a new one, and was requesting approval for a site plan. The other main action item on Thursday’s agenda was site plan approval to build a new Noodles restaurant on West Stadium Boulevard, at the location of the former Sze-Chuan West. Both projects will be considered at the planning commission’s March 6 meeting. [Full Story]

Ann Arbor Adds Flashers, Alters Traffic Law

Ann Arbor city council meeting (Dec. 19, 2011): At its last meeting of the year, the council ended the current round of discussion on the city’s pedestrian safety ordinance by finalizing changes that clarified conditions under which vehicles are required to stop for people who are trying to cross the street.

Jane Lumm crosswalk ordinance approaching air quotes

Jane Lumm (Ward 2) made air quotes around the word "approaching" as the council discussed the city's ordinance on crosswalks. (Photos by the writer.)

The current ordinance amendment maintains an existing requirement that motorists accommodate not just pedestrians who are “within” a crosswalk, but also those who are verging on entering a crosswalk. What’s different is the way the concept is expressed. In July 2010, the council chose to describe pedestrians who are about to enter a crosswalk as “approaching” the crosswalk. The version of the ordinance finalized on Dec. 19 requires motorists to accommodate “… a pedestrian stopped at the curb, curb line or ramp leading to a crosswalk and to every pedestrian within a crosswalk …”

As part of the previous amendments made in 2010, the council also had removed language that specified a half of the roadway where drivers needed to accommodate pedestrians. This time around, the council restored similar language, which reads, “… when the pedestrian is on the half of the roadway on which the vehicle is traveling or when the pedestrian is approaching so closely from the opposite half of the roadway as to be in danger.”

In other crosswalk-related business, the council approved an expenditure of $81,000 to install five rectangular rapid flashing beacons (RRFB) on existing pedestrian islands in the city. Four of the locations are along Plymouth Road, at Georgetown, Traver Village, Beal and Bishop. The fifth location is at Seventh and Washington.

Also at the Dec. 19 meeting, the council ended a long process of review by the city and negotiation with neighbors by approving a change to the zoning of the Hoover Mansion property on Washtenaw Avenue, which University Bank uses as its headquarters. The change will allow University Bank to build 13 new parking spaces on the east side – behind the main building, allowing the bank in accommodate expanded employment.

Towards the end of the council’s meeting, a relatively rare debate unfolded about a mayoral nomination to a city board. At issue was the nomination of a city employee – transportation program manager Eli Cooper – to the board of the Ann Arbor Transportation Authority. He’s replacing another city employee on the board, public services area administrator Sue McCormick, who left her position with the city in mid-December. In the end, Cooper’s nomination was confirmed with dissent from two councilmembers. A separate vote on a general policy opposing nominations of city employees to boards and commissions received only four votes of support.

The council considered two compensation-related issues – one for its city attorney, Stephen Postema, and another for election workers who staff the polls. After a closed session to discuss Postema’s performance review, the council voted with dissent from one councilmember to award Postema the ability to cash out 250 hours of banked time. The council delayed its vote on pay increases for election workers, on the possibility that their pay could be increased more than what’s proposed, to match the amount specified in the city’s living wage ordinance.

In other business, the council approved a bond re-funding, authorized reimbursement for a broken electromagnet at the materials recovery facility, accepted additional federal money for solar projects, and heard about a possible strategy for addressing vacant and dilapidated properties. [Full Story]

Traver Village Site Plan Approved

Ann Arbor planning commission meeting (Dec. 20, 2011): With four of the city’s nine planning commissioners absent, the last meeting of the year was brief, with only one action item: site plan approval for changes at Traver Village.

Earl Ophoff, Jeff Kahan

From left: Earl Ophoff of Midwestern Consulting talks with Jeff Kahan of the city's planning staff about proposed changes at Traver Village. (Photos by the writer.)

The owner, First Martin Corp., plans to reconfigure retail space that the Blockbuster video store previously occupied, at the southern part of the complex near Plymouth Road, converting it into three smaller retail spaces.

Plans call for adding a new 25-space parking lot to serve that location, between the south side of the building and Plymouth. Elsewhere within the complex, 128 parking spaces will be removed – primarily in the northwest area behind the Kroger grocery. More bike spaces and landscaping are part of the plan as well, which was approved unanimously by commissioners after brief discussion. It will now be forwarded to the city council for consideration.

