Council OKs Mack Pool Roof Replacement

A roof replacement has been approved for the city of Ann Arbor’s Mack indoor pool, located within the Ann Arbor Open school near the corner of Miller and Brooks. The action came at the city council’s June 3, 2013 meeting.

At its May 21, 2013 meeting, the Ann Arbor park advisory commission had recommended awarding a contract to Pranam GlobalTech Inc. for $193,000 to cover the roof replacement and painting refurbishment. A 10% construction contingency brings the project’s budget to $212,300.

Pranam provided the lowest of two bids. The other bidder was Wm. Molnar Roofing Co. Inc., which bid $271,319 for the work. Pranam was previously selected to replace the roof at Veterans Memorial Park Ice Arena. The contract for that project was approved by the city council at its May 20, 2013 meeting.

According to parks staff, the existing roof from the early 1990s was expected to last just 15 years. There are leaks and rusted steel lintels and joists, which need to be replaced. The project also includes removing rust and painting the pool ceiling and joists.

Funding for the project is available from two sources: (1) $186,088 from the fund balance of the parks maintenance and capital improvements millage; and (2) $26,212 from the Ann Arbor Public Schools, which pays annually into a capital facilities escrow account earmarked for Mack Pool.

The work will be done in June and July, while school is out of session. The pool is not open during the summer months