Communications during the 30-minute meeting included a reminder of a series of public forums on sustainability starting early next year. The first one, on Thursday, Jan. 12, will feature a panel of city staff on the topic of resource management. All forums will be held at the Ann Arbor District Library’s downtown building, 343 S. Fifth Ave., beginning at 7 p.m. It’s part of a broader sustainability initiative that began earlier this year, funded by a Home Depot Foundation grant. [Full Story]

Planning Group OKs Arbor Hills Site Plan

At its Oct. 18, 2011 meeting, the Ann Arbor planning commission recommended approval of the site plan for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw. Action had been postponed at the commission’s June 7, 2011 meeting so that the developer – Campus Realty – could address some outstanding issues with the plan.

The project involves tearing down three vacant commercial structures and putting up four one- and two-story buildings throughout the 7.45-acre site – a total of 90,700-square-feet of space for retail stores and offices. Three of the buildings would face Washtenaw Avenue, across the street from the retail complex where Whole Foods grocery is located. The site would include 310 parking spaces.

According to city planning … [Full Story]

Despite Concerns, The Varsity Moves Ahead

Ann Arbor planning commission meeting (Oct. 4, 2011): At a meeting that started later than usual to accommodate the dedication of city hall’s new Dreiseitl water sculpture, planning commissioners approved two projects that had previously been postponed.

Stephen Ranzini at sculpture dedication

Stephen Ranzini looks up at the water sculpture by Herbert Dreiseitl, during a public reception and dedication for the piece at city hall on Tuesday evening. Ranzini, president of University Bank, later attended a planning commission meeting inside city hall, where he told commissioners that No Parking signs are ugly. It's not clear what he thought about the sculpture.

Changes to a University Bank site plan for property at 2015 Washtenaw Ave., known as the Hoover Mansion, were approved unanimously, despite some concerns voiced by neighbors during a public hearing on the proposal. The changes – which primarily relate to creation of a new parking lot – required amending the supplemental regulations of the site’s planned unit development (PUD) zoning district originally approved in 1978.

Also back for review was The Varsity, a proposed “planned project” consisting of a 13-story apartment building with 181 units at 425 E. Washington, between 411 Lofts and the First Baptist Church. Intended for students, it’s the first project to go through the city’s new design review process. Only minor changes had been made since the proposal was first considered at the planning commission’s Sept. 20 meeting.

Fourteen people spoke during a public hearing on The Varsity, including several residents of the nearby Sloan Plaza who raised concerns about traffic at the Huron Street entrance, as well as aesthetic issues with the building’s facade facing Huron. The project was supported by a paster pastor at the First Baptist Church and the head of the State Street merchant association.

In addition to public hearings held on these two projects, one person spoke during public commentary at the start of the meeting. Rick Stepanovic told commissioners that he’s a University of Michigan student, and that Wendy Rampson – head of the city’s planning staff – had spoken to one of his classes last year. Among other things, she’d mentioned the city’s need for more student input, he said. Since then he’s been elected to the Michigan Student Assembly, and was offering to provide that input, either as a resident – he lives in the neighborhood near Packard and Hill – or by taking an issue back to MSA for broader student feedback.

Stepanovic indicated his intent to attend future planning commission meetings, but noted that MSA meetings are held at the same time – on Tuesday evenings. [Full Story]

The Varsity Prompts Design, Traffic Concerns

Ann Arbor planning commission meeting (Sept. 20, 2011): Commissioners handled one major agenda item at its most recent meeting: A site plan proposal for The Varsity Ann Arbor on East Washington.

Site of the proposed 13-story Varsity apartments

Site of proposed 13-story The Varsity Ann Arbor, at 425 E. Washington, where a two-story office building is now located. To the left is 411 Lofts. To the right is the entrance to the First Baptist Church parking lot. (Photos by the writer.)

The Varsity is a 13-story apartment building proposed for 425 E. Washington St., east of the 411 Lofts building and west of the First Baptist Church. Currently on the site is a two-story office building that formerly housed the Prescription Shop. The proposed 177,180-square-foot apartment building would include 181 apartments with a total of 415 bedrooms, to be marketed to university students.

Four residents spoke during a public hearing on the project, and were generally supportive. However, they cited concerns over the attractiveness of the facade facing Huron Street and traffic issues that might arise from that entrance. Some commissioners also raised issues about parking and design, and wondered about the possibility of retail space on the first floor. The developer’s representatives felt retail wasn’t feasible at this time.

City planning staff recommended that site plan approval be postponed, so that some relatively minor issues could be resolved. Commissioners followed that advice, and postponed action on the project. It’s expected to be on the agenda again for the commission’s Oct. 4 meeting.

In addition to The Varsity, Tuesday’s meeting included several communications from staff and commissioners. Wendy Rampson, head of the city’s planning staff, reported that a Sept. 21 meeting of the R4C/R2A advisory committee had been postponed and will be rescheduled. City planning staff had heard from several committee members who felt they needed more information before reconvening. The advisory group is developing recommendations for zoning changes in Ann Arbor’s near-downtown residential neighborhoods.

Tony Derezinski, a commissioner who also serves on city council, reported on planning-related items that emerged at the council’s Sept. 19 meeting. He noted that although it wasn’t on the council’s agenda or discussed publicly, the issue of the City Place apartment complex, which is poised to break ground in the coming weeks, was “quietly being discussed” among councilmembers, he said. While it looks like the project will move forward and that an alternative project on that site called Heritage Row won’t be realized, Derezinski said – somewhat cryptically – there’s “many a slip twixt the cup and the lip.”  [Full Story]

Site Plan for Former Frank’s Nursery OK’d

At its Aug. 16, 2011 meeting, the Ann Arbor planning commission recommended approval of the site plan for 3590 Washtenaw Ave., at the southwest corner of Washtenaw Avenue and Yost Boulevard. The plan calls for building a 9,500-square-foot, single-story addition to the existing 15,769-square-foot retail building that currently houses the Dollar Tree. The new space is designated for an additional tenant. The plan would require approval by the Ann Arbor city council.

The building addition would replace an existing unenclosed canopy area used by the former tenant, Frank’s Nursery. The site is part of a larger retail center along Washtenaw Avenue that consists of five parcels with the same owner. The site plan includes construction of a new public sidewalk in … [Full Story]

Approval Postponed on Arbor Hills Crossing

Ann Arbor planning commission meeting (June 7, 2011): The main action item on the planning commission’s agenda was a resolution to approve the site plan for Arbor Hills Crossing, a proposed retail and office complex at Platt and Washtenaw.

A rendering of Arbor Hills Crossing at Platt and Washtenaw

A rendering of one of four buildings planned at Arbor Hills Crossing, located on the southeast corner of Platt and Washtenaw. This view is looking northwest from the center of the site. (Image by ReFORM Studios)

The project involves tearing down several vacant structures and putting up four one- and two-story buildings throughout the 7.45-acre site – a total of 90,700-square-feet of space for retail stores and offices. Three of the buildings would face Washtenaw Avenue, across the street from the retail complex where Whole Foods grocery is located. The site is also directly north of the new location for Summers-Knoll School. Planning commissioners had approved the Summers-Knoll project at their May 17 meeting.

Comments from commissioners about Arbor Hills Crossing ranged from disappointment in the lack of density to concerns about pedestrian safety. Commissioners generally expressed the sense that they were glad to see the site developed.

Citing some outstanding issues, planning staff recommended postponing action on the plan. Several commissioners raised other issues they’d like to see addressed before the site plans come back to the commission for approval. Among those issues: future plans for bike lanes along Washtenaw Avenue, as identified in the city’s non-motorized transportation plan; and possible pedestrian access to a wetland area. The vote to pospone was unanimous.

Later in the meeting, planning manager Wendy Rampson got feedback on a draft memo to Pittsfield Township, providing input from the commission on the township’s draft master plan. In part, the memo states an objection to the township’s description of itself as “providing an Ann Arbor mailing address while placing a much lower tax burden on businesses.” The memo points out that the plan could be improved by emphasizing regional cooperation. [Full Story]

Arbor Hills Crossing Site Plan Postponed

At its June 7, 2011 meeting, the Ann Arbor planning commission postponed action on site plan approval for Arbor Hills Crossing at 3100 Washtenaw Avenue. The  property at the southeast corner of Washtenaw and Platt is owned by Campus Realty. The plan calls for demolishing several commercial buildings and constructing a 90,700-square-foot retail and office center with four buildings and 310 parking spaces on a 7.45-acre site. Retail space would primarily include smaller stores that would be visible from Washtenaw Avenue.

The city’s planning staff recommended postponement, citing several unresolved issues: (1) a formal decision from the Michigan Dept. of Transportation (MDOT) regarding a traffic signal at the Washtenaw/Platt intersection; (2) approval from the Washtenaw County water resources commissioner; and (3) resolving issues related … [Full Story]

Ann Arbor Council OKs Packard Square

At its May 2, 2011 meeting, the Ann Arbor city council voted to approve the site plan and development agreement, as well as the brownfield redevelopment plan, for the Packard Square development, located at the site of the former Georgetown Mall. The development would include 230 apartment units, 23,790 square feet of retail space, 454 parking spaces and stormwater detention facilities.

At its March 15 meeting, the Ann Arbor city planning commission had unanimously recommended approval of the Packard Square site plan. [Chronicle coverage: "Packard Square, Fraternity Site Plan OK'd"]

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link] [Full Story]

Near North PUD Revisions OK’d

At its April 19, 2011 meeting, the Ann Arbor city council authorized revisions to the elevations of the Near North PUD affordable housing development on North Main Street. The city council originally approved rezoning for the project – a four-story, 39-unit mixed use residential building on a 1.19-acre site – on Sept. 21, 2009.

The changes include modification of the locations where the exterior materials – glazing, panelized exterior cladding materials, plus accent materials – will be used. Roof lines have also been proposed, but the building is still under the maximum height permitted. The changes, which were prompted by alterations to the interior layout of the building, were presented to the surrounding neighbors at a meeting on March 17, 2011.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron. A more detailed report will follow: [link] [Full Story]

Residential Site Plan for Former Bindery OK’d

At its April 19, 2011 meeting, the Ann Arbor city council unanimously approved a site plan for 215 N. Fifth Ave. – formerly the site of the Bessenberg Bindery, which has moved to the Thomson-Shore Inc. facility in Dexter. The Fifth Avenue property is now owned by Jon and Lisa Rye. Jon Rye, a University of Michigan alumnus, is president and chairman of Greenfield Partners and Greenfield Commercial Credit, both located in Bloomfield Hills.

The plan calls for tearing down the one-story building and constructing a two-story, single-family, owner-occupied house with an attached two-car garage. The entrance will be oriented to the north, and the garage will be accessed from the public alley on the west side of the site. The site is directly north of the Armory condos and south of a two-story residential rental property.

The project requires a site plan because the single-family house is on property that’s not zoned solely for residential purposes. It’s zoned D2 (downtown interface) and is located in the Old Fourth Ward Historic District. The Ann Arbor historic district commission already reviewed the site plan and issued a certificate of appropriateness at its Feb. 10, 2011 meeting. The Ann Arbor city planning commission had given its recommendation for approval of the site plan at its March 15, 2011 meeting.

This brief was filed from the city council’s chambers on the second floor of city hall, located at 301 E. Huron St. A more detailed report will follow: [link] [Full Story]

Packard Square, Fraternity Site Plans OK’d

Ann Arbor planning commission meeting (March 15, 2011): Commissioners spent more than 90 minutes on Tuesday discussing a project that could transform the site of the former Georgetown Mall, which has been sitting vacant for well over a year.

Eric Mahler

Eric Mahler, chair of the Ann Arbor planning commission. He cautioned developers of Packard Square not to try to undersell the size of their project. (Photos by the writer.)

Despite concerns raised by some commissioners, as well as residents who spoke during a public hearing, the planning commission ultimately voted to recommend approval of the site plan and development agreement for Packard Square, a complex off of Packard Street. The plan calls for 230 apartments and 23,790-square-feet of retail space in a single building.

The commission also recommended approval of two other site plans: (1) at 630 Oxford, between South University and Hill, where the University of Michigan chapter of Phi Kappa Psi plans to convert a rental duplex  into a fraternity house for up to 24 occupants; and (2) at 215 N. Fifth, where owners want to tear down the former Bessenberg Bindery building and construct a two-story, single-family house.

All votes were unanimous. The three site plans will now be considered by the Ann Arbor city council for final approval. [Full Story]

House Plan OK’d at Former Bindery Site

The Ann Arbor planning commission, at its March 15, 2011 meeting, unanimously recommended approval of a site plan for a single-family house at 215 N. Fifth Ave. – formerly the site of the Bessenberg Bindery, which has moved to the Thomson-Shore Inc. facility in Dexter. The plan calls for tearing down the building and constructing a two-story, single-family, owner-occupied house with an attached two-car garage. The garage will be accessed from the public alley on the west side of the site. Architect Dick Mitchell was on hand to describe the design.

The project requires a site plan because the single-family house is on property that’s not zoned solely for residential purposes. It’s zoned D2 (downtown interface) and is located in the Old Fourth Ward Historic District. The Ann Arbor Historic District Commission has already reviewed the site plan and issued a certificate of appropriateness at its Feb. 10, 2011 meeting. The project will next be voted on by city council for final approval.

This brief was filed from the boardroom in the Washtenaw County administration building, where the planning commission is meeting due to renovations in the city hall building. A more detailed report will follow. [Full Story]

Site Plan Approved for Phi Kappa Psi

At their March 15, 2011 meeting, the Ann Arbor planning commission unanimously approved a site plan and a special exception use for a property at 630 Oxford, between South University and Hill. The University of Michigan chapter of Phi Kappa Psi plans to convert a rental duplex – which now allows for up to eight occupants – into a fraternity house for up to 24 occupants. The plan calls for a rear parking lot with eight spaces, plus an enclosed area for bikes. The commission had postponed the item at its Jan. 20, 2011 meeting, in order for the fraternity to make revisions to the plan as requested by city planning staff. The site plan will be forwarded to the city council for final approval.

This brief was filed from the boardroom in the Washtenaw County administration building, where the planning commission is meeting due to renovations in the city hall building. A more detailed report will follow. [Full Story]

Council Approves Avalon’s Pauline Plan

At its Feb. 22, 2011 meeting, the Ann Arbor city council approved the site plan for an Avalon Housing project at 1500 Pauline Blvd. that would construct 32 dwelling units and 39 surface parking spaces. The plan includes demolition of four existing apartment buildings containing 48 units. The new construction would include six new buildings totaling 53,185 square feet. Five of the buildings would include one-, two- and three-bedroom apartments and three-bedroom townhomes. The sixth building would be a community center with a playground.

Estimated cost of the project is $8 million. That cost includes an upfront developer’s fee of 15% – typical for nonprofit projects like this – as well as costs associated with relocating current residents and paying for their housing at an alternative site for up to five years, as mandated by federal law under the Uniform Relocation Assistance and Real Property Acquisition Policies Act.

Avalon expects to fund the project through a combination of sources, including Low Income Housing Tax Credits, HOME program subsidy (HUD funds allocated through the Michigan State Housing Development Authority and the Washtenaw Urban County), the Federal Home Loan Bank, and private loan funds.

The proposal complies with the site’s R4B zoning. The city’s planning commission approved the site plan at its Jan. 20, 2011 meeting on a 7-0 vote.

This brief was filed from the boardroom in the Washtenaw County administration building, where the council is meeting due to renovations in the city hall building. A more detailed report will follow: [link] [Full Story]

Ann Arbor Council OKs Lake Trust Site Plan

At its Jan. 18, 2011 meeting, the Ann Arbor city council approved a site plan request from Lake Trust Credit Union. The credit union plans to construct a new building at the southeast corner of West Liberty and West Stadium Boulevard.

The project had previously won site plan approval at the planning commission’s Sept. 21, 2010 meeting. The project includes demolishing the existing structure and constructing a new one-story, 3,686-square-foot building. The planning staff recommended approval of the site plan. No one spoke during the planning commission’s public hearing on the proposal. On that occasion, the project received two dissenting votes from the planning commission, from commissioners Bonnie Bona and Erica Briggs.

This brief was filed from the boardroom in the Washtenaw County administration building, where the council is meeting due to renovations in the city hall building. A more detailed report will follow: [link] [Full Story]

Site Plan Filed for Fuller Road Station

The cardboard box sat on the counter of the Ann Arbor planning department’s sixth floor city hall offices, stuffed with copies of the Fuller Road Station site plan, which was submitted to the city Monday morning.

Copies of the site plan for Fuller Road Station

Multiple copies of the site plan for Fuller Road Station were filed this morning with the city's planning department. The hand in the photo belongs to Matt Kowalski of the city's planning staff. (Photos by the writer.)

The submission of the site plan – 44 oversized pages of details about the project’s engineering, architecture and landscaping – marks the start of the formal approval process with the city, after months of debate and discussion. The $46 million project is proposed for city-owned property south of Fuller Road and north of the University of Michigan medical campus. The site plan is for the first phase of the project – a five-level parking structure and bus depot. Officials envision that a later phase will include a station for commuter and high-speed rail, though funding for that is still uncertain.

Jeff Kahan, the city planner who’ll be shepherding the project through the approval process, told The Chronicle that it will be on the planning commission’s agenda no earlier than Sept. 21. [Full Story]

AHP Zoning Revisions Go to City Council

Ann Arbor Planning Commission meeting (July 8, 2010):  The 4th of July holiday caused some reshuffling of city meeting times and locations, and sent planning commissioners to the Ann Arbor District Library on Thursday night to conduct their business.

Wendy Rampson, Eric Mahler

Wendy Rampson, head of the city's planning staff, and Eric Mahler, newly elected chair of the Ann Arbor planning commission, at the commission's July 8, 2010 meeting. (Photos by the writer.)

That business included approval of revised area, height and placement (AHP) standards that have been under review for more than two years. The revisions have pulled back from some of the original proposals – for example, there’s no longer an uncapped building height in certain districts. It’s the first significant overhaul of these standards in roughly 50 years, with the goal of reflecting prevailing community values. The recommendations will now be forwarded to city council for final approval.

The planning commission also voted to postpone action on a project at the Kroger on South Maple. The grocery is adding a drive-thru pharmacy, and needs city approval to reconfigure its parking lot to accommodate the drive-thru lane. A few unresolved issues led commissioners to push back consideration until their July 20 meeting.

And the commission elected a new slate of officers, with local attorney Eric Mahler replacing architect Bonnie Bona as chair. [Full Story]

Heritage Row Vote Likely Delayed

On the published agenda for Monday’s June 7 council meeting are public hearings on two different site plans – Heritage Row and a planned project at Glacier Hills. Public hearings such as these are required to be published in a newspaper of general circulation one week before they take place.

WLNJune32010

From the June 3, 2010 edition of the Washtenaw Legal News, the published notice of the June 7, 2010 Glacier Hills and Heritage Row site plan public hearings. (Image links to wider view and higher resolution file.)

In a phone interview on Friday, city clerk Jackie Beaudry confirmed for The Chronicle that an email sent by the Ann Arbor city clerk’s office to the Detroit News – requesting publication of the notices for Sunday, May 30 – was not received by The News. Due to the Memorial Day holiday, the city clerk’s staff did not learn of the communication snafu until Tuesday. That was not in time to meet the publication requirement for the June 7 public hearings.

As a result, no vote is now expected on the site plans for those two projects at Monday’s June 7 city council meeting. The notice of public hearings for those projects, Beaudry said, was published in the June 3 edition of the Washtenaw Legal News. Those WLN notices in the June 3 edition still specify the site plan public hearings for June 7, but indications from inside city hall are that if when the hearings are opened on June  7, they’ll be left open and continued through the council’s June 21 meeting, when a vote will be taken on the site plans as well as the Heritage Row rezoning.

The zoning change for the Heritage Row project, which is considered separately from the site plan by the council and is given a separate public hearing, was properly noticed, Beaudry told The Chronicle. How can one of the public hearings receive proper notice, but the other one not, when they’re part of the same project? [Full Story]

Planning Commission: A Matter of Timing

Ann Arbor City Planning Commission (June 1, 2010): City planning commissioner Evan Pratt’s garden doesn’t have any deadlines attached to the work he does in it. So there might not be any corn this year, he says.

rain-planning-commission-deadlines

Mike Rein of Bowers + Rein spoke to the Ann Arbor city planning commission in opposition to eliminating time deadlines for planning commission and city council review of site plan submissions. (Photos by the writer.)

He was illustrating why he thought deadlines in the approval process for site plans and other petitions were a good idea.

But Pratt was the lone dissenter on the commission, which recommended that deadlines in the city’s zoning code be replaced with a standard of “reasonable time.”

The current deadlines apply to two different stages of site plan reviews. The first is the maximum time between the planning commission’s receipt of a report from city staff and the commission’s recommendation – 60 days. The second stage is the time between the planning commission’s recommendation and city council action – 30 days. The commission voted to recommend replacement of the deadlines with language that refers to a “reasonable” time.

Currently, if the bodies do not act within the prescribed time parameters, site plan petitions are considered to be recommended or approved automatically – by default. At its Tuesday meeting, the automatic approval language was recommended to be dropped from the city code.

The code changes regarding timing would now need city council approval in order to take effect.

The timing issue joins two other technical revisions to the city’s zoning code, which the planning commission voted to recommend at its previous meeting. Those revisions involve fee reimbursements associated with applications and a requirement that up-to-date drawings for site plans be publicly accessible 24/7 for a week prior to public hearings.

At Tuesday’s meeting, the commission also heard a presentation from the city’s environmental coordinator, Matt Naud, on the city’s environmental indicators. Part of the background of the presentation was a recent joint meeting of the city’s planning, energy and environmental commissions that focused on sustainability. [Full Story